Permit: T21CM09453

Parcel: 11620637A


Addresses:

165 S LINDA AV


Inspection Status: Partial Pass

Inspection History: COT - HCBU - Interior Shear Bracing 

Permit Number - T21CM09453

Inspection Description - COT - HCBU - Interior Shear Bracing 

Inspection Status - Partial Pass

Date Description Inspector Results Comments
02/21/2025 COT - HCBU - Interior Shear Bracing  Partial Pass 2/21/25: partial pass for shear walls 2nd floor Area A,
03/05/2025 COT - HCBU - Interior Shear Bracing  Partial Pass Level #3, Areas A & B: shear wall system at interior walls in units, exterior walls, hallway walls. Ok to cover progress areas.
03/12/2025 COT - HCBU - Interior Shear Bracing  Partial Pass North building shear walls in room units and corridors. Ok to,cover progress areas.
04/04/2025 COT - HCBU - Interior Shear Bracing  Not Ready
04/11/2025 COT - HCBU - Interior Shear Bracing  Partial Pass 2/21/25: partial pass for shear walls 2nd floor Area A,
4/11/25: 5th floor interior shear walls passed.
05/02/2025 COT - HCBU - Interior Shear Bracing  Partial Pass Building A, Level #3, Room Units 346, 347, 348, 349, 350 sheet rock nailing. Ok to tape progress areas.
05/05/2025 COT - HCBU - Interior Shear Bracing  Partial Pass Level #3, Areas A and B ; sheet rock nailing for Room Units; 340, 352, 353, 364, 355, 356, 357, 358, 359, 360. Ok to,tape progress areas.
05/15/2025 COT - HCBU - Interior Shear Bracing  Not Ready
05/28/2025 COT - HCBU - Interior Shear Bracing  Re-inspection required 2/21/25: partial pass for shear walls 2nd floor Area A,
4/11/25: 5th floor interior shear walls passed.
5/28/25: room #431,432,433,434,435,436,438,439,440 inspected. All fasteners shall be no closer than 3/8" from edge of sheathing and shall penetrate no more than 1/8".
06/02/2025 COT - HCBU - Interior Shear Bracing  Not Ready
06/04/2025 COT - HCBU - Interior Shear Bracing  Partial Pass 6/4/2025 partial pass. Units 329,330,331,332,333,334,335,336,337,338,&339. 1st layer at 2hr rated walls approved. Ceilings okay for tape and mud for drop ceilings. Fire caulk all penetrations through ceiling prior to framing. Extend receptacle boxes throughout. Max depth recessed into drywall is 1/4". All fasteners shall be no closer than 3/8" from edge of sheathing and shall penetrate no more than 1/8".
06/11/2025 COT - HCBU - Interior Shear Bracing  Partial Pass 6/11/2025 Drywall Nail at level 4th Section B approved. Okay to proceed with second layer at firewalls.
06/18/2025 COT - HCBU - Interior Shear Bracing  Partial Pass 6-18-25: anchor tie systems/hold-downs at Area C-room's 304, 306, 305, 307, 308, 310, 311, 312, 327, 325, 302, 304 verified per plans. Okay to continue with construction at progress areas.
06/24/2025 COT - HCBU - Interior Shear Bracing  Partial Pass Level #1 Stairwell at Levels 1 - 5. Sheet rock nailing in fire truck turn-around area and mechanical room. Ok to,tape first level and apply second layer.
07/02/2025 COT - HCBU - Interior Shear Bracing  Partial Pass 2/21/25: partial pass for shear walls 2nd floor Area A,
4/11/25: 5th floor interior shear walls passed.
5/28/25: room #431,432,433,434,435,436,438,439,440 inspected. All fasteners shall be no closer than 3/8" from edge of sheathing and shall penetrate no more than 1/8".

6/4/2025 partial pass. Units 329,330,331,332,333,334,335,336,337,338,&339. 1st layer at 2hr rated walls approved. Ceilings okay for tape and mud for drop ceilings. Fire caulk all penetrations through ceiling prior to framing. Extend receptacle boxes throughout. Max depth recessed into drywall is 1/4". All fasteners shall be no closer than 3/8" from edge of sheathing and shall penetrate no more than 1/8".

6/11/2025 Drywall Nail at level 4th Section B approved. Okay to proceed with second layer at firewalls.
6-18-25: anchor tie systems/hold-downs at Area C-room's 304, 306, 305, 307, 308, 310, 311, 312, 327, 325, 302, 304 verified per plans. Okay to continue with construction at progress areas.
7/2/25:drywall fastened per Schedule at rooms 126,171 first layer north walls,122 second layer,
07/09/2025 COT - HCBU - Interior Shear Bracing  Partial Pass 2/21/25: partial pass for shear walls 2nd floor Area A,
4/11/25: 5th floor interior shear walls passed.
5/28/25: room #431,432,433,434,435,436,438,439,440 inspected. All fasteners shall be no closer than 3/8" from edge of sheathing and shall penetrate no more than 1/8".

6/4/2025 partial pass. Units 329,330,331,332,333,334,335,336,337,338,&339. 1st layer at 2hr rated walls approved. Ceilings okay for tape and mud for drop ceilings. Fire caulk all penetrations through ceiling prior to framing. Extend receptacle boxes throughout. Max depth recessed into drywall is 1/4". All fasteners shall be no closer than 3/8" from edge of sheathing and shall penetrate no more than 1/8".

6/11/2025 Drywall Nail at level 4th Section B approved. Okay to proceed with second layer at firewalls.
6-18-25: anchor tie systems/hold-downs at Area C-room's 304, 306, 305, 307, 308, 310, 311, 312, 327, 325, 302, 304 verified per plans. Okay to continue with construction at progress areas.
7/2/25:drywall fastened per Schedule at rooms 126,171 first layer north walls,122 second layer,
7/9/25: interior shear wall OSB at S102,S104,S105,S107, commercial (S162,S163,S164,S165),S110, S127, S112, approved.
07/11/2025 COT - HCBU - Interior Shear Bracing  Partial Pass Areas C & D rooms and corridor shear walls. OK to insulate and cover.
07/21/2025 COT - HCBU - Interior Shear Bracing  Partial Pass 2/21/25: partial pass for shear walls 2nd floor Area A,
4/11/25: 5th floor interior shear walls passed.
5/28/25: room #431,432,433,434,435,436,438,439,440 inspected. All fasteners shall be no closer than 3/8" from edge of sheathing and shall penetrate no more than 1/8".

6/4/2025 partial pass. Units 329,330,331,332,333,334,335,336,337,338,&339. 1st layer at 2hr rated walls approved. Ceilings okay for tape and mud for drop ceilings. Fire caulk all penetrations through ceiling prior to framing. Extend receptacle boxes throughout. Max depth recessed into drywall is 1/4". All fasteners shall be no closer than 3/8" from edge of sheathing and shall penetrate no more than 1/8".

6/11/2025 Drywall Nail at level 4th Section B approved. Okay to proceed with second layer at firewalls.
6-18-25: anchor tie systems/hold-downs at Area C-room's 304, 306, 305, 307, 308, 310, 311, 312, 327, 325, 302, 304 verified per plans. Okay to continue with construction at progress areas.
7/2/25:drywall fastened per Schedule at rooms 126,171 first layer north walls,122 second layer,
7/9/25: interior shear wall OSB at S102,S104,S105,S107, commercial (S162,S163,S164,S165),S110, S127, S112, approved.
7/21/25: Level 3 units in section C approved.