Permit: TC-COM-0526-00763
Permit Details
Status:
In Review
Type:
Commercial Building
Address:
8755 S RITA RD BLDG 2
Address NEW:
8755 S RITA RD BLDG 2
Apply Date:
05/22/2026
Applicant:
Charlie Smith
Description:
Wastewater pretreatment facility expansion: 1. New concrete slab with a canopy of approximately 18’ interior eave height (22' peak height) to cover the wastewater process equipment. The sides will be open air. 2. New pre-engineered metal building 54’x37.5’ (2,025 square feet) to house electrical equipment, blowers, & chemical dosing equipment. 3. Two new bolted-steel, open-top, above grade tanks for wastewater equalization (47.5’ diameter and 32.5’ tall) and biological treatment (55.5’ diameter and 24.75’ tall), and two new closed-top FRP sludge storage tanks approximately 13’ diameter and 28’ tall. 4. A new cooling tower (18’ tall) installed on a 12’x12’ concrete slab. Split the Commercial New Building application into (2) separate permits: 1. SEE SEPARATE PERMIT: “Permit #1” two bolted steel wastewater treatment tanks, cooling tower, and sludge storage tanks, and underground piping. Structural foundation and slab design. Special Inspections Certificate form will be submitted prior to Start of Inspections as a deferred submittal. 2. THIS PERMIT: “Permit #2” Slab and erection of the pre-engineered metal building, equipment canopy, and associated building systems designs. Permit #2 broken into “Phase 1” (THIS PERMIT) foundation and slab design to expedite review of the concrete work. Permit #2 Phase 2 (SEE SEPARATE PERMIT) above-grade building/canopy structure, equipment anchorage, and electrical, heating/cooling, and plumbing disciplines.
Permit Reviews
Permit Number - TC-COM-0526-00763
Permit Status: In review
Permit Description: Wastewater pretreatment facility expansion:
1. New concrete slab with a canopy of approximately 18’ interior eave height (22' peak height) to cover the wastewater process equipment. The sides will be open air.
2. New pre-engineered metal building 54’x37.5’ (2,025 square feet) to house electrical equipment, blowers, & chemical dosing equipment.
3. Two new bolted-steel, open-top, above grade tanks for wastewater equalization (47.5’ diameter and 32.5’ tall) and biological treatment (55.5’ diameter and 24.75’ tall), and two new closed-top FRP sludge storage tanks approximately 13’ diameter and 28’ tall.
4. A new cooling tower (18’ tall) installed on a 12’x12’ concrete slab.
Split the Commercial New Building application into (2) separate permits:
1. SEE SEPARATE PERMIT: “Permit #1” two bolted steel wastewater treatment tanks, cooling tower, and sludge storage tanks, and underground piping. Structural foundation and slab design. Special Inspections Certificate form will be submitted prior to Start of Inspections as a deferred submittal.
2. THIS PERMIT: “Permit #2” Slab and erection of the pre-engineered metal building, equipment canopy, and associated building systems designs.
Permit #2 broken into “Phase 1” (THIS PERMIT) foundation and slab design to expedite review of the concrete work. Permit #2 Phase 2 (SEE SEPARATE PERMIT) above-grade building/canopy structure, equipment anchorage, and electrical, heating/cooling, and plumbing disciplines.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/27/2026 | COMMERCIAL REVIEW - FULL v.1 | 06/11/2026 | REQUIRES RESUBMIT |
| 06/11/2026 | COMMERCIAL REVIEW - FULL v.2 | N/A | IN REVIEW |
Outstanding Activity Conditions
Permit Number - TC-COM-0526-00763
Permit Status: In review
Permit Description: Wastewater pretreatment facility expansion:
1. New concrete slab with a canopy of approximately 18’ interior eave height (22' peak height) to cover the wastewater process equipment. The sides will be open air.
2. New pre-engineered metal building 54’x37.5’ (2,025 square feet) to house electrical equipment, blowers, & chemical dosing equipment.
3. Two new bolted-steel, open-top, above grade tanks for wastewater equalization (47.5’ diameter and 32.5’ tall) and biological treatment (55.5’ diameter and 24.75’ tall), and two new closed-top FRP sludge storage tanks approximately 13’ diameter and 28’ tall.
4. A new cooling tower (18’ tall) installed on a 12’x12’ concrete slab.
Split the Commercial New Building application into (2) separate permits:
1. SEE SEPARATE PERMIT: “Permit #1” two bolted steel wastewater treatment tanks, cooling tower, and sludge storage tanks, and underground piping. Structural foundation and slab design. Special Inspections Certificate form will be submitted prior to Start of Inspections as a deferred submittal.
2. THIS PERMIT: “Permit #2” Slab and erection of the pre-engineered metal building, equipment canopy, and associated building systems designs.
Permit #2 broken into “Phase 1” (THIS PERMIT) foundation and slab design to expedite review of the concrete work. Permit #2 Phase 2 (SEE SEPARATE PERMIT) above-grade building/canopy structure, equipment anchorage, and electrical, heating/cooling, and plumbing disciplines.
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 05/27/2026 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. |
Conditions
Permit Number - TC-COM-0526-00763
Permit Status: In review
Permit Description: Wastewater pretreatment facility expansion:
1. New concrete slab with a canopy of approximately 18’ interior eave height (22' peak height) to cover the wastewater process equipment. The sides will be open air.
2. New pre-engineered metal building 54’x37.5’ (2,025 square feet) to house electrical equipment, blowers, & chemical dosing equipment.
3. Two new bolted-steel, open-top, above grade tanks for wastewater equalization (47.5’ diameter and 32.5’ tall) and biological treatment (55.5’ diameter and 24.75’ tall), and two new closed-top FRP sludge storage tanks approximately 13’ diameter and 28’ tall.
4. A new cooling tower (18’ tall) installed on a 12’x12’ concrete slab.
Split the Commercial New Building application into (2) separate permits:
1. SEE SEPARATE PERMIT: “Permit #1” two bolted steel wastewater treatment tanks, cooling tower, and sludge storage tanks, and underground piping. Structural foundation and slab design. Special Inspections Certificate form will be submitted prior to Start of Inspections as a deferred submittal.
2. THIS PERMIT: “Permit #2” Slab and erection of the pre-engineered metal building, equipment canopy, and associated building systems designs.
Permit #2 broken into “Phase 1” (THIS PERMIT) foundation and slab design to expedite review of the concrete work. Permit #2 Phase 2 (SEE SEPARATE PERMIT) above-grade building/canopy structure, equipment anchorage, and electrical, heating/cooling, and plumbing disciplines.
| Date | Description | Comments |
|---|---|---|
| 05/27/2026 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. |