Inspection Status: Passed
Inspection History: COT - HCEL - Electrical Underground
| Date |
Description |
Inspector |
Results |
Comments |
| 02/28/2024 |
COT - HCEL - Electrical Underground |
|
Passed |
|
| 09/18/2023 |
COT - HCEL - Electrical Underground |
|
Partial Pass |
Temporary construction power lines (4 each 2” lines) from transformer to electric panel and disconnect box. Ok to cover progress areas. |
| 09/22/2023 |
COT - HCEL - Electrical Underground |
|
Partial Pass |
Partial pass. Underground electrical conduit to ejector pits, okay to backfill. 9/22/2023 |
| 09/27/2023 |
COT - HCEL - Electrical Underground |
|
Partial Pass |
Temporary construction power for site: crane, trailers, general building site. Transformer, disconnects, service panels. OK to energize system. |
| 09/28/2023 |
COT - HCEL - Electrical Underground |
|
Partial Pass |
Lines from crane to disconnect. Ok to energize,system and install a meter. |
| 10/02/2023 |
COT - HCEL - Electrical Underground |
|
Partial Pass |
Lines from mobile generator to temporary power panel and disconnect. |
| 10/05/2023 |
COT - HCEL - Electrical Underground |
|
Not Ready |
|