Permit: DP16-0167
Permit Details
Apply Date:
09/20/2016
Applicant:
Lisa Bowers
Description:
SITE/GRADING/SWPPP - STORAGE COMMERCIAL OF VEHICLESOriginally approved 11/3/2016 (9 pages)
Permit Reviews
Permit Number - DP16-0167
Permit Status: Complete
Permit Description: SITE/GRADING/SWPPP - STORAGE COMMERCIAL OF VEHICLESOriginally approved 11/3/2016 (9 pages)
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/20/2016 | DEV PKG - OK TO SUBMIT | 09/22/2016 | COMPLETED |
| 09/22/2016 | DEV PKG | 10/24/2016 | COMPLETED |
| 10/31/2016 | DEV PKG | 11/02/2016 | COMPLETED |
| 11/02/2016 | DEV PKG - RESUBMITTAL | 11/03/2016 | COMPLETED |
Completed Inspections
Permit Status: Complete
Permit Number: DP16-0167
Permit Description: SITE/GRADING/SWPPP - STORAGE COMMERCIAL OF VEHICLESOriginally approved 11/3/2016 (9 pages)
Total Completed Inspections - 9
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/09/2016 | PDSD Engineering Division Pre-Construction SITE | Passed | {Activity date: 11/09/2016; Status: Approved; Inspector: MRUSSO; Comment: Entered by MRUSSO1 - 1) INSTALL SEDIMENT CONTROLS PER YOUR SWPPP 2) INSTALL A STABILIZED CONSTRUCTION ENTRANCE/EXIT 3) POST A COPY OF YOUR NOI 4) INSTALL A CONCRETE WASH OUT ON SITE 5) PERFORM AND DOCUMENT STORM WATER SELF INSPECTIONS PER YOUR SWPPP 6) SWEEP UP TRACKED SOIL OFF OF ADJACENT ROADWAYS ROUTINELY 7) CALL FOR INSPECTION FOR ANY SITE QUESTIONS/CONCERNS 8) NPPO APPROVED} |
|
| 11/17/2016 | SITE - Stormwater Setup and Controls | Passed | {Activity date: 11/17/2016; Status: Approved; Inspector: MRUSSO; Comment: Entered by MRUSSO1 - 1) WADDLE (SILT SOCK) INSTALLED PER PLAN 2) MAY NEED TO ADD SUPPLEMENTAL SEDIMENT CONTROLS ALONG THE WEST SIDE 3) INSTALL A CONCRETE WASH OUT WHEN APPLICABLE 4) ENSURE SELF INSPECTIONS ARE PERFORMED AND DOCUMENTED.} |
|
| 12/21/2016 | SITE - Stormwater Follow-up | Passed | {Activity date: 12/21/2016; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - WALL AROUND SITE, PAVING THIS WEEK} ; {Activity date: 12/12/2016; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME} ; {Activity date: 12/06/2016; Status: Continued; Inspector: MRUSSO; Comment: Entered by MRUSSO1 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME} | |
| 12/21/2016 | ENGR Grading Final | Passed | {Activity date: 12/21/2016; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } | |
| 12/28/2016 | PDSD Site/Engineering Division - NPPO | Passed | {Activity date: 12/28/2016; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } | |
| 12/28/2016 | COT - ENGR - Signage Final | Passed | {Activity date: 12/28/2016; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } | |
| 01/18/2017 | PDSD Site/Engineering Division - Landscaping | Passed | {Activity date: 01/18/2017; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } ; {Activity date: 12/06/2016; Status: Continued; Inspector: MRUSSO; Comment: Entered by MRUSSO1 - NO LANDSCAPING AT THIS TIME} ; {Activity date: 11/09/2016; Status: Continued; Inspector: MRUSSO; Comment: Entered by MRUSSO1 - NPPO IMPLEMENTED PER PLAN} | |
| 01/18/2017 | ENGR Engineering Final | Passed | {Activity date: 01/18/2017; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } ; {Activity date: 12/30/2016; Status: Partial Approval; Inspector: MRUSSO; Comment: Entered by DROBERT5 - PARTIAL APPROVAL FOR FINAL GRADING. PRIOR TO FINANAL GRADING APPROVAL AND ENGINEERING FINAL APPROVAL, COMPLETE ALL SITE/GRADING/LANDSCAPING SHOWN ON THE APPROVED PLANS AND CALL FOR RE-INSPECTION.} ; {Activity date: 12/28/2016; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - COMPLETE ALL SITE WORK PER THE APPROVED PLANS, CALL FOR RE-INSPECTION} |
|
| 01/18/2017 | SITE - Stormwater Final Inspection | Passed | {Activity date: 01/18/2017; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } ; {Activity date: 12/21/2016; Status: Partial Approval; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) ENSURE A (NOT) IS SUBMITTED TO ADEQ WHEN COMPLETED 2) SWEEP SOIL OFF OF ADJACENT STREETS ROUTINELY 3) CLEAN UP OLD STORM WATER SEDIMENT CONTROLS, ( SILT SOCK, SILT FENCE) WHEN CONSTRUCTION COMPLETE} |