Permit: T21CM09453

Parcel: 11620637A


Addresses:

165 S LINDA AV

Inspection Status: Partial Pass

Inspection History: COT - HCME - Mechanical Progress 

Date Description Inspector Results Comments
02/06/2026 COT - HCME - Mechanical Progress  Partial Pass 2/6/26: MEP 4TH FLOOR AREA C 427,425,424,401,408,407,405, 406,404,427,425,424,404,426,428,412,413,414,415,416, 418,417, 419,420
03/09/2026 COT - HCME - Mechanical Progress  Not Ready
06/08/2026 COT - HCME - Mechanical Progress  Partial Pass 5th floor all corridors section B. Dropped ceilings approved. Okay to proceed progress areas. 6/8/2026
06/11/2026 COT - HCME - Mechanical Progress  Not Ready
06/18/2026 COT - HCME - Mechanical Progress  Partial Pass 6.18.26
HVAC refrigerant lines running A2L Freon will need to be in a shaft.
06/30/2026 COT - HCME - Mechanical Progress  Partial Pass Partial pass 2nd floor MEP approved units 210, 211. 6/30/2026
07/07/2026 COT - HCME - Mechanical Progress  Partial Pass Partial pass. 2nd floor MEP approved in units 213, 214,215,216,218,217. 7/7/2026
07/10/2026 COT - HCME - Mechanical Progress  Partial Pass Partial pass. MEP approved 2nd floor units 219,220,221,222. 7/10/2026
07/16/2026 COT - HCME - Mechanical Progress  Not Ready
07/22/2026 COT - HCME - Mechanical Progress  Not Ready
07/28/2026 COT - HCME - Mechanical Progress  Partial Pass 7-28-26: Inspection of MEP's above ceiling at garage entryway- add ground screws to 6-metal boxes. Penetrations above ceiling grid properly fire caulked and DWV supported. Will need to verify ground screws but okay to continue with construction at progress areas.