Permit Details

Status:
Complete
Type:
Development Package
Address NEW:
9455 E VALENCIA RD
Apply Date:
09/26/2014
Applicant:
Description:
DP: SITE, GRADING, SWPPP - VAIL CHRISTIAN CHURCH

Permit Reviews

Permit Number - DP14-0177
Permit Status: Complete
Permit Description: DP: SITE, GRADING, SWPPP - VAIL CHRISTIAN CHURCH
Start Date Submittal Complete Date Status  
09/17/2015 REVISION - SITE 09/09/2016 COMPLETED Review Details
09/26/2014 DEV PKG - OK TO SUBMIT 09/26/2014 COMPLETED Review Details
09/26/2014 SITE and/or GRADING 10/14/2014 COMPLETED Review Details
11/03/2014 RESUB - SITE and/or GRADING 11/19/2014 COMPLETED Review Details
11/26/2014 RESUB - SITE and/or GRADING 12/12/2014 COMPLETED Review Details
12/12/2014 RESUB - SITE and/or GRADING 12/19/2014 COMPLETED Review Details

Completed Inspections

Permit Status: Complete
Permit Number: DP14-0177
Permit Description: DP: SITE, GRADING, SWPPP - VAIL CHRISTIAN CHURCH
Total Completed Inspections - 8
Date Description Inspector Results Comments
02/18/2015 PDSD Engineering Division Pre-Construction SITE Passed {Activity date: 02/18/2015; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) MET WITH PROJECT MANAGER, REVIEWED PLANS AND WALKED SITE.
2) CONTRACTOR HAS STARTED IMPLEMENTING NPPO. PLANTS HAVE BEEN TAGGED AND IDENTIFIED.
3) A NUSERY WILL BE ESTABLISHED AND PLANTS WILL BE MOVED.
4) ENSURE YOUR STORM WATER PLAN IS IMPLEMENTED PRIOR TO GRUBBING AND GRADING.
5) CALL FOR RE-INSPECTION FOR QUESTIONS AND/OR CONCERNS}
03/24/2015 SITE - Stormwater Setup and Controls Passed {Activity date: 03/24/2015; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) CONTRACTOR INSTALLED SEDIMENT CONTROLS PER THIER SWPPP
2) ENSURE STORM WATER SELF INSPECTIONS ARE PERFORMED
3) SWEEP UP ANY TRACKED SOIL ONTO VALENCIA ROAD.} ; {Activity date: 03/20/2015; Status: Continued; Inspector: DROBERTS; Comment: Entered by DROBERT5 - LOOKED OVER THE SITE TOO ENSURE THAT THE CONTRACTOR HAD COMPLETED THE INSTALLATION OF THE STORMWATER CONTROLS. I AM UNABLE TO INSPECT THE SITE FULLY SINCE THERE ARE NO SWPPP PLANS ON THE SITE AT THIS TIME. MIKE WILL LOOK OVER THE SITE ON 3/23/2015 WHEN HE RETURNS TO ENSURE THAT THE SITE IS AS NOTED ON THE APPROVED PLANS. CURRENTLY THE SITE IS WRAPPED WITH WADDLE AND HAS STAKED STRAWBALES IN THE AREAS OF HIGH FLO.} ; {Activity date: 03/13/2015; Status: Violation; Inspector: MRUSSO; Comment: Entered by CSHARRA1 - CORRECTIONS REQ:
1. INSTALL SEDIMENT CONTROLS PER YOUR SWPPP
2. YOU ARE IN NON-COMPLIANCE WITH ADEQ AND THE CITY OF TUCSON STORM WATER ORDINANCE
3. THIS IS YOUR SECOND NOTICE
4. COMPLY BY 7 DAYS, NON-COMPLIANCE WILL RESULT IN A NOTICE OF VIOLATION AND I WILL CONTACT ADEQ} ; {Activity date: 03/09/2015; Status: Violation; Inspector: MRUSSO; Comment: Entered by DROBERT5 - CONTRACTOR IS WORKING SITE WITH NO STORM WATER CONTROLS INSTALLED.} ; {Activity date: 03/03/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - CORRECTION REQUIRED:
1) INSTALL SEDIMENT CONTROLS PER YOUR SWPPP
2) POST A COPY OF YOUR NOI AT ENTRANCE
3) INSTALL A STABIZED CONSTRUCTION ENTRANCE/EXIT
4) INSTALL A CONCRETE/MATERIALS WASH OUT
5) PROVIDE A MONITORING REPORT FROM THE LANDSCAPE ARCHITECT

