Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Parcel Search

 
Parcel Attributes
Parcel14041134D
JurisdictionTucson
City of Tucson ZoningI-1
Water Course

Washes

Tucson WardWard 5
Pima County Data Assessor, Recorder, Treasurer, ...
Parcel Map Map
Addresses

Annexations & Original City Zoning (OCZ)

Date - 11/05/2024 12:44 p.m.
Total Number Of OZC Plans - (1)
Plan Description Annexation Ordinance Effective Date OCZ Ordinance
C15-88-01 Country Club - Valencia 7025 10/07/1988 7090

Permits

Parcel Number - 14041134D
Date - 11/05/2024 12:44 p.m.
Total Number Of Permits - (51)
Permit Permit Status Entered Date Expired Date Unit Type Description
T22FC00010 Expired 01/06/2022 05/03/2023 Fire Construction Permit Automatic Fire Extingshing Sys - INSTALL NEW INRACK SPRINKLER SYSTEM IN RACK EXPANSION.
T19FC00082 Expired 01/29/2019 02/04/2020 Fire Construction Permit Automatic Fire Extingshing Sys - ADD 5 WET SYSTEMS TO NEW MEZZANINE #4, CONNECT AT EXISTING RISER MANIFOLD.; Commercial Fire Sprinkler Systems - Standpipe Modified; Additional Inspections: 3
DP21-0047 Complete 02/16/2021 07/30/2022 Development Package Site/Grading/Swppp - Homegoods, parking addition for commercial storage.
T22CM01540 Revision fees due 03/02/2022 10/03/2023 Commercial Building Installation of Storage Racks into an existing building
T22FO00205 Complete 03/02/2022 03/23/2023 Fire Operational Permit High-Piled Storage - Installation of storage racks into an existing building.; Other Operational Permit
D08-0018 Expired 03/13/2008 03/09/2010 Development Package AVN PROPERTIES
DS15-10 Approved 03/17/2015 N/A Zoning Compliance HOME GOODS - 6803 S PALO VERDE RD 4-02 SECTION 2.2
DP15-0052 Complete 03/25/2015 12/15/2018 Development Package GRADING / SWPP / DRAINAGE PAVING - HOME GOODS
TE-FPU-0324-00094 Void 03/28/2024 N/A Floodplain Use Voided - Duplicate Tucson Water Project - Installation of 6100' of new 24" waterline west of the alignment of Alvernon way. the contract includes a vegetation remediation plan. no disturbance to traffic or pavement.
TF-FCP-0523-00657 Complete 05/04/2023 N/A Fire Construction Permit Add Dual Input module to tie in newly installed Sprinkler Riser Flow and Valver Tamper.
DP21-0125 Complete 05/18/2021 12/11/2026 Development Package Site: HomeGoods Distribution Center.
T22FC00428 Complete 06/21/2022 11/21/2023 Fire Construction Permit Fire Alarm & Detection Systems - Adding 2 duct detectors, two test switches, and 2 Horn Strobes to newly remodeled patio enclosure.; Fire Alarm Systems - Devices Modified: 4
T21CM05616 Expired 07/09/2021 05/31/2022 Commercial Building The demolition of 12 knock-out panels and the addition of 12 new dock doors to match existing. Work
DS07-26 Approved 07/12/2007 N/A Zoning Compliance 6803 SOUTH PALO VERDE ROAD
TC-COM-0724-01384 Inspections 07/18/2024 04/21/2025 Commercial Building New Attached Fabric Shade Structure - 31' x 78' with 16' - 7" MAX Overall Height
TD-DEV-0724-00209 Inspections 07/18/2024 10/11/2027 Development Package Development Plan For New Attached Fabric Shade Structure - 78' x 31' With 16' - 7" MAX Height
T21CM06682 Complete 08/17/2021 05/28/2024 Commercial Building Enclosing an existing 2,500 SF outdoor patio area. Work to include structural, mechanical, and elect
TR-UTL-1023-02642 Complete 10/05/2023 01/29/2025 Right-of-Way (ROW) - Utility Tucson Water Project - Installation of 6100' of new 24" waterline west of the alignment of Alvernon way. the contract includes a vegetation remediation plan. no disturbance to traffic or pavement.
DP14-0182 Complete 10/06/2014 N/A Development Package SITE - NEW DISTRIBUTION WAREHOUSE Originally approved 10/8/2014Full plans approved 6/8/2015
TF-FCP-1024-00915 In review 10/29/2024 N/A Fire Construction Permit Request Paper permit to install one control relay to tie fire alarm into card access system.
DP18-0307 Complete 12/19/2018 08/05/2020 Development Package SITE - HomeGoods, mezzanine, breakroom expansion, bus stop walkway.
T15CM02190 C of o 04/03/2015 11/06/2018 COMBO TCO approved for training operations. AREA 1 THRU 8 NEW DISTRIBUTION CENTER
T16BU00676 Expired 04/29/2016 N/A TANKS 3 TANKS
T16CM01930 Final 03/14/2016 07/19/2017 COMBO ELECTRIC FEEDER FOR CONVEYOR- and per revision #1, the complete conveyor system wiring.
T16CM02086 Final 03/21/2016 07/25/2017 COMBO MATERIAL HANDLING SYSTEM - HOME GOODS
T16CM09446 Final 12/19/2016 04/30/2018 COMBO NEW SOLAR PANELS
T17RW05589 Withdrwn 12/20/2017 N/A ROW
T18CM09068 L of c 11/14/2018 05/16/2020 COMBO MEZZANINE
T19CM00954 Final 02/07/2019 04/17/2023 COMBO TI: MATERIAL HANDELING EQUIPTMENT RENOVATION TJX HOMEGOODS
