Permit: DP16-0206

Parcel: 10321025H

Inspection Status: Passed

Inspection History: ENGR Grading Final

Permit Number - DP16-0206

Inspection Description - ENGR Grading Final

Inspection Status - Passed

Date Description Inspector Results Comments
04/30/2018 ENGR Grading Final MRUSSO Approved Entered by DROBERT5 -
04/18/2018 ENGR Grading Final DROBERT5 Continued Entered by DROBERT5 - THE ENTRANCE WILL BE MODIFIED BY THE ENGINEER OF RECORD DUE TO INCORRECT ASBUILT GRADES.
05/07/2018 ENGR Grading Final MRUSSO Approved Entered by DROBERT5 -
04/30/2018 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - NO SIGNIFICANT CHANGES OR CONCERNS AT THIS TIME
04/20/2018 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - PROGRESS INSPECTION ON PAVING, NO CONCERNS AT THIS TIME
04/18/2018 ENGR Grading Final DROBERT5 Continued Entered by DROBERT5 - CREWS ARE WORKING ON THE STRUCTURES ON THIS SITE, AND ARE PAVING THE INTERNAL ROADWAYS ADJACENT TO BUILDINGS 4 THROUGH 9, THE REMAINDER OF THE AREAS WILL BE PAVED TOMORROW.
04/12/2018 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 -
09/29/2017 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - 1) LOOKED AT LAST CATCH BASIN INSTALL AND PIPE TRANSITION. OK TO COVER 2) SWEEP UP TRACKED SOIL OFF SILVERBELL 3) RE-ESTABLISH YOU STABILIZED CONSTRUCTION ENTRANCE
09/14/2017 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - 1) LOOKED AT CATCH BASIN INSTALL ALONG E SIDE OF SITE AT SRP TIE-IN, GROUT OK, OK TO COVER - PICS TAKEN 2) ENSURE YOUR STABILIZED CONSTRUCTION ENTRANCE IS MAINTAINED THROUGHOUT CONSTRUCTION 3) MAINTAIN PERIMETER SEDIMENT CONTROLS AS NEEDED 4) PERFORM STORM WATER SELF INSPECTIONS AND DOCUMENT THEM
08/31/2017 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - 1) PROGRESS CHECK FOR SITE 2) PICTURES TAKEN OF CHANNEL AND CATCH BASINS 3) CALL FOR RE-INSPECTION WHEN ADDITIONAL BASINS COME IN FOR INSTALL
08/23/2017 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - 1) PROGRESS CHECK OF INSTALL OF 24"SRP AND PRE-CAST CATCH BASINS 2) TOOK PICTURES OF SET CATCH BASINS AND GROUTING OF PIPE - OK 3) TOOK PICTURES OF DRAINAGE CHANNEL PROGRESS ALONG THE EAST SIDE 4) SWEEP UP TRACKED SOIL 5) ENSURE SAFETY RAILING ALONG RET/DET BASIN AND DRAINAGE CHANNEL IS ADDRESSED
08/17/2017 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - 1) LOOKED AT GROUTED CONNECTION BETWEEN SRP AND CATCH BASIN N. SIDE - OK 2) LOOKED AT RE-BAR LAY OUT AND FORMS FOR SRP TO RCP TRANSITION - OK TO POUR CONCRETE. 3) LOOKED AT PROGRESS OF SHOT-CRETE ALONG DRAINAGE CHANNEL EAST SIDE - OK
08/16/2017 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - 1) INSTALL OF 24" SRP W/ PRECAST CATCH BASIN ALONG NORTH SIDE OF SITE. 2)CONTRSCTOR WILL GROUT CONNECTIONS OF PIPE TO BASIN 3) INSTALL OF TRANSITION FOR SRP TO RCP - RE-BAR WILL BE INSTALLED FOR COLLAR - CALL FOR INSPECTION PRIOR TO CONCRETE.
08/14/2017 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - 1) SWEEP UP TRACKING OFF OF PUBLIC ROADWAY. 2) RE-ESTABLISH STABILIZED CONSTRUCTION ENTRANCE. 3) SITE IS SATURATED AND CONCRETE WORK HAS BEEN POSTPONED
08/09/2017 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - 1) SEDIMENT CONTROLS ARE IN PLACE ALONG THE NORTH SIDE OF THE SITE; HOWEVER STORM WATER REG WILL CHANGE AS CONSTRUCTION ADVANCES 2) LOOKED AT A SECTION OF STORM CHANNEL ALONG EAST SIDE OF SITE - SHOTCRETE THIS WEEK 3) CALL FOR RE-INSPECTIOBN PRIOR TO COVERING STORM PIPE AND CATCH BASINS
08/04/2017 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - 1) CONTINUED INSTALL OF 24" SRP ALONG NORTH SIDE OF SITE. 2) PROVIDE PICTURES OF SHADING OF PIPE TO SPRING LINE PRIOR TO COVER 3) CALL FOR INSPECTION PRIOR TO COVERING PIPE TRANSITION POINTS, CATCH BASINS, MANHOLES, ETC.
08/03/2017 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - 1) INSTALL OF 24' RCP ALONG NORTH SIDE OF SITE 2) ENSURE COMPACTION AND BEDDING OF PIPE PER MANUFACTURER SPECS 3) CALL FOR RE-INSP PRIOR TO COVER OF PIPE PICS TAKEN 4) ENSURE SWPP IS INSTALLED PER YOUR PLAN
05/30/2018 ENGR Grading Final MRUSSO Approved Entered by DROBERT5 -
02/26/2018 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - RE-BAR LAY OUT FOR TRASH ENCLOSURE WALLS. FOOTINGS INSTALLED PER PLAN OK FOR CONCRETE
05/30/2018 ENGR Grading Final MRUSSO Approved Entered by DROBERT5 -
04/03/2018 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - 1) PROGRESS INSPECTION, CONTRCTOR WORKING ON PREP FOR PAVING. INSTALL OF CURBING AND VALLEY GUTTER PER PLAN. 2) CALL FOR INSPECTION FOR RE-BAR LAY OUT FOR TRASH ENCLOSURE PAD