CORRECT WITH IN 10 WORKING DAYS}
03/02/2016 SITE - Stormwater Follow-up Passed {Activity date: 03/02/2016; Status: Approved; Inspector: MRUSSO1; Comment: Entered by MRUSSO1 - } ; {Activity date: 01/07/2016; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME} ; {Activity date: 12/10/2015; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } ; {Activity date: 10/16/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - ENSURE SEDIMENT CONTTROLS ARE MAINTAINED THROUGHOUT CONSTRUCTION} ; {Activity date: 10/07/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO CHANGES AND/OR CONCERNS AT THIS TIME} ; {Activity date: 09/21/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME} ; {Activity date: 08/14/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) PVC STORM PIPE PARTIAL SECTIONS WERE INSTALLED PER THE APPROVED CIVIL PLAN - OK TO COVER
2) CONTRACTOR WORKING ON OVER-EXCAVATING FOR BRIDGE ACROSS WASH
3) CULVERT PIPES INSTALL AT OTHER CROSSINGS
4) ENSURE YOUR IN COMPLIANCE WITH YOUR SWPPP UNTIL THE SITE IS STABILIZED} ; {Activity date: 06/03/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) ENSURE STORM WATER MAINT. SELF INSPECTIONS ARE PERFORMED AND DOCUMENTED PER YOUR SWPPP.
2) INSPECTION MUST BE KEPT ON SITE FOR VERIFICATION
3) CALL FOR INSPECTION PRIOR TO COVERING STORM PIPE - PER YOUR GRADING NOTES.
4) ENSURE ALL SITE/GRADING/LANDSCAPE CHANGES ARE APPROVED THROUGH THE CITY OF TUCSON AND ARE REFLECTED ON THE SITE DRAWINGS
5) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME} ; {Activity date: 05/11/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
2) ENSURE STORM WATER SELF INSPECTIONS ARE PERFORMED AND DOCUMENTED.
3) SWEEP UP TRACKING OFF OF PUBLIC ROADWAYS} ; {Activity date: 04/30/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME} ; {Activity date: 04/14/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) STORM WATER SEDIMENT CONTROLS IN PLACE
2) ENSURE COMPLIANCE WITH YOUR STORM WATER PLAN AND PERMIT} ; {Activity date: 04/01/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME} ; {Activity date: 03/18/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by CSHARRA1 - NEED TO CONTACT PROJECT MANAGER - SITE NON-COMPLIANCE W/ STORM WATER PLAN AND PERMIT}
04/11/2016 PDSD Site/Engineering Division - Landscaping Passed {Activity date: 04/11/2016; Status: Approved; Inspector: MRUSSO; Comment: Entered by MRUSSO1 - } ; {Activity date: 03/03/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - CORRECTION REQUIRED:
1) INSTALL SEDIMENT CONTROLS PER YOUR SWPPP
2) POST A COPY OF YOUR NOI AT ENTRANCE
3) INSTALL A STABIZED CONSTRUCTION ENTRANCE/EXIT
4) INSTALL A CONCRETE/MATERIALS WASH OUT
5) PROVIDE A MONITORING REPORT FROM THE LANDSCAPE ARCHITECT