T19CM03456 L of c 05/15/2019 01/21/2020 COMBO WALKWAY LIGHTING
T19CM03868 C of o 05/31/2019 06/15/2020 COMBO OFFICE
T19FC00155 Final 02/27/2019 04/11/2020 FIRECONS MEZZANINE FIRE ALARM ADDITION
T19FC00658 Final 08/20/2019 05/03/2020 FIRECONS ADD 4000 SQFT OF LIGHT HAZARD (BREAKROOM) SPRINKLERS TO EXISTING SYSTEM 19
T19FC00823 Final 10/03/2019 10/10/2020 FIRECONS BREAK ROOM - FIRE ALARM ADDITION
T19FO00889 Final 10/16/2019 04/09/2020 FIREOPER 1 TENT 10.12.19-10.14.19 ADDED 1 HOUR ON HERE FOR T19FO00848
T19FO00982 Final 11/07/2019 N/A FIREOPER HOMEGOODS - OCC: 700
T19RW06648 Final 10/30/2019 11/29/2019 ROW AIR-VACUUM EXCAVATION OF 5 UTILITY POTHOLES APPROXIMATELY 12" X 12" IN SIZE ALONG SHOULDER OF ALVERNON WAY FOR THE DESIGN PHASE OF TUCSON WATER AEROSPACE CORRIDOR 16" WATER LINE PROJECT. NOTE: ALVERNON WAY is under a pavement moratorium, any new asphalt that is disturbed will require a 2" mill and overlay for 50' in each direction from the outside of the cut for all effected travel lanes. ADDRESS ON APPLICATION 8800 S ALVERNON WAY
T20FC00262 Final 04/24/2020 02/21/2021 FIRECONS Addition of 8 new Duct Detector Control Modules (Duct Detectors are manufacturer provided)
T20FO00261 Final 05/11/2020 05/18/2021 FIREOPER 2 Tents for shade to enforce social distancing.
T20RW05164 Final 09/23/2020 02/23/2021 ROW JOC FOR ROADWAY CONSTRUCTION, ALVERNON WAY @ SHADOW BRANCH/HOME GOODS, DR-13 INSTALLATION OF A TRAFFIC SIGNAL, A SMALL RIGHT-TURN LANE ON THE WEST LEG, SIDEWALKS, ADA PEDESTRIAN ACCESS RAMPS, PAVEMENT MARKINGS AND SIGNAGE. Alvernon Way north of Atherton Drive is Pima County jurisdiction. Traffic control setup will not impact that area. Project will not impact Holiday Restriction.
T20RW06650 Void 12/29/2020 N/A ROW TEMPORARY INSTALL OF CONSTRUCTION WATER SOURCE FOR SITE DEVELOPMENT. MILLING AND TRENCHING ON CORONA ROAD, BETWEEN ALVERNON WAY AND PALO VERDE RD. INSTALL AND PLACE HDPE PIPE UNDER ROAD. THEN WILL PLACE PLATES OVER MILLED AND TRENCHED AREAS. ONCE COMPLETE WE WILL REMOVE AND PATCH BACK.
T21CM00175 L of c 01/06/2021 02/27/2022 COMBO Tenant improvement of existing warehouse space to include new ADA restrooms, HVAC upgrades and 2nd floor mezzanine
T21FC00038 Final 01/19/2021 01/27/2022 FIRECONS Temporary 10,000 gallon fuel tank
T21FC00478 Final 06/15/2021 02/19/2022 FIRECONS Add (5) pendent sprinklers in new restrooms and (2) in new offices
T21FC00505 Final 06/22/2021 07/31/2022 FIRECONS Lowering 15 Sprinkler branches( 1 head per branch). Note: Lowering pipe only, sprinkler heads will not be moved and coverage will not change.
T21FC00543 Final 07/08/2021 02/20/2022 FIRECONS DDING (6) LED NOTIFICATION DEVICES TO EXISTING POWER SUPPLY FOR THE R.R. AND OFFICE T.I.
T21FO00137 Final 03/01/2021 03/22/2022 FIREOPER 1 TET SET UP DATE 03.04.21 20X20
T21RW00131 Final 01/11/2021 04/08/2021 ROW Speed Trailers 8506 and 8507 will be temporarily placed in ROW to capture speed/volume data and mitigate speeding in road construction area.
T21RW01233 Final 03/16/2021 04/17/2021 ROW INSTALL DRIVEWAYS AND CURB FOR NEW DEVELOPMENT INGRESS/ EGRESS FOR BUSINESS AND RESIDENTIAL ACCESS SHALL BE MAINTAINED. FIELD ADJUSTMENTS MAY BE REQUIRED. PAVEMENT PATCHING IS NECESSARY WHERE PAVEMENT IS CUT. PATCH LIMITS- THE LIMITS OF THE PAVING SHALL BE A MINIMUM OF 1-FT OUTSIDE THE EXCAVATION. POTHOLES SPACED CLOSELY TOGETHER AND WITHIN 8-FT OF EACH OTHER WILL NEED TO BE JOINED TOGETHER BY ONE SURFACE PATCH. BACKFILL WITH CLSM SLURRY OR AGGREGATE BASE COURSE (ABC.) ASPHALTIC CONCRETE USED SHALL BE CITY OF TUCSON MIX NO. 3 OR COT MIX NO. 2 WITH TR-22, INSPECTOR TO ADVISE. TRENCHES/ PITS CANNOT BE LEFT OPEN OVERNIGHT. MUST BE BACKFILLED AND PATCHED OR PLATED. REPAIR ALL LANDSCAPING DISTURBED. THIS INCLUDES IRRIGATION, PLANTINGS, GROUNDCOVER, AND HARDSCAPE. REPLACE/ REFRESH ALL STRIPING THAT IS INTERRUPTED BY PATCHES. GOOD HOUSEKEEPING MEASURES SHALL BE PRACTICED DURING WORK AND CONSTRUCTION MAINTAIN PEDESTRIAN ACCESS.
T21RW01564 Final 04/02/2021 07/14/2021 ROW N.841593 - Job will require MH #24056 access required to push counts lso20, 53-54 from ex 72ct [a1sz1] to new 72 fiber cable on S Alvernon Way (South of E Shadow Branch Dr). 968 ft of aerial cable placement/removed, 5 ft of trenching on S Alvernon Way. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. OTHER ACTIVITIES IN THE AREA, WILL NEED TO COORDINATE TRAFFIC CONTROL SETUP WITH EXISTING SETUP.
T22RW01395 Final 04/07/2022 07/12/2022 ROW N.975185- ALONG S. ALVERNON WAY ACCESS HH 24056 TO SPLICE EXISTING CABLE.

