Permit: DP16-0011
Permit Details
Apply Date:
01/20/2016
Applicant:
Description:
GRADING/FPUP
Permit Reviews
Permit Number - DP16-0011
Permit Status: Complete
Permit Description: GRADING/FPUP
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/20/2016 | GRADING | 01/20/2016 | COMPLETED |
01/20/2016 | GRADING | 02/11/2016 | COMPLETED |
02/12/2016 | GRADING | 03/03/2016 | COMPLETED |
07/17/2017 | REVISION - GRADING | 07/25/2017 | COMPLETED |
07/25/2017 | REVISION - GRADING | 07/25/2017 | COMPLETED |
Outstanding Activity Conditions
Permit Number - DP16-0011
Permit Status: Complete
Permit Description: GRADING/FPUP
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
02/10/2016 | The following 13 conditions apply to grading permit DP16-0011:1)CALL FOR PRE-CONSTRUCTION MEETING. FOR A PDSD ENGINEERING INSPECTION, CALL IVR (791-3111), OR SCHEDULE WITH A CUSTOMER SERVICE REPRESENTATIVE AT THE PLANNING & DEVELOPMENT SERVICES DEPARTMENT - ANGIE 837-4917, OR CONTACT PDSD ENGINEERING AT 837-4888, OR SCHEDULE INSPECTIONS ONLINE AT: HTTPS://WWW.TUCSONAZ.GOV/PDSD/SCHEDULING-INSPECTIONS2)COPY OF THE GRADING PLAN / PERMIT DP16-0011 SHALL BE KEPT AT THE SITE AT ALL TIMES, UNTIL FINAL GRADING APPROVAL.3)PDSD INSPECTOR SHALL BE CALLED TO INSPECT SPECIAL GRADING, SUCH AS DRAINAGE SWALES, RETAINING WALLS, SLOPE OR EROSION PROTECTION WHEN UNDER CONSTRUCTION.4)ANY WALLS ON THESE PLANS MAY REQUIRE SEPARATE BUILDING PERMIT APPLICATIONS.5)THERE SHALL BE NO DISTURBANCE OUTSIDE OF THE DISTURBANCE/GRADING LIMITS. A MINIMUM 2-FT SETBACK IS REQUIRED AT ALL PROPERTY LINES.6)DRIVEWAY SHALL BE CONSTRUCTED TO PROVIDE NO STEEPER THAN A 15% SLOPE.7)PER HILLSIDE DEVELOPMENT ZONE REQUIREMENTS, ANY ROCK SHALL BE EITHER HANDPLACED RIP RAP WITH FLITER FABRIC OR HANDPLACED GROUTED RIP RAP.8)ANY SLOPES THAT EXCEED 3:1(H:V) SHALL HAVE RIP RAP WITH FILTER FABRIC OTHERWISE A SEALED GEOTECHNICAL LETTER SHALL BE REQUIRED STATING THAT THE CONSTRUCTED SLOPES ARE STABLE. 9)TEMPORARY EROSION AND SEDIMENT CONTROL DEVICES SHALL BE PLACED AT LOCATIONS WHERE STORMWATER RUNOFF EXITS GRADING LIMITS TO PREVENT DEBRIS, CONSTRUCTION SILT, AND/OR CHEMICALS FROM ENTERING STREETS OR ANY DRAINAGE WAYS. ANY INTERIM EROSION AND SEDIMENT CONTROLS THAT ARE INSTALLED SHOULD BE MAINTAINED, PER APPROVED PLANS OR PER EOR OR RAOR, AT DOWNSTREAM AREAS OF DISTURBANCE LIMITS. THESE INTERIM CONTROLS MUST BE REMOVED AFTER ALL PERMANENT CONTROLS HAVE BEEN ESTABLISHED.10)REVISIONS TO THE DESIGN MUST BE DISCUSSED WITH A CIVIL ENGINEER AT THE CITY OF TUCSON PLANNING & DEVELOPMENT SERVICES DEPARTMENT ENGINEERING DIVISION, PRIOR TO ANY CONSTRUCTION ACTIVITY, TO DETERMINE WHETHER ADDITIONAL DETAILS, CALCULATIONS, DRAINAGE STATEMENT, OR A REVISED GRADING PLAN IS NEEDED, OR, WHETHER CHANGES MAY BE PROVIDED ON AS-BUILTS. CONTACT PDSD ENGINEERING AT 791-5550 TO DISCUSS CHANGES IN GRADING DESIGN. ALL WORK COMPLETED WITHOUT APPROVAL IS SUBJECT TO STOP WORK ORDER. 11)IF GRADING CONSTRUCTION IS EXPECTED TO LAST LONGER THAN THE EXPIRATION DATE OF THE GRADING PERMIT, CONTACT DSD TO RENEW/EXTEND THE GRADING PERMIT. IF FINAL GRADING INSPECTION HAS NOT BEEN COMPLETED BEFORE THE GRADING PERMIT EXPIRES, AND THE PERMIT HAS NOT BEEN RENEWED, ADDITIONAL FEES AND REVIEWS MAY BE REQUIRED.12)PERMITTEE SHALL NOTIFY THE PDSD WHEN THE GRADING OPERATION IS READY FOR FINAL GRADING INSPECTION. FINAL GRADING APPROVAL SHALL NOT BE GIVEN UNTIL ALL WORK, INCLUDING INSTALLATION OF ALL DRAINAGE IMPROVEMENTS AND THEIR PERMANENT PROTECTIVE DEVICES, AND ALL PERMANENT EROSION CONTROL MEASURES HAVE BEEN COMPLETED IN ACCORDANCE WITH THE APPROVED GRADING PLAN AND GRADING PERMIT, AND ALL CONDITIONS OF PERMIT ARE COMPLETED. ANY