Inspection Status: Passed
Inspection History: COT - HCBU - Stem Wall/Retaining Wall
Permit Number - T22CM05823
Inspection Description - COT - HCBU - Stem Wall/Retaining Wall
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/28/2024 | COT - HCBU - Stem Wall/Retaining Wall | Passed | ||
02/28/2024 | COT - HCBU - Stem Wall/Retaining Wall | Passed | ||
02/28/2024 | COT - HCBU - Stem Wall/Retaining Wall | Passed | ||
08/10/2023 | COT - HCBU - Stem Wall/Retaining Wall | Partial Pass | Tower base at GL: G/3 - 5.4, Stair way # at GL: J/3 - 4.1. OK to place concrete. | |
09/13/2023 | COT - HCBU - Stem Wall/Retaining Wall | Partial Pass | North perimeter wall at GL: A.1/2.8 - 7.1. Columns at GL: 4/A.1, 4/A.1, 5.4/A.1, A.1/5.9, 7/A.1. OK to set forms and place concrete in progress areas. | |
09/21/2023 | COT - HCBU - Stem Wall/Retaining Wall | Partial Pass | Basement ramp wall detail 17 s5.10 rebar per plan. Two west walls and south wall okay for concrete placement. 9/21/2023 | |
09/25/2023 | COT - HCBU - Stem Wall/Retaining Wall | Partial Pass | ||
10/16/2023 | COT - HCBU - Stem Wall/Retaining Wall | Not Ready | Contractor cancelled | |
10/20/2023 | COT - HCBU - Stem Wall/Retaining Wall | Partial Pass | Crash walls and stair walls at North side of ramp. Ok to place concrete in progress areas. | |
COT - HCBU - Stem Wall/Retaining Wall | Partial Pass | Basement ramp wall detail 17 s5.10 rebar per plan. Two west walls and south wall okay for concrete placement. 9/21/2023 10/25/23: level one ramp reinforcement per plan G.8-G/1-3.7 |
||
10/25/2023 | COT - HCBU - Stem Wall/Retaining Wall | Partial Pass | 10/25/23: level one ramp reinforcement per plan G.8-G/1-3.7 | |
10/25/2023 | COT - HCBU - Stem Wall/Retaining Wall | Partial Pass | 10/25/23: level one ramp reinforcement per plan G.8-G/1-3.7 | |
11/02/2023 | COT - HCBU - Stem Wall/Retaining Wall | Not Ready | Contractor cancelled: slab concrete not cured enough to work on. Will reschedule for 3 November. |