Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Parcel Search

 
Parcel Attributes
Parcel11504495A
JurisdictionTucson
City of Tucson ZoningC-1, UC-1, UC-1
Tucson WardWard 6
Tucson Registered NeighborhoodWest University
Pima County Data Assessor, Recorder, Treasurer, ...
Parcel Map Map
Addresses

Annexations & Original City Zoning (OCZ)

Date - 11/14/2024 5:42 p.m.
Total Number Of OZC Plans - (1)
Plan Description Annexation Ordinance Effective Date OCZ Ordinance
1/4 Mile Each Direction (N, E, S, W) 202 08/17/1905 None

Rezoning Cases

Date - 11/14/2024 5:42 p.m.
Total Number Of Rezone Cases - (1)
Case No. Description New Zone Status Status Date Address
C9-12-01 C9-12-01 Main Gate Dist. (UOD) UOD Effectuated 01/05/2012 E 1ST

Special Development Requests & Requirements

Date - 11/14/2024 5:42 p.m.
Total Number Of Special Development Permits - (4)
Activity Number Status Apply Date Expired Date Type Description
H000013583 Closed N/A
T20SA00331 Complete N/A Zoning Compliance Letter
T20SA00343 Approved N/A
T22SA00270 Void N/A Zoning Compliance Letter