REVEGETATED AREAS MAY REQUIRE LANDSCAPING APPROVAL OF ESTABLISHED VEGETATION PRIOR TO FINAL GRADING APPROVAL. ANY OTHER EXPOSED FLAT AREAS THAT ARE NOT RESEEDED SHALL BE COVERED IN GRAVEL, UNLESS OTHER MATERIAL IS PROPOSED, REVIEWED, AND ACCEPTED BY CITY OF TUCSON.13)AS-BUILTS SHALL SHOW FINISHED PAD OR FINISHED FLOOR ELEVATION, INVERTS OF ANY DRAINAGE PIPES, FRONT OF DRIVEWAY AT STREET ELEVATION, AND ANY AS-BUILT ELEVATIONS AS DEEMED NECESSARY BY THE RLS. SUBMIT AS-BUILTS AS A 'REVISION' TO THE GRADING PERMIT DP16-0011 PRIOR TO FINAL GRADING INSPECTION. PROJECT ENGINEERING COMPLETION LETTERS, AS WELL AS AS-BUILTS ARE REQUIRED TO BE SUBMITTED PRIOR TO FINAL GRADING INSPECTION. LETTER OF CERTIFICATION FROM A GEOTECHNICAL ENGINEER OF RECORD FOR PROJECT SUBSTANTIAL COMPLETION MAY BE REQUIRED IF SPECIAL RETAINING OR SLOPE GRADING CONSTRUCTION IS PERFORMED, AND IS TO BE SUBMITTED PRIOR TO FINAL GRADING INSPECTION. |
Completed Inspections
Permit Status: Complete
Permit Number: DP16-0011
Permit Description: GRADING/FPUP
Total Completed Inspections - 8
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/21/2016 | SITE - Stormwater Setup and Controls | Passed | {Activity date: 07/21/2016; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 07/18/2016; Status: Not ready for Inspection; Inspector: RLEDONN1; Comment: Entered by RLEDONN1 - } | |
07/21/2016 | PDSD Engineering Division Pre-Construction SITE | Passed | {Activity date: 07/21/2016; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 07/18/2016; Status: Not ready for Inspection; Inspector: RLEDONN1; Comment: Entered by RLEDONN1 - PROVIDE AP INSTALL OF SWPPP CONTROLS TO LET SILT GO UNDER WATTEL . COMPLET INSTALL PER AP PLANS.} ; {Activity date: 07/07/2016; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 07/06/2016; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - MET WITH GRADING CONTRACTOR ON SITE ABOUT INSTALLING SWPPP CONTROLS.} ; {Activity date: 07/05/2016; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
12/07/2017 | PDSD Site/Engineering Division - Landscaping | Passed | {Activity date: 12/07/2017; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
12/07/2017 | PDSD Site/Engineering Division - NPPO | Passed | {Activity date: 12/07/2017; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 06/28/2017; Status: Not ready for Inspection; Inspector: RLEDONN1; Comment: Entered by RLEDONN1 - } | |
12/07/2017 | ENGR Engineering Final | Passed | {Activity date: 12/07/2017; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 06/28/2017; Status: Not ready for Inspection; Inspector: RLEDONN1; Comment: Entered by RLEDONN1 - SEE NOTES ON 9027 ENGINEERING.} ; {Activity date: 06/28/2017; Status: Not ready for Inspection; Inspector: RLEDONN1; Comment: Entered by RLEDONN1 - } | |
12/07/2017 | SITE - Stormwater Follow-up | Passed | {Activity date: 12/07/2017; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 12/28/2016; Status: Continued; Inspector: RLEDONN; Comment: Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.} ; {Activity date: 11/02/2016; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.} ; {Activity date: 08/18/2016; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.} ; {Activity date: 08/05/2016; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.} | |
12/07/2017 | ENGR Grading Final | Passed | {Activity date: 12/07/2017; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
12/07/2017 | SITE - Stormwater Final Inspection | Passed | {Activity date: 12/07/2017; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 06/28/2017; Status: Not ready for Inspection; Inspector: RLEDONN1; Comment: Entered by RLEDONN1 - } |