CORRECT WITH IN 10 WORKING DAYS} ; {Activity date: 02/18/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) MET WITH PROJECT MANAGER, REVIEWED PLANS AND WALKED SITE.
2) CONTRACTOR HAS STARTED IMPLEMENTING NPPO. PLANTS HAVE BEEN TAGGED AND IDENTIFIED.
3) A NUSERY WILL BE ESTABLISHED AND PLANTS WILL BE MOVED.
4) ENSURE YOUR STORM WATER PLAN IS IMPLEMENTED PRIOR TO GRUBBING AND GRADING.
5) CALL FOR RE-INSPECTION FOR QUESTIONS AND/OR CONCERNS}
04/11/2016 SITE - Zoning Final Passed {Activity date: 04/11/2016; Status: Approved; Inspector: MRUSSO; Comment: Entered by MRUSSO1 - } ; {Activity date: 09/30/2015; Status: Prior to Final Inspectn; Inspector: eleibol1; Comment: Entered by ELEIBOL1 - As-built submittal must include Revision #1 changes for stormdrain systems, and riparian covenant (see Landscape comments).}
04/11/2016 ENGR Engineering Final Passed {Activity date: 04/11/2016; Status: Approved; Inspector: MRUSSO; Comment: Entered by MRUSSO1 - } ; {Activity date: 12/10/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - PRIOR TO FINAL APPROVAL, ALL ASPECTS OF PHASE ONE SHOWN ON THE APPROVED PLANS MUST BE COMPLETED}
04/11/2016 ENGR Grading Final Passed {Activity date: 04/11/2016; Status: Approved; Inspector: MRUSSO; Comment: Entered by MRUSSO1 - } ; {Activity date: 03/02/2016; Status: Continued; Inspector: MRUSSO1; Comment: Entered by MRUSSO1 - NO FINAL INSPECTIONS CALLED IN} ; {Activity date: 10/16/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - CONTRACTOR SPREADING AB FOR PAVING OF PARKING LOT} ; {Activity date: 10/07/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO CHANGES AND/OR CONCERNS AT THIS TIME} ; {Activity date: 09/21/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) LOOKED AT PVC ROOF DRAIN PIPE ALONG THE NORTH SIDE OF BLDG #3 - CONTRACTOR MADE CONNECTION TO THE MAIN LINE AND STUBBED THE PIPE - OK TO BURY
2) CALL FOR INSPECTION PRIOR TO POURING CONCRETE FOR THE HEAD WALL CONSTRUCTION
3) ENSURE TOE DOWNS FOR GROUTED RIP RAP MEET PLAN DETAILS
4) COMPLY WITH YOUR SWPPP UNTIL THE SITE IS STABILIZED

PICTURES TAKEN} ; {Activity date: 09/03/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) CONTRACTOR GROUTING MAHOLE CONNECTIONS TO STORM PIPE.- OK
2) LOOKED A EQUALIZER PIPE FOR RET/DET BASINS ALONG THE NORTH SIDE} ; {Activity date: 08/24/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) LOOKED AT COLLAR INSTALL FOR TRANSITION FROM SRP TO RCP - OK TO COVER
2) LOOKED AT MANHOLE PREP FOR RCP ALONG SOUTHWEST ENTRANCE AREA - OK TO POUR
3) LOOKED AT MANHOLE ALONG THE NE SIDE OF BLDG

PICTURES TAKEN} ; {Activity date: 08/21/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) LOOKED AT MANHOLE ALONG NE CORNER OF BLDG - TRANSITION FOR STORM PIPE PER COT STD DETAIL 300 AND 302. HAND FORMED WITH STEEL - OK TO POUR
2) LOOKED AT PVC LATERAL ALONG NW CORNER OF BLDG - INSTALLED PER PLAN - OK TO POUR
3) LOOKED AT RCP TO SRP TRANSITION W/STEEL COLLAR ALONG WEST ENTRANCE- OK TO POUR