Code Enforcement

Parcel Number - 14041134D
Date - 11/05/2024 12:44 p.m.
Total Number Of Code Cases - 2
Case Number Case Status Entered Date Closed Date Unit Type Description
CE-VIO0624-02294 Closed - unfounded 06/13/2024 06/26/2024 Code Enforcement Case PMMULT / Referred from Sun Link / Overgrown Palo Verde trees on South side of property along E Corona Rd (at Bus stop) trees are low hanging impeding with Sun Link
T21DV00917 Complian 02/18/2021 N/A DNR_VIOL BRIGHT LIGHTS FROM SIGN TRESPASSING INTO RODAWAY AND ADJACENT PROPERTIES

Plans

Parcel Number - 14041134D
Date - 11/05/2024 12:44 p.m.
Total Number Of Plans - 8
Plan Number Plan Status Application Date Expired Date Unit Type Description
C15-88-01A Approved 01/16/2015 N/A Map/Use Changes - Entitlements Homegoods, Inc
CWH-15-0052 Active 03/25/2015 12/15/2018 Basin GRADING / SWPP / DRAINAGE PAVING - HOME GOODS
T21BA00015 Approved 08/23/2021 N/A Basin Basin A
T21BA00016 Approved 08/23/2021 N/A Basin Basin B
T21BA00017 Approved 08/23/2021 N/A Basin Basin C
T21BA00018 Approved 08/23/2021 N/A Basin Basin D
T21BA00019 Submitted 08/23/2021 N/A Basin Basin E
TP-PRE-0723-00262 Complete 07/07/2023 N/A Pre-Application The proposed project consists of the widening of an existing entrance drive and reconfiguration of the existing parking lot/fencing/light poles for the distribution center.