Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Passed
Inspection History: COT - HCBU - Excavation/Rebar/Zoning
Permit Number - T22CM05823
Inspection Description - COT - HCBU - Excavation/Rebar/Zoning
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/28/2024 | COT - HCBU - Excavation/Rebar/Zoning | Passed | ||
08/09/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Pre-construction meeting at job site. | |
08/11/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Stairwell #2 footing at GL: E/3.7 - 4, E - F.5. OK to place concrete in progress areas. | |
08/16/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Spread footings at 2/I, F8, CC6, F10 CC12/J. OK to place,concrete in progress areas. | |
08/17/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Elevator footing/columns at GL: H/3.7 - 4. Footing at GL: H/4. OK to place concrete in progress areas | |
08/18/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Footings/columns at GL: F8 CC6 I/2, F10 CC1 J/2, FB3CC9 K/2, FB3 CC9 M/2, FB2 CC1 L/2.8, FB2 CC1 M/2.8, FB2 CC1 L/4, FB2 CC1 M/4, Footing at GL; G - H/3.7. OK to place concrete in progress areas. | |
08/23/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Columns at GL: 2.8/B.6, 2.2/B.6. Column footings at GL: 1.2/B.6, 1.2/C, E.2/2, G/1.4, G.8/2, G.8/1.2, 1.4/I, 3/G, 3/E. OK to place concrete in progress areas. | |
08/25/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Columns at GL: M/4, L/4, L/2.8. Shear wall at H3 - H4 (elevator pit). Footings at GL:C/4, C/5, B.7/6, B.7/7, E/5, F/5, B/6, B/7, A.1/3, E.2/7, A/5, A.1/5.4, 1.1/E.2. OK to place concrete in progress areas. | |
08/29/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | South wall at GL: 2.8 - 4/N. Columns at GL: M/4, M/2.8, L/2.8. Shear wall at H/3 - 4 (elevator pit). Footings at C/4, C/5.1, B.7/6, B.7/7, E/5, F/6, D/6, D.7. OK to place concrete in progress areas. | |
08/31/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Columns at GL: 5.1/G.8, 5.1/J, 6/F, 7/F. Perimeter wall at GL: 2/L - I. OK to place concrete in progress areas. | |
09/01/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | West perimeter wall at GL: H.6 - H/1.1, G.I - G/1.1, G - E.2/1. OK to set forms and place concrete. | |
09/05/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | west retaining wall at GL: I/2. I/1.1. Columns at GL: G/2, G.2/2, C/2.2, B/2.2, B/2.8, I/2, OK to set forms and place concrete in progress areas. | |
09/06/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Retaining wall at GL: G - A.1/1. Columns at GL: C/1.1, B/1.1. OK to set forms and place concrete. | |
09/07/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Columns at GL: G.3/6, G.3/7, G/3, H/7, F.2/7.1, F.4/7.1. Footings at L/5.3, M/5.3, N/5.1 - 5.4, K.T - N. OK to place concrete in progress areas. | |
09/08/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | West wall at GL; 1.8 - 2.4, L - , K - L. North wall at,GL; 1 - 3.7/A.1. OK to set forms and place concrete. | |
09/11/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Spread footings and dowels at GL: J/6, FB10 CC1, CC L/6, FB2 CC10, K/7, J/6, H - N/7, N/5.3 - 7.1, J/6, L/6; core wall at J/5.2 - 4.2. Ok to place concrete in progress areas. | |
09/12/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Stairwell B, North wall. Ok to set forms and place concrete. | |
09/15/2023 | COT - HCBU - Excavation/Rebar/Zoning | Not Ready | Contractor cancelled. | |
09/18/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Vertical columns at GL: H/4, H/6.4, H/3, G - H/3.7, A/4, C/4, C/5.1, F/7, D/7, F/7, E/5, H/6, H/5, J/6, M/5. Perimeter wall at 7.1/A - F. OK to set forms and place concrete. | |
09/19/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | South elevator West and Northwest walls. Ok to set forms and place concrete. | |
09/20/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Epoxy placement was observed by special inspector. | |
09/22/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | North and west stair shear wall grid line 3.7 - 4. Columns G.8 - 2, G - 3, and E. 3. Okay for concrete placement. 9/22/2023 |
|
09/26/2023 | COT - HCBU - Excavation/Rebar/Zoning | Not Ready | Contractor cancelled. | |
09/27/2023 | COT - HCBU - Excavation/Rebar/Zoning | Not Ready | Contractor cancelled. | |
09/28/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Southeast site wall at GL: 7.8/N - F. OK to set forms and place concrete. | |
09/29/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Columns at GL: D/6, B.6/6, G/5, G.3/6, D.3/7, H/7, L/5.3, J/5. Exterior South wall at GL: N/5.2 - 7.1. OK to set forms and place concrete. | |
10/02/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | ||
10/04/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Columns at GL: K/7, F/6, F/5.1. OK to set forms and place concrete. Plumbing underground: waste lines (4” - 6”) in Southeast portion of site. Ok to cover progress areas. | |
10/09/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Slab on grade #1 at GL: 1 - 4.1/A.1, A.1/N, 2 -4.1/N. OK to place concrete in progress areas. | |
10/13/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Columns at GL: K/7, N/2. OK to set forms and place concrete. | |
10/17/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Northeast to Southeast slab, #4 wire mesh reinforcement throughout. Rebar backing at all columns, first portion of ramp. Ok to place concrete in progress areas. | |
10/24/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | North and west stair shear wall grid line 3.7 - 4. Columns G.8 - 2, G - 3, and E. 3. Okay for concrete placement. 9/22/2023 10/24/23:Slab on grade for North stairwell (3.7-4 on line E) & 8" concrete wall below ramp (F.2 to G on line 3.7) |
|
11/01/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | North and west stair shear wall grid line 3.7 - 4. Columns G.8 - 2, G - 3, and E. 3. Okay for concrete placement. 9/22/2023 10/24/23:Slab on grade for North stairwell (3.7-4 on line E) & 8" concrete wall below ramp (F.2 to G on line 3.7) 11/1/23: Level 1slab Pour #2 Gridline: A-G and 1-5.1 & beams: BM04, BM06, BM15, BM08 reinforcement per plan ok to proceed. |
|
11/03/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Level #1 columns at GL: G/3, G/2, G/1.1, E.2/1.1, C/1.1, B/1.1, B/2.2, B/2.8, A.2/4, C/4, C/2.2. Ok to set forms and place,concrete in progress areas. | |
11/06/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Columns at GL: B/2.8, E/3, E/2. Electric underground beams for electric conduit to main electric room. Ok to place concrete in progress areas. | |
11/08/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Level #1; pour #3, double mat rebar at GL: 5 - 7/A - G.3; 4 -5/G -G.8. OK to place concrete in progress areas. Underground electric beam at L - H/2 -2.8. OK to place concrete in progress areas. | |
11/22/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Level #1 columns on GL: I/2, J/2, H.6/3.9, H/6, H/7, L/2.8, G.8/1. Ok to set forms and place concrete. | |
12/01/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Columns at GL: A.2/7, A.2/5.9, A.2/5.4, A.2/5.1, F/7, G/5.1, G/3.7, G/3, G/2, G/1.1, E.2/2, E.2/1.1. OK to set forms and place concrete in progress areas. | |
12/05/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Column (Exterior “Y”) on GL: K at 8’4”. Ok to set forms and place concrete in progress areas. | |
12/07/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Level #1, Columns at GL: L/4, M/4, M/2.8, J/2, G.8/2, G.8/1, H/3, H.6/3.9, H/4. OK to set forms and place concrete. |