PICTURES TAKEN} ; {Activity date: 08/14/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) PVC STORM PIPE PARTIAL SECTIONS WERE INSTALLED PER THE APPROVED CIVIL PLAN - OK TO COVER
2) CONTRACTOR WORKING ON OVER-EXCAVATING FOR BRIDGE ACROSS WASH
3) CULVERT PIPES INSTALL AT OTHER CROSSINGS
4) ENSURE YOUR IN COMPLIANCE WITH YOUR SWPPP UNTIL THE SITE IS STABILIZED} ; {Activity date: 06/03/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) ENSURE STORM WATER MAINT. SELF INSPECTIONS ARE PERFORMED AND DOCUMENTED PER YOUR SWPPP.
2) INSPECTION MUST BE KEPT ON SITE FOR VERIFICATION
3) CALL FOR INSPECTION PRIOR TO COVERING STORM PIPE - PER YOUR GRADING NOTES.
4) ENSURE ALL SITE/GRADING/LANDSCAPE CHANGES ARE APPROVED THROUGH THE CITY OF TUCSON AND ARE REFLECTED ON THE SITE DRAWINGS
5) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME}
04/11/2016 SITE - Stormwater Final Inspection Passed {Activity date: 04/11/2016; Status: Approved; Inspector: MRUSSO; Comment: Entered by MRUSSO1 - ENSURE A NOTICE OF TERMINATION IS FILED WITH ADEQ} ; {Activity date: 03/02/2016; Status: Continued; Inspector: MRUSSO1; Comment: Entered by MRUSSO1 - STABILIZE ALL AREAS EFFECTED BY CONSTRUCTION, FILE A (NOT) WITH ADEQ} ; {Activity date: 12/10/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - SEDIMENT CONTROLS MUST REMAIN IN PLACE UNTIL THE SITE IS STABILIZED}

