Description:
GRADING/SWPPP- NW MEDICAL CENTER

Permit Reviews

Permit Number - DP14-0246
Permit Status: Complete
Permit Description: GRADING/SWPPP- NW MEDICAL CENTER
Start Date Submittal Complete Date Status  
02/27/2015 RESUB - SITE and/or GRADING 03/24/2015 ACTIVE Review Details
12/24/2014 GRADING 12/24/2014 COMPLETED Review Details
12/24/2014 GRADING 02/03/2015 COMPLETED Review Details

Completed Inspections

Permit Status: Complete
Permit Number: DP14-0246
Permit Description: GRADING/SWPPP- NW MEDICAL CENTER
Total Completed Inspections - 7
Date Description Inspector Results Comments
04/27/2015 PDSD Engineering Division Pre-Construction SITE Passed {Activity date: 04/27/2015; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) SITE HAS A SWPPP THAT HAS BEEN IMPLEMENTED
2) MAINTAIN SEDIMENT CONTROLS THROUGHOUT CONSTRUCTION
3) INSTALL A CONCRETE/MATERIALS WASH OUT WHEN APPLICABLE
4) PERFORM AND DOCUMENT YOUR STORM WATER SELF INSPECTIONS PER YOUR SWPPP
5) CONTACT ENGINEERING PRIOR TO ANY UNDERGROUND STORM PIPE WORK OR FOR ANY SITE CHANGES/CONCERNS}
11/20/2015 SITE - Stormwater Follow-up Passed {Activity date: 11/20/2015; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } ; {Activity date: 10/27/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME} ; {Activity date: 09/24/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - MAY NEED SUPPLEMENTAL SEDIMENT CONTROLS ALONG THE NORTH SIDE OF SITE IN ORDER TO COMPLY WITH YOUR SWPPP} ; {Activity date: 09/24/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME} ; {Activity date: 09/15/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) ENSURE STORM WATER SELF INSPECTIONS ARE PERFORMED AND DOCUMENTED PER YOUR SWPPP
2) SWEEP UP TRACKED SOIL AS NEEDED} ; {Activity date: 09/02/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME} ; {Activity date: 08/27/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) BASE OF CATCH BASIN POURED, RE-BAR SET AND FORMS CONSTRUCTED
2) RE-BAR = #4 AT 12" OC BOTH WAYS
3) SEDIMENT CONTROLS HAVE BEEN RE-ESTABLISHED AT THE NEW PERIMETER
} ; {Activity date: 08/26/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) NO INSPECTIONS CALLED IN FOR MANHOLE CONSTRUCTION
2) NEED TO RE-ESTABLISH SEDIMENT CONTROLS AT PERIMETER OF SITE , TO INCLUDE AREA TO THE WEST WHERE CONSTRUCTION HAS EXPANDED BEYOND THE PROPETY LINE.
3) CALL IN FOR INSPECTION FOR ANY UNDERGROUND STORM WORK, APPROVALS WILL NOT BE GIVEN FOR SITE WORK NOT INSPECTED
4) PROVIDE A CERT LETTER FROM THE ENG OF RECORD PRIOR TO FINAL
5) ENSURE STORM WATER SELF INSPECTIONS} ; {Activity date: 08/17/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME} ; {Activity date: 07/17/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME} ; {Activity date: 06/24/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME} ; {Activity date: 06/02/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - INSTALL SEDIMENT CONTROLS AROUND TEMP. STOCKPILE} ; {Activity date: 05/14/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
ENSURE YOU INSTALL A CONCRETE/MATERIALS WASH OUT WHEN APPLICABLE}
11/20/2015 ENGR Grading Final Passed {Activity date: 11/20/2015; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - }
11/20/2015 SITE - Stormwater Setup and Controls Passed {Activity date: 11/20/2015; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - }
12/07/2015 SITE - Stormwater Final Inspection Passed {Activity date: 12/07/2015; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - SUBMIT A NOTICE OF TERMINATION WITH ADEQ} ; {Activity date: 11/20/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) STABILIZE ALL DISTURBED AREAS ON SITE
2) SUBMIT A NOTICE OF TERMINATIONATION TO ADEQ.}
12/10/2015 PDSD Site/Engineering Division - Landscaping Passed {Activity date: 12/10/2015; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } ; {Activity date: 12/07/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) INSTALL TRASH ENCLOSURE GATES
2) COMPLETE ADA PARKING CHANGES
3) INSTALL OVERHEAD POLES IN DRIVE AREA
4) COMPLETE LANDSCAPING
5) INSTALL BIKE PARKING PER PLAN} ; {Activity date: 11/20/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - COMPLETE LANDSCAPING}
12/10/2015 ENGR Engineering Final Passed {Activity date: 12/10/2015; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } ; {Activity date: 12/07/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) INSTALL TRASH ENCLOSURE GATES
2) COMPLETE ADA PARKING CHANGES
3) INSTALL OVERHEAD POLES IN DRIVE AREA
4) COMPLETE LANDSCAPING
5) INSTALL BIKE PARKING PER PLAN} ; {Activity date: 11/20/2015; Status: Denied; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) COMPLETE SITE WORK TO INCLUDE LANDSCAPING AND STABILIZATION OF ALL DISTURBED AREAS
2) PROVIDE CERTIFICATION STATEMENT FROM THE ENG OF RECORD STATING THAT THE SITE/GRADING WAS CONSTRUCTED PER THE APPROVED PLANS.
3) PROVIDE AN AS-BUILT DRAWING
4) INSTALL BOLLARDS IN TRASH ENCLOSURE PER COT DEV. STD 6-01.0.
5) SUBMIT NOTICE OF TERMINATION WITH ADEQ}

