Inspection History Details
Inspection Status: Not Ready
Inspection History: COT - HCPL - Plumbing Above Ceiling
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/03/2026 | COT - HCPL - Plumbing Above Ceiling | Not Ready | ||
| 02/23/2026 | COT - HCPL - Plumbing Above Ceiling | Partial Pass | Commercial suites at North Building. Ok to set ceiling tiles. | |
| 03/09/2026 | COT - HCPL - Plumbing Above Ceiling | Not Ready | ||
| 04/09/2026 | COT - HCPL - Plumbing Above Ceiling | Re-inspection required | 4-9-26: MEP's at 1st. floor corridor (south side Courtyard A)-fire caulk penetrations at west end of corridor and above elevator, add supports to DWV at intervals of 4', add clamps to secure AWG wires every 4', fire caulk horizontal penetrations at corridor rated walls. Room's 508, 507-flex is severely crush and repairs shall be made to avoid loss of airflow, 506-add a support to exhaust in bedroom to avoid sagging, 505-seal opening above ceiling with drywall at bedroom, add supports to hvac whip and remove from ceiling grid. Per NEC 300.1.1(B), awg wires cannot be zip tied to ceiling grids-make corrections by adding supports using an independent approved method (applies to room's 508, 507, 506, and 505). | |
| 04/14/2026 | COT - HCPL - Plumbing Above Ceiling | Partial Pass | 4/14/26: ABOVE CEILING IN CORRIDOR A approved in north building ok to proceed. | |
| 04/22/2025 | COT - HCPL - Plumbing Above Ceiling | Canceled | ||
| 04/28/2026 | COT - HCPL - Plumbing Above Ceiling | Partial Pass | Above at drop ceilings approved in rooms 527,525,524,501,502,503,506,508. Okay to proceed progress areas. Re walk 504,505,507 4/28/2026 |
|
| 04/29/2026 | COT - HCPL - Plumbing Above Ceiling | Partial Pass | 4/29/2026 Re walk 504,507,515,520 505,528,512,513,514,517,518,519 401&402 in wall MEP approved. |
|
| 05/01/2026 | COT - HCPL - Plumbing Above Ceiling | Partial Pass | 5/1/2026 All corrections were made in rooms 504,507,515. Above ceiling at drop lids. Pending 520. Okay to proceed progress areas. |
|
| 06/17/2025 | COT - HCPL - Plumbing Above Ceiling | Partial Pass | 6-17-25: plumbing above ceiling in room's (pex lines) 531, 532, 534, 533, 535, 536, 538 verified per plans and under test. Penetrations at top plates fire caulked and pex lines properly supported. Okay to continue with construction at progress areas. | |
| 08/01/2025 | COT - HCPL - Plumbing Above Ceiling | Partial Pass | Domestic water lines and fire sprinkler lines in trash chutes on Level #5. | |
| 10/16/2024 | COT - HCPL - Plumbing Above Ceiling | Partial Pass | Level #1, Area B, rooms 131 and 142 waste lines for tubs above. | |
| 10/24/2024 | COT - HCPL - Plumbing Above Ceiling | Partial Pass | Level #1, Room,units S133, S135, S138, S139, S140, S157, S158, S160. | |
| 10/29/2024 | COT - HCPL - Plumbing Above Ceiling | Partial Pass | Level #1, room units S131, S143< S144, S148, S159. |