Date Description Inspector Results Comments
01/05/2024 COT - HCBU - Preslab   Partial Pass Podium, Placement,#8, bottom rebar mat. Ensure stirrups are properly placed in beam areas.
01/22/2024 COT - HCBU - Preslab   Not Ready Contractor cancelled due to inclement weather.
02/01/2024 COT - HCBU - Preslab   Partial Pass Podium at placement #10, bottom mat. Ok to place concrete in progress areas
02/14/2024 COT - HCBU - Preslab   Partial Pass Slab area #10. Ok to place concrete in progress areas.
07/06/2023 COT - HCBU - Preslab   Partial Pass This inspection is for excavation/layout rebar for concrete column footings at HL: H/11 (F2), I/11 (F2), J/11 (F4). Ok to place concrete in progress areas.
07/10/2023 COT - HCBU - Preslab   Partial Pass Area A, Elevator #2 footings. Ok to place concrete in progress areas. Column footings (F2, F4) at GL: J/8, L/1O, M/10, L/12, I/12, H/12, G/11, K/10.
09/20/2023 COT - HCBU - Preslab   Partial Pass Plumbing underground in Areas A & B; 4” waste lines. Ok to cover progress areas.
10/12/2023 COT - HCBU - Preslab   Partial Pass North west portion of Areas A & B. Ok to place concrete in progress areas.
11/03/2023 COT - HCBU - Preslab   Partial Pass Level #1, Area B: Top and bottom rebar mat. Followed plans are per Asst Superintendent Keven, checked as closely as possible. Ok to place concrete in progress areas.
11/06/2023 COT - HCBU - Preslab   Partial Pass Area B, pour #1, top and bottom rebar mesh in place. Ok to place concrete in progress areas.
11/09/2023 COT - HCBU - Preslab   Not Ready Contractor cancelled. Will reschedule for 13 November
11/13/2023 COT - HCBU - Preslab   Partial Pass Area B placement #2 bottom mat (areas except for West side of slab).
11/16/2023 COT - HCBU - Preslab   Partial Pass Area B - A, placement #2; top rebar mat and hold downs. Ok to place concrete in progress areas.
11/17/2023 COT - HCBU - Preslab   Partial Pass Podium area, placements #3; bottom mat and hold-downs. Ensure all add,on rebars are properly tied down and all hold downs are in place.
11/28/2023 COT - HCBU - Preslab   Partial Pass Level #1, concrete placement #4, bottom mat of double mat rebar system. Ensure hold downs are in place as per plans. Ok to place concrete in progress areas.
11/29/2023 COT - HCBU - Preslab   Partial Pass Area A, Placement #4; Podium area. Ok to place concrete in progress areas.
11/30/2023 COT - HCBU - Preslab   Partial Pass Slab on grade for placement #6. Ok to place concrete in progress areas.
12/07/2023 COT - HCBU - Preslab   Partial Pass Slab areas A and B, pour #5 bottom mat.
12/14/2023 COT - HCBU - Preslab   Partial Pass Bottom mat for Area A/B, pour #6.
12/19/2023 COT - HCBU - Preslab   Partial Pass Podium area,double Matt for placement,#6. Ok to place concrete in progress areas.
12/21/2023 COT - HCBU - Preslab   Partial Pass Podium area at placement #6; information only.
12/28/2023 COT - HCBU - Preslab   Partial Pass Podium, placement #7 in areas C & D. Ok to place concrete in progress areas.