Permit: DP16-0206

Parcel: 10321025H

Inspection Status: Passed

Inspection History: SITE - Stormwater Follow-up

Permit Number - DP16-0206

Inspection Description - SITE - Stormwater Follow-up

Inspection Status - Passed

Date Description Inspector Results Comments
05/07/2018 SITE - Stormwater Follow-up MRUSSO Approved Entered by DROBERT5 -
04/18/2018 SITE - Stormwater Follow-up DROBERT5 Continued Entered by DROBERT5 - NO CONCERNS AT THIS TIME.
01/26/2018 SITE - Stormwater Follow-up MRUSSO Continued Entered by DROBERT5 - 1) SITE IS UNDER AN AZPDES PERMIT AND SWPPP UNTIL THE SITE IS STABILIZED PER THE APPROVED PLANS. 2) ENSURE SEDIMENT CONTROLS ARE MAINTAINED THROUGHOUT CONSTRUCTION. 3) CONTINUE TO SWEEP UP TRACKED SOIL ROUTINELY
09/29/2017 SITE - Stormwater Follow-up MRUSSO Continued Entered by DROBERT5 - 1) LOOKED AT LAST CATCH BASIN INSTALL AND PIPE TRANSITION. OK TO COVER 2) SWEEP UP TRACKED SOIL OFF SILVERBELL 3) RE-ESTABLISH YOU STABILIZED CONSTRUCTION ENTRANCE
09/14/2017 SITE - Stormwater Follow-up MRUSSO Continued Entered by DROBERT5 - 1) LOOKED AT CATCH BASIN INSTALL ALONG E SIDE OF SITE AT SRP TIE-IN, GROUT OK, OK TO COVER - PICS TAKEN 2) ENSURE YOUR STABILIZED CONSTRUCTION ENTRANCE IS MAINTAINED THROUGHOUT CONSTRUCTION 3) MAINTAIN PERIMETER SEDIMENT CONTROLS AS NEEDED 4) PERFORM STORM WATER SELF INSPECTIONS AND DOCUMENT THEM
08/23/2017 SITE - Stormwater Follow-up MRUSSO Continued Entered by DROBERT5 - 1) PROGRESS CHECK OF INSTALL OF 24"SRP AND PRE-CAST CATCH BASINS 2) TOOK PICTURES OF SET CATCH BASINS AND GROUTING OF PIPE - OK 3) TOOK PICTURES OF DRAINAGE CHANNEL PROGRESS ALONG THE EAST SIDE 4) SWEEP UP TRACKED SOIL 5) ENSURE SAFETY RAILING ALONG RET/DET BASIN AND DRAINAGE CHANNEL IS ADDRESSED
08/14/2017 SITE - Stormwater Follow-up MRUSSO Continued Entered by DROBERT5 - 1) SWEEP UP TRACKING OFF OF PUBLIC ROADWAY. 2) RE-ESTABLISH STABILIZED CONSTRUCTION ENTRANCE. 3) SITE IS SATURATED AND CONCRETE WORK HAS BEEN POSTPONED
08/09/2017 SITE - Stormwater Follow-up MRUSSO Continued Entered by DROBERT5 - 1) SEDIMENT CONTROLS ARE IN PLACE ALONG THE NORTH SIDE OF THE SITE; HOWEVER STORM WATER REG WILL CHANGE AS CONSTRUCTION ADVANCES 2) LOOKED AT A SECTION OF STORM CHANNEL ALONG EAST SIDE OF SITE - SHOTCRETE THIS WEEK 3) CALL FOR RE-INSPECTIOBN PRIOR TO COVERING STORM PIPE AND CATCH BASINS
08/03/2017 SITE - Stormwater Follow-up MRUSSO Continued Entered by DROBERT5 - 1) INSTALL OF 24' RCP ALONG NORTH SIDE OF SITE 2) ENSURE COMPACTION AND BEDDING OF PIPE PER MANUFACTURER SPECS 3) CALL FOR RE-INSP PRIOR TO COVER OF PIPE PICS TAKEN 4) ENSURE SWPP IS INSTALLED PER YOUR PLAN