Permit Review Detail
Review Status: Completed
Review Details: DEV PKG
Permit Number - DP16-0167
Review Name: DEV PKG
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 10/31/2016 | LBOJORQ1 | START | PLANS SUBMITTED | Completed | |
| 10/31/2016 | SSHIELD1 | ZONING HC | REVIEW | Approved | |
| 10/31/2016 | SSHIELD1 | ADA | REVIEW | Passed | |
| 10/31/2016 | LOREN MAKUS | ENGINEERING | REVIEW | Approved | |
| 10/31/2016 | STEVE SHIELDS | ZONING | REVIEW | Reqs Change | CDRC TRANSMITTAL TO: Development Services Department Plans Coordination Office FROM: Steve Shields - Principal Planner PDSD Zoning Review Section PROJECT: Commercial Storage Lot Development Package (2nd Review) DP16-0167 TRANSMITTAL DATE: October 31, 2016 COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed. Section 3.3.3.G.5.c UDC, An applicant has one year from the date of application to obtain approval of a site plan that complies with zoning and other development requirements in effect at the time of application, unless an ordinance adopted by Mayor and Council during this period states otherwise. A site plan application that has been in review for a period of one year and has not yet been approved is considered denied. To continue the review of a site plan for the property, a new site plan must be submitted that complies with regulations in effect at the time of re-submittal. The new submittal initiates a new one-year review period. One year Expiration date is September 20, 2016. 2-06.4.9.U - Indicate graphically, where possible, compliance with conditions of rezoning. 1. COMMENT: There are not wall elevations provided on the plan. Provide wall elevations per Special Exception condition 9. If you have any questions about this transmittal, please Steve Shields, (520) 837-4956 or Steve.Shields@tucsonaz.gov RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development package |
| 11/02/2016 | TOM MARTINEZ | OTHER AGENCIES | AZ DEPT TRANSPORTATION | Needs Review | |
| 11/02/2016 | ARUIZ1 | LANDSCAPE | REVIEW | Needs Review | |
| 11/02/2016 | ARUIZ1 | TUCSON WATER NEW AREA DEVELOPMENT | REVIEW | Needs Review | |
| 11/02/2016 | LIZA CASTILLO | UTILITIES | TUCSON ELECTRIC POWER | Needs Review | |
| 11/02/2016 | ED ABRIGO | PIMA COUNTY | ASSESSOR | Needs Review | |
| 11/02/2016 | ARUIZ1 | OTHER AGENCIES | PIMA ASSN OF GOVTS | Needs Review | |
| 11/02/2016 | ROBERT YOUNG | PIMA COUNTY | PIMA CTY - DEV REVIEW | Needs Review | |
| 11/02/2016 | ARUIZ1 | UTILITIES | SOUTHWEST GAS | Needs Review | |
| 11/02/2016 | TIM ROWE | PIMA COUNTY | WASTEWATER | Needs Review | |
| 11/02/2016 | ARUIZ1 | OTHER AGENCIES | TUCSON AIRPORT AUTHORITY | Needs Review | |
| 11/02/2016 | JENNIFER STEPHENS | PIMA COUNTY | ADDRESSING | Needs Review | |
| 11/02/2016 | ARUIZ1 | UTILITIES | CENTURYLINK | Needs Review | |
| 11/02/2016 | ARUIZ1 | OTHER AGENCIES | U. S. POST OFFICE | Needs Review | |
| 11/02/2016 | ARUIZ1 | UTILITIES | EL PASO NATURAL GAS | Needs Review | |
| 11/02/2016 | ARUIZ1 | COT NON-DSD | REAL ESTATE | Needs Review | |
| 11/02/2016 | ARUIZ1 | ZONING-DECISION LETTER | REVIEW | Needs Review | |
| 11/02/2016 | ARUIZ1 | COT NON-DSD | TRAFFIC | Needs Review | |
| 11/02/2016 | ARUIZ1 | COT NON-DSD | FIRE | Needs Review | |
| 11/02/2016 | GLENN HICKS | COT NON-DSD | PARKS & RECREATION | Needs Review | |
| 11/02/2016 | JOHN BEALL | COT NON-DSD | COMMUNITY PLANNING | Needs Review | |
| 11/02/2016 | ARUIZ1 | COT NON-DSD | ENVIRONMENTAL SERVICES | Needs Review |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 11/02/2016 | ARUIZ1 | OUT TO CUSTOMER | Completed |