Documents

File Name Document Type  
001_COVER SHEET_C000.TIF DEVELOPMENT PACKAGE VIEW
002_EXISTING CONDITIONS_C1.0.TIF DEVELOPMENT PACKAGE VIEW
003_EXISTING CONDITIONS_C2.0.TIF DEVELOPMENT PACKAGE VIEW
004_SITE NOTES_C200.TIF DEVELOPMENT PACKAGE VIEW
005_EROSION / SEDIMENT CONTROL_C300.TIF DEVELOPMENT PACKAGE VIEW
006_EROSION / SEDIMENT CONTROL DETAILS_C301.TIF DEVELOPMENT PACKAGE VIEW
007_SITE DEMOLITION_C400.TIF DEVELOPMENT PACKAGE VIEW
008_OVERALL SITE LAYOUT_C500.TIF DEVELOPMENT PACKAGE VIEW
009_DETAILED SITE LAYOUT / GRADING / DRAINAGE_C501.TIF DEVELOPMENT PACKAGE VIEW
010_SITE GRADING / DRAINAGE_C600.TIF DEVELOPMENT PACKAGE VIEW
011_STORM DRAIN / PROFILE_C601.TIF DEVELOPMENT PACKAGE VIEW
012_SITE UTILITY_C700.TIF DEVELOPMENT PACKAGE VIEW
013_SANITARY SEWER / PROFILE_C701.TIF DEVELOPMENT PACKAGE VIEW
014_SITE DETAILS_C800.TIF DEVELOPMENT PACKAGE VIEW
015_SITE DETAILS_C801.TIF DEVELOPMENT PACKAGE VIEW
016_CITY OF TUCSON DETAILS_C802.TIF DEVELOPMENT PACKAGE VIEW
017_SITE LANDSCAPE_L100.TIF DEVELOPMENT PACKAGE VIEW
018_SITE LANDSCAPE DETAILS_L200.TIF DEVELOPMENT PACKAGE VIEW
019_SITE IRRIGATION_L300.TIF DEVELOPMENT PACKAGE VIEW
020_SITE IRRIGATION_L300.TIF DEVELOPMENT PACKAGE VIEW
None DOCUMENTS VIEW