Documents

File Name Document Type  
001_COVER SHEET / NOTES_1 OF 55.TIF DEVELOPMENT PACKAGE VIEW
002_GRADING / PAVING NOTES_2 OF 55.TIF DEVELOPMENT PACKAGE VIEW
003_PRIVATE UTILITY NOTES_3 OF 55.TIF DEVELOPMENT PACKAGE VIEW
004_GENERAL NOTES_4 OF 55.TIF DEVELOPMENT PACKAGE VIEW
005_SITE_5 OF 55.TIF DEVELOPMENT PACKAGE VIEW
006_GRADING / PAVING_6 OF 55.TIF DEVELOPMENT PACKAGE VIEW
007_GRADING / PAVING_7 OF 55.TIF DEVELOPMENT PACKAGE VIEW
008_GRADING / PAVING_8 OF 55.TIF DEVELOPMENT PACKAGE VIEW
009_GRADING / PAVING_9 OF 55.TIF DEVELOPMENT PACKAGE VIEW
010_SITE / GRADING DETAILS_10 OF 55.TIF DEVELOPMENT PACKAGE VIEW
011_SITE / GRADING / UTILITY DETAILS_11 OF 55.TIF DEVELOPMENT PACKAGE VIEW
012_SITE / GRADING DETAILS_12 OF 55.TIF DEVELOPMENT PACKAGE VIEW
013_STORM DRAIN_13 OF 55.TIF DEVELOPMENT PACKAGE VIEW
014_PRIVATE UTILITY_14 OF 55.TIF DEVELOPMENT PACKAGE VIEW
015_FORCE MAIN SEWER_15 OF 55.TIF DEVELOPMENT PACKAGE VIEW
016_HORIZONTAL CONTROL_16 OF 55.TIF DEVELOPMENT PACKAGE VIEW
017_HORIZONTAL CONTROL DATA_17 OF 55.TIF DEVELOPMENT PACKAGE VIEW
018_LANDSCAPE / NPP GENERAL NOTES_18 OF 55.TIF DEVELOPMENT PACKAGE VIEW
019_WATER HARVESTING GENERAL NOTES_19 OF 55.TIF DEVELOPMENT PACKAGE VIEW
020_IRRIGATION DETAILS_20 OF 55.TIF DEVELOPMENT PACKAGE VIEW
021_PLANTING DETAILS_21 OF 55.TIF DEVELOPMENT PACKAGE VIEW
022_LANDSCAPE SPECIFICATIONS_22 OF 55.TIF DEVELOPMENT PACKAGE VIEW
023_LANDSCAPE SPECIFICATIONS_23 OF 55.TIF DEVELOPMENT PACKAGE VIEW
024_LANDSCAPE SPECIFICATIONS_24 OF 55.TIF DEVELOPMENT PACKAGE VIEW
025_PLANTING LEGEND_25 OF 55.TIF DEVELOPMENT PACKAGE VIEW
026_PLANTING_ 26 OF 55.TIF DEVELOPMENT PACKAGE VIEW
027_PLANTING_27 OF 55.TIF DEVELOPMENT PACKAGE VIEW
028_PLANTING_28 OF 55.TIF DEVELOPMENT PACKAGE VIEW
029_PLANTING_29 OF 55.TIF DEVELOPMENT PACKAGE VIEW
030_IRRIGATION LEGEND_30 OF 55.TIF DEVELOPMENT PACKAGE VIEW
031_IRRIGATION_31 OF 55.TIF DEVELOPMENT PACKAGE VIEW
032_IRRIGATION_32 OF 55.TIF DEVELOPMENT PACKAGE VIEW
033_IRRIGATION_33 OF 55.TIF DEVELOPMENT PACKAGE VIEW
034_IRRIGATION_34 OF 55.TIF DEVELOPMENT PACKAGE VIEW
035_WATER HARVESTING IMPLEMENTATION_35 OF 55.TIF DEVELOPMENT PACKAGE VIEW
036_WATER HARVESTING IMPLEMENTATION_36 OF 55.TIF DEVELOPMENT PACKAGE VIEW
037_NPPP_37 OF 55.TIF DEVELOPMENT PACKAGE VIEW
038_NPPP_38 OF 55.TIF DEVELOPMENT PACKAGE VIEW
039_NPPP_39 OF 55.TIF DEVELOPMENT PACKAGE VIEW
040_NPPP_40 OF 55.TIF DEVELOPMENT PACKAGE VIEW
041_NPPP_41 OF 55.TIF DEVELOPMENT PACKAGE VIEW
042_NPPP_42 OF 55.TIF DEVELOPMENT PACKAGE VIEW
043_NPPP_43 OF 55.TIF DEVELOPMENT PACKAGE VIEW
044_ENVIRONMENTAL RESOURCE REPORT_44 OF 55.TIF DEVELOPMENT PACKAGE VIEW
045_ENVIRONMENTAL RESOURCE REPORT_45 OF 55.TIF DEVELOPMENT PACKAGE VIEW
046_ENVIRONMENTAL RESOURCE REPORT_46 OF 55.TIF DEVELOPMENT PACKAGE VIEW
047_ENVIRONMENTAL RESOURCE REPORT_47 OF 55.TIF DEVELOPMENT PACKAGE VIEW
048_ENVIRONMENTAL RESOURCE REPORT_48 OF 55.TIF DEVELOPMENT PACKAGE VIEW
049_SWPPP_49 OF 55.TIF DEVELOPMENT PACKAGE VIEW
050_SITE ACCESSIBILITY DETAILS_X1.0.TIF DEVELOPMENT PACKAGE VIEW
051_SITE ACCESSIBILITY DETAILS_X1.1.TIF DEVELOPMENT PACKAGE VIEW
052_SITE ACCESSIBILITY DETAILS_X2.0.TIF DEVELOPMENT PACKAGE VIEW
053_SITE ACCESSIBILITY DETAILS_X3.0.TIF DEVELOPMENT PACKAGE VIEW
054_SITE ACCESSIBILITY DETAILS_3A1.0.TIF DEVELOPMENT PACKAGE VIEW
055_SITE ACCESSIBILITY DETAILS_3A1.1.TIF DEVELOPMENT PACKAGE VIEW
None DOCUMENTS VIEW