Permit: T21CM09453

Parcel: 11620637A


Addresses:

165 S LINDA AV

Inspection Status: Not Ready

Inspection History: COT - HCPL - Plumbing Above Ceiling

Date Description Inspector Results Comments
02/03/2026 COT - HCPL - Plumbing Above Ceiling Not Ready
02/23/2026 COT - HCPL - Plumbing Above Ceiling Partial Pass Commercial suites at North Building. Ok to set ceiling tiles.
03/09/2026 COT - HCPL - Plumbing Above Ceiling Not Ready
04/09/2026 COT - HCPL - Plumbing Above Ceiling Re-inspection required 4-9-26: MEP's at 1st. floor corridor (south side Courtyard A)-fire caulk penetrations at west end of corridor and above elevator, add supports to DWV at intervals of 4', add clamps to secure AWG wires every 4', fire caulk horizontal penetrations at corridor rated walls. Room's 508, 507-flex is severely crush and repairs shall be made to avoid loss of airflow, 506-add a support to exhaust in bedroom to avoid sagging, 505-seal opening above ceiling with drywall at bedroom, add supports to hvac whip and remove from ceiling grid. Per NEC 300.1.1(B), awg wires cannot be zip tied to ceiling grids-make corrections by adding supports using an independent approved method (applies to room's 508, 507, 506, and 505).
04/14/2026 COT - HCPL - Plumbing Above Ceiling Partial Pass 4/14/26: ABOVE CEILING IN CORRIDOR A approved in north building ok to proceed.
04/22/2025 COT - HCPL - Plumbing Above Ceiling Canceled
04/28/2026 COT - HCPL - Plumbing Above Ceiling Partial Pass Above at drop ceilings approved in rooms 527,525,524,501,502,503,506,508. Okay to proceed progress areas.
Re walk 504,505,507 4/28/2026
04/29/2026 COT - HCPL - Plumbing Above Ceiling Partial Pass 4/29/2026 Re walk 504,507,515,520
505,528,512,513,514,517,518,519
401&402 in wall MEP approved.
05/01/2026 COT - HCPL - Plumbing Above Ceiling Partial Pass 5/1/2026 All corrections were made in rooms 504,507,515. Above ceiling at drop lids.
Pending 520. Okay to proceed progress areas.
06/17/2025 COT - HCPL - Plumbing Above Ceiling Partial Pass 6-17-25: plumbing above ceiling in room's (pex lines) 531, 532, 534, 533, 535, 536, 538 verified per plans and under test. Penetrations at top plates fire caulked and pex lines properly supported. Okay to continue with construction at progress areas.
08/01/2025 COT - HCPL - Plumbing Above Ceiling Partial Pass Domestic water lines and fire sprinkler lines in trash chutes on Level #5.
10/16/2024 COT - HCPL - Plumbing Above Ceiling Partial Pass Level #1, Area B, rooms 131 and 142 waste lines for tubs above.
10/24/2024 COT - HCPL - Plumbing Above Ceiling Partial Pass Level #1, Room,units S133, S135, S138, S139, S140, S157, S158, S160.
10/29/2024 COT - HCPL - Plumbing Above Ceiling Partial Pass Level #1, room units S131, S143< S144, S148, S159.