Permits

Parcel Number - 11504495A
Date - 11/14/2024 5:42 p.m.
Total Number Of Permits - (40)
Permit Permit Status Entered Date Expired Date Unit Type Description
TR-ROW-0124-00061 Issued 01/11/2024 07/05/2024 Right-of-Way (ROW) Updated - 5/01/2024 - Overhead crane work and large loads access points on Right-of- Way. To place large concrete slabs on the roof of High rise building. Park Ave: - Closure to all Sidewalks, Bike Lanes, and Drive Lanes from June 3rd at 5:00AM to June 14th at 5:00pm to allow for safe operating space. 6/3/2024 (5:00am ) - 6/14/2024 (5:00pm) J H Findorff & Son Inc. will be the Contractor responsible for the work, ROC # 328650. Updated - 4/09/2024 -- Revision for Night Work- " Revising permit for Overnight pours in Late April & Early May per provided and approved TNE. No Changes to Existing TCP.. TNE Dates - April 19th with backup dates of April 18th & 22nd, April 25th with backup dates of April 24th & April 26th ; May 6th with backup dates of May 3rd & May 7th, starting at 1 am and continuing until Sunrise on the following day. 3/19/2024 - Revising permit for overnight pours in late March and Early April per provided and approved TNE. No changes to existing TCP. -- New Night work dates - March 25th with backup dates of March 22nd & 26th, April 1st with backup dates of March 29th & April 2nd, April 8th with backup dates of April 5th & 8th, April 25th with back up dates of April 12th & 16th, starting at 1 am and continuing until Sunrise.. Original - Full road closure- Continuation of TR-ROW-0823-01028 which expired 01-07-2024 (with renewal) Overnight concrete pours 01-16-2024: TNE for January 23rd with January 22nd and 24th as backup dates AND January 30th with January 29th and 31st as backup dates if needed, starting at 1am and continuing until Sunrise on the following day. notes from previous permit TR-ROW-0823-01028: **** UPDATED - Park Ave: - Closure to all Sidewalks, Bike Lanes, and Drive Lanes from 5:00AM - 3:00PM the to allow for safe operating space of the Telebelt Material Placement Machine to safely Operate. In addition, on the 9/25 and 9/29 closures, we will also be testing the (3) new manholes that were installed this summer with Pima County. Duration of the work will be the following days: 9/25/23 from 5AM to 3PM 9/29/23 from 5AM to 3PM 10/6/23 from 5AM to 3PM... ***** Overnight Closure of Park Ave for concrete pour associated with DP20-0152 on Thursday, August 10, 2023 at 6:00am. Additional dates include Sundays August 13th and 27th from 11pm through sunrise the following day 12/6/23 Revised TNE - December 7th with backup dates of December 6th OR 8th and December 20th with backup dates of December 19th OR 21st starting at 1am and continuing until Sunrise 12/22/23 -full closure per approved TCP for December 20, 2023 through January 4, 2024 to perform onsite work while students are out of school. Approved TNE for January 2, 2024 with back up dates of December 29th, 2023 or January 3rd, 2024 starting at 1AM and continuing through sunrise. 01/02/2024- (TNE) January 9, 2024 with back up dates of January 8th OR January 10th, 2024 starting at 1am and continuing until Sunrise on the following day.
DP13-0015 Complete 01/28/2013 07/13/2020 Development Package SITE
TR-ROW-0223-00344 Complete 02/07/2023 03/16/2024 Right-of-Way (ROW) Right of way closures associated with DP20-0152. Full closure of alley, access to garages and trash will be from Speedway to the north. Sidewalk closure along 1st St from the alley East to Park Av. Sidewalk closure on Park from Speedway to 1st. 2 lanes will be maintained on Park and 1st.
TC-COM-0224-00363 Issued 02/27/2024 04/29/2025 Commercial Building Construction of new elevated pool & spa.
TR-ROW-0324-00305 Issued 03/18/2024 03/17/2025 Right-of-Way (ROW) continuation of TR-ROW-0223-00344 Right of way closures associated with DP20-0152. Full closure of alley, access to garages and trash will be from Speedway to the north. Sidewalk closure along 1st St from the alley East to Park Av. Sidewalk closure on Park from Speedway to 1st. 2 lanes will be maintained on Park and 1st.
TR-ROW-0423-00652 Complete 04/19/2023 08/26/2023 Right-of-Way (ROW) Closure of S Park Ave to erect on-site crane. 24/7 closure but work will only occur during allowable construction hours. TNE Approval for 8/19 7pm-6am, 8/20 7pm-6am, 8/21 7pm-6am if needed
TC-COM-0424-00707 Issued 04/19/2024 12/17/2024 Commercial Building Provide a Remote Fill Connection for the Emergency Back-Up Generator provided under separate contract.
TR-ROW-0423-00677 Complete 04/25/2023 07/28/2023 Right-of-Way (ROW) Closure for Sewer Work
TR-UTL-0623-01835 Issued 06/21/2023 08/09/2023 Right-of-Way (ROW) - Utility Installing 2-8" Fire Protection Services, 1" water service with 1" irrigation meter, 4" potable water meter and 2 system abandonments
TF-FCP-0623-00820 Void 06/29/2023 N/A Fire Construction Permit VOID-SUBMITTED NEW PERMIT#TF-FCP-0823-00931 BY POWER DESIGN INC-ERRC
TC-COM-0723-01768 Void 07/19/2023 01/15/2024 Commercial Building VOID: Wrong permit type. Submit new application under commercial new build and a complete set of plans prepared and stamped by a registered Arizona architect or engineer. Electrical work for new construction build
TC-COM-0723-01786 Void 07/20/2023 01/16/2024 Commercial Building VOID - Duplicate Application. There is already a permit in process for this address which included this scope of work TC-COM-1222-00337. Electrical Work for a new commercial building
TR-ROW-0724-00849 Complete 07/25/2024 10/03/2024 Right-of-Way (ROW) 24 hour closure to remove tower crane from site September 3-6
DP20-0152 Issued 07/28/2020 10/23/2026 Development Package Site/Main Gate District - Hub Five Tucson.
T22CM05823 Issued 07/30/2022 08/26/2024 Commercial Building Foundation Only for Future Apartment building
TR-UTL-0724-01424 Complete 07/31/2024 11/19/2024 Right-of-Way (ROW) - Utility Barricade Only: PRJ276352-1:Cox to PUll 220 through existing CATV conduit for system tie.
