Permit: DP13-0199
Permit Details
Apply Date:
10/09/2013
Applicant:
Lisa Bowers
Description:
SITE/GRADING
Permit Reviews
Permit Number - DP13-0199
Permit Status: Complete
Permit Description: SITE/GRADING
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/22/2014 | RESUB - SITE/GRADING ALL | 01/28/2014 | COMPLETED |
| 01/28/2014 | SITE and/or GRADING | 01/28/2014 | COMPLETED |
| 05/08/2014 | REVISION - SITE | 05/22/2014 | COMPLETED |
| 10/09/2013 | DEV PKG - OK TO SUBMIT | 10/10/2013 | COMPLETED |
| 10/10/2013 | SITE and/or GRADING | 11/07/2013 | COMPLETED |
| 12/06/2013 | RESUB - SITE and/or GRADING | 01/22/2014 | COMPLETED |
Completed Inspections
Permit Status: Complete
Permit Number: DP13-0199
Permit Description: SITE/GRADING
Total Completed Inspections - 6
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/27/2014 | PDSD Engineering Division Pre-Construction SITE | Passed | {Activity date: 02/27/2014; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) NO ENGINEERING PRE-CON MEETING CALLED IN, CONTRACTOR ABOUT 25% COMPLETED WITH PROJECT. 2) SOME SITE WORK TO COMPLETE INCLUDE A PARKING LOT, PEDESTRIAN ACCESS, TRASH ENCLOSURE, STORM WATER DRAINAGE AND LANDSCAPING. 3) NO STORM WATER PERMIT REQUIRED, SITE IS LESS THAN 1 ACRE, HOWEVER CONTRACTOR MUST KEEP DISTURBED SOIL ON SITE DURING CONSTRUCTION. 4) TRASH ENCLOSURE DIMENSIONS OK. RE-BAR LAYOUT PER STRUCTURAL ENGINEER DETAIL - BOLLARDS SET PER PLAN. OK TO POUR CONCRETE. 5) NO CLEAR NPPO PLAN OR REQUIREMENT. CALL FOR RE-INSPECTION} |
|
| 05/28/2014 | PDSD Site/Engineering Division - Landscaping | Passed | {Activity date: 05/28/2014; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } | |
| 05/28/2014 | SITE - Stormwater Follow-up | Passed | {Activity date: 05/28/2014; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } ; {Activity date: 03/31/2014; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME 2) SUBGRADE SET FOR PARKING, CURB CUTS IN PLACE 3) HC ACCESS RAMP BEING INSTALLED ALONG SE ACCESS AND HC PARKING. 4) CHECKED SLOPES ON ACCESS SIDEWALKS - OK} ; {Activity date: 03/28/2014; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME} ; {Activity date: 03/06/2014; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) SWEEP UP TRACKED SOIL OFF OF ADJACENT ROADWAY 2) PROTECT ANY STORM CATCH BASINS IN AREA AROUND THE CONSTRUCTION SITE. 3) TRASH ENCLOSURE WALL RE-BAR LAYOUT PER APPROVED PLAN, OK TO GROUT 4) ENSURE LANDSCAPE AREAS ARE DEPRESSED 6" MIN} ; {Activity date: 02/27/2014; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) NO ENGINEERING PRE-CON MEETING CALLED IN, CONTRACTOR ABOUT 25% COMPLETED WITH PROJECT. 2) SOME SITE WORK TO COMPLETE INCLUDE A PARKING LOT, PEDESTRIAN ACCESS, TRASH ENCLOSURE, STORM WATER DRAINAGE AND LANDSCAPING. 3) NO STORM WATER PERMIT REQUIRED, SITE IS LESS THAN 1 ACRE, HOWEVER CONTRACTOR MUST KEEP DISTURBED SOIL ON SITE DURING CONSTRUCTION. 4) TRASH ENCLOSURE DIMENSIONS OK. RE-BAR LAYOUT PER STRUCTURAL ENGINEER DETAIL - BOLLARDS SET PER PLAN. OK TO POUR CONCRETE. 5) NO CLEAR NPPO PLAN OR REQUIREMENT. CALL FOR RE-INSPECTION} |
|
| 05/28/2014 | ENGR Grading Final | Passed | {Activity date: 05/28/2014; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } | |
| 05/28/2014 | SITE - Stormwater Final Inspection | Passed | {Activity date: 05/28/2014; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } | |
| 06/09/2014 | ENGR Engineering Final | Passed | {Activity date: 06/09/2014; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } ; {Activity date: 05/28/2014; Status: Partial Approval; Inspector: MRUSSO; Comment: Entered by DROBERT5 - PROVIDE A CERTIFICATION STATEMENT FROM THE ENG OF RECORD PER YOUR APPROVED PLANS} |