Inspection Status: Partial Pass
Inspection History: COT - LCBU - Excavation/Rebar/Zoning
| Date |
Description |
Inspector |
Results |
Comments |
| 08/06/2026 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
Partial pass for tank 1 and 2 footings. |
| 09/17/2026 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
9/17/26: excavation/reinforcement footers at stem wall building verified per F8, F6, F7, F4, F9X2, F5. Canopy building excavation /reinforcement on exterior columns verified per F3, F1X2, F2. Okay for concrete placement at progress areas. |
| 09/29/2026 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
9/29/2026 Partial pass. Cooling tower foundation per plan. Detail SD015. Total of two footers. Okay for concrete placement. |
| 09/30/2026 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
9/30/2026 Partial pass. Verified horizontal reinforcements for cooling tower pads. foundation per. Detail SD015. Okay for concrete placement. |
| 10/08/2026 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Not Ready |
|