TR-ROW-0823-01028 Issued 08/02/2023 01/07/2024 Right-of-Way (ROW) **** UPDATED - Park Ave: - Closure to all Sidewalks, Bike Lanes, and Drive Lanes from 5:00AM - 3:00PM the to allow for safe operating space of the Telebelt Material Placement Machine to safely Operate. In addition, on the 9/25 and 9/29 closures, we will also be testing and cameraing the (3) new manholes that were installed this summer with Pima County. Duration of the work will be the following days: 9/25/23 from 5AM to 3PM 9/29/23 from 5AM to 3PM 10/6/23 from 5AM to 3PM... ***** Overnight Closure of Park Ave for concrete pour associated with DP20-0152 on Thursday, August 10, 2023 at 6:00am. Additional dates include Sundays August 13th and 27th from 11pm through sunrise the following day 12/6/23 Revised TNE - December 7th with backup dates of December 6th OR 8th and December 20th with backup dates of December 19th OR 21st starting at 1am and continuing until Sunrise 12/22/23 -full closure per approved TCP for December 20, 2023 through January 4, 2024 to perform onsite work while students are out of school. Approved TNE for January 2, 2024 with back up dates of December 29th, 2023 or January 3rd, 2024 starting at 1AM and continuing through sunrise. 01/02/2024- (TNE) January 9, 2024 with back up dates of January 8th OR January 10th, 2024 starting at 1am and continuing until Sunrise on the following day.
TF-FCP-0823-00931 Expired 08/04/2023 09/25/2024 Fire Construction Permit New Construction installation of a code compliant Fire Alarm & ERRCES in a 12-story high rise.
TR-ROW-0924-01135 In review 09/26/2024 N/A Right-of-Way (ROW) Placement of mobile crane in ROW to fly materials to rooftop
TF-FCP-0923-01162 Issued 09/29/2023 04/26/2025 Fire Construction Permit New Automatic Fire Sprinkler System w/ underground
TF-FCP-1023-01185 Void 10/09/2023 N/A Fire Construction Permit VOID-SUBMIT UNDER PERMIT#TF-FCP-0823-00931-Emergency Responder Radio Communications System Installation at 1001 North Park Avenue, Tucson, AZ 85719 - Project Name: Hub V at Tucson
T22BU00398 Complete 10/19/2022 03/19/2024 Demolition Permit Full demolition of existing credit union
TS-PRM-1024-00473 In review 10/29/2024 04/27/2025 Sign - Permanent Must be submitted by Fluoresco
TR-ROW-1122-00048 Complete 11/04/2022 06/08/2023 Right-of-Way (ROW) Remove ISL-3 Switch Cabinet - trenching 150 LF in 1st ST and 450 LF in Alley
TR-ROW-1124-01302 Issued 11/06/2024 01/22/2025 Right-of-Way (ROW) Barricade only associated with TR-PIA-1223-00032
TR-UTL-1123-02882 Complete 11/07/2023 02/14/2024 Right-of-Way (ROW) - Utility TEP WO T48525 - Pulling in new cable from riser on 1st Street to J1 cabinet, outage required for traffic light
TF-FCP-1123-01304 Void 11/13/2023 N/A Fire Construction Permit VOID-Submit under Permit#TF-FCP-0823-00931 - ERRCES
TR-ROW-1223-01424 Issued 12/04/2023 03/16/2024 Right-of-Way (ROW) Placement of Construction Trailer in Alley between Park Av and Tyndall Av. Extension of TR-ROW-0623-00849
TR-PIA-1223-00032 Inspections 12/11/2023 03/25/2025 Private Improvement Agreement (PIA) Offsite improvements for Hub V Tucson at Main Gate District.
TC-COM-1222-00337 Issued 12/20/2022 05/12/2025 Commercial Building New Multi-Family Structure HUB V
T04CM05240 Expired 12/02/2004 06/06/2005 COMBO DEMO:INTERIOR AND ROOF
T04CM05620 C of o 12/30/2004 12/26/2005 COMBO TI:BANK
T05OT00345 Final 02/15/2005 10/11/2005 SIGN SIGN:8516 ARIZONA STATE SAVINGS & CREDIT UNION
T05OT01476 Final 06/14/2005 03/14/2006 SIGN SIGN: 9178 ARIZONA STATE SAVINGS & CREDIT UNION
T05OT01477 Final 06/14/2005 01/25/2006 SIGN SIGN: 9177 ARIZONA STATE SAVINGS & CREDIT UNION
T05OT01781 Final 07/20/2005 01/18/2006 SIGN SIGN: 9376 ARIZONA STATE SAVINGS & CREDIT UNION
T16OT00276 Final 02/29/2016 10/23/2016 SIGN 2 -NON ILLUM WALL SIGNS & 1- CofC on DP
T21RW04681 Final 10/14/2021 11/20/2021 ROW Remove and replace curb at the NW corner of Park Ave & 1st St, 20 LF of curb and 20 SF of sidewalk
T22RW01127 Final 03/24/2022 04/29/2022 ROW Utility potholing @14 for design of shoring for new underground parking garage in the ROW of 1st St west of Park Ave. ** PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. OTHER ACTIVITIES IN THE AREA, WILL NEED TO COORDINATE TRAFFIC CONTROL SETUP WITH EXISTING SETUP. PAVEMENT PATCH TYPE SHALL BE IN CONFORMANCE TO THE CURRENT EDITION OF THE CITY OF TUCSON PUBLIC UTILITY ADMINISTRATIVE MANUAL.
T22RW02042 Final 06/06/2022 08/09/2022 ROW Gas service permanent abandonment for (1001 N PARK AVE ) Excavate approximately a 5'x5' bell hole , gas main located in asphalt alley to the west of property . Excavation is located approximately 89.4FT North from E 1ST ST center line . *Crews may be working Saturdays from 6:00 am to 3:00 pm. ** PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING PAVEMENT PATCH TYPE SHALL BE IN CONFORMANCE TO THE CURRENT EDITION OF THE CITY OF TUCSON PUBLIC UTILITY ADMINISTRATIVE MANUAL. IN THE EVENT THAT WEEKEND OR AFTER-HOURS WORK IS INTENDED, CONTACT COT INSPECTION STAFF. DAN ROBERTSON AT 520-400-6722 OR TOM ADKINS AT 520-400-3813.

Code Enforcement

Parcel Number - 11504495A
Date - 11/14/2024 5:42 p.m.
Total Number Of Code Cases - 2
Case Number Case Status Entered Date Closed Date Unit Type Description
CE-VIO1123-06556 Closed - unfounded 11/20/2023 11/21/2023 Code Enforcement Case CWOP: Construction Noise after 8p,, possible CWOP (CMO).
T11DV09019 Complian 11/03/2011 N/A DNR_VIOL Caller gave addresses of 1001/1007 E 1st Street: Four overgrown mesquite trees in front of both parcels (2 on each parcel) in between sidewalk and curb area that need to be trimmed.

Plans

Parcel Number - 11504495A
Date - 11/14/2024 5:42 p.m.
Total Number Of Plans - 2
Plan Number Plan Status Application Date Expired Date Unit Type Description
SD-0523-00048 Complete 05/04/2023 N/A Special Districts Main Gate Overlay Design Package for Hub V Project- Minor Change Request
T20PRE0057 Closed 04/24/2020 N/A NEIGHBORHOOD NOTIFICATION Site/Main Gate District: Hub V at Park & First.