Permit: T21CM09453

Parcel: 11620637A


Addresses:

165 S LINDA AV

Inspection Status: Partial Pass

Inspection History: COT - HCEL - Electrical Progress  

Date Description Inspector Results Comments
01/09/2025 COT - HCEL - Electrical Progress   Partial Pass Level #2, Section A room units: s330, s329, s356, s358, s360, s340, s339, s338, S337, S336, S335, S333, S334, S331.
01/14/2025 COT - HCEL - Electrical Progress   Partial Pass Level #3, Area B room units in North building.
01/29/2025 COT - HCEL - Electrical Progress   Partial Pass In wall electric for rooms #129, 130, 119, 112, 113.
02/06/2026 COT - HCEL - Electrical Progress   Partial Pass 2/6/26: MEP 4TH FLOOR AREA C 427,425,424,401,408,407,405, 406,404,427,425,424,404,426,428,412,413,414,415,416, 418,417, 419,420
02/11/2025 COT - HCEL - Electrical Progress   Partial Pass Rooms #235 and 237.
03/09/2026 COT - HCEL - Electrical Progress   Not Ready
03/19/2025 COT - HCEL - Electrical Progress   Not Ready 3/19/25: section A rooms, 431,432,434,433,435,436,439,440 ( Not ready will need to re-inspect rooms)
03/25/2025 COT - HCEL - Electrical Progress   Re-inspection required 3/19/25: section A rooms, 431,432,434,433,435,436,439,440 ( Not ready will need to re-inspect rooms)
3/25/25: Section A 4th floor rooms (441,460,459,458,457,456) not ready multiple issues need to be addressed prior to re-inspection. 3rd floor room 352 not ready
03/28/2025 COT - HCEL - Electrical Progress   Re-inspection required 3/19/25: section A rooms, 431,432,434,433,435,436,439,440 ( Not ready will need to re-inspect rooms)
3/25/25: Section A 4th floor rooms (441,460,459,458,457,456) not ready multiple issues need to be addressed prior to re-inspection. 3rd floor room 352 not ready
3/28/25: Section B 4th floor rooms (455,454,453,452,451,450,449,448,446) Not ready multiple issues need to be addressed prior to re-inspection.
04/03/2025 COT - HCEL - Electrical Progress   Re-inspection required (with fee) 3/19/25: section A rooms, 431,432,434,433,435,436,439,440 ( Not ready will need to re-inspect rooms)
3/25/25: Section A 4th floor rooms (441,460,459,458,457,456) not ready multiple issues need to be addressed prior to re-inspection. 3rd floor room 352 not ready
3/28/25: Section B 4th floor rooms (455,454,453,452,451,450,449,448,446) Not ready multiple issues need to be addressed prior to re-inspection.
4/3/25: Re-inspection required with fee
04/14/2026 COT - HCEL - Electrical Progress   Partial Pass
05/01/2025 COT - HCEL - Electrical Progress   Partial Pass 3/19/25: section A rooms, 431,432,434,433,435,436,439,440 ( Not ready will need to re-inspect rooms)
3/25/25: Section A 4th floor rooms (441,460,459,458,457,456) not ready multiple issues need to be addressed prior to re-inspection. 3rd floor room 352 not ready
3/28/25: Section B 4th floor rooms (455,454,453,452,451,450,449,448,446) Not ready multiple issues need to be addressed prior to re-inspection.
4/3/25: Re-inspection required with fee
5/1/25: Electrical intermediate in rooms 557,558,559,560,536 approved.
05/08/2026 COT - HCEL - Electrical Progress   Partial Pass 5/8/2026 partial pass. BHA1,1HA1,1HA2. SES A & B sector house panel. Letter of torque was provided. All raceways have been sealed. Lock out tag out has been provided for those not in use.
05/12/2026 COT - HCEL - Electrical Progress   Not Ready
05/13/2025 COT - HCEL - Electrical Progress   Not Ready 3/19/25: section A rooms, 431,432,434,433,435,436,439,440 ( Not ready will need to re-inspect rooms)
3/25/25: Section A 4th floor rooms (441,460,459,458,457,456) not ready multiple issues need to be addressed prior to re-inspection. 3rd floor room 352 not ready
3/28/25: Section B 4th floor rooms (455,454,453,452,451,450,449,448,446) Not ready multiple issues need to be addressed prior to re-inspection.
4/3/25: Re-inspection required with fee
5/1/25: Electrical intermediate in rooms 557,558,559,560,536 approved.
5/13/25:not ready
06/08/2026 COT - HCEL - Electrical Progress   Partial Pass 5th floor all corridors section B. Dropped ceilings approved. Okay to proceed progress areas. 6/8/2026
06/11/2026 COT - HCEL - Electrical Progress   Not Ready
06/22/2026 COT - HCEL - Electrical Progress   Canceled 6-22-26: canceled.
06/23/2025 COT - HCEL - Electrical Progress   Partial Pass 3/19/25: section A rooms, 431,432,434,433,435,436,439,440 ( Not ready will need to re-inspect rooms)
3/25/25: Section A 4th floor rooms (441,460,459,458,457,456) not ready multiple issues need to be addressed prior to re-inspection. 3rd floor room 352 not ready
3/28/25: Section B 4th floor rooms (455,454,453,452,451,450,449,448,446) Not ready multiple issues need to be addressed prior to re-inspection.
4/3/25: Re-inspection required with fee
5/1/25: Electrical intermediate in rooms 557,558,559,560,536 approved.
5/13/25:not ready
6/23/25: electrical intermediate in walls approved in room 539,540,541,560,558,556,557,555,554,551,550,548,549.
06/30/2026 COT - HCEL - Electrical Progress   Partial Pass Partial pass 2nd floor MEP approved units 210, 211. 6/30/2026
07/07/2026 COT - HCEL - Electrical Progress   Partial Pass Partial pass. 2nd floor MEP approved in units 213, 214,215,216,218,217. 7/7/2026
07/10/2026 COT - HCEL - Electrical Progress   Partial Pass Partial pass. MEP approved 2nd floor units 219,220,221,222. 7/10/2026
07/16/2026 COT - HCEL - Electrical Progress   Not Ready
07/22/2026 COT - HCEL - Electrical Progress   Not Ready
07/28/2026 COT - HCEL - Electrical Progress   Partial Pass 7-28-26: Inspection of MEP's above ceiling at garage entryway- add ground screws to 6-metal boxes. Penetrations above ceiling grid properly fire caulked and DWV supported. Will need to verify ground screws but okay to continue with construction at progress areas.
08/01/2024 COT - HCEL - Electrical Progress   Partial Pass Wiring for lighting in corridors #160, and West courtyard corridors. Additional inspections; corridors above ceilings as per details #5 and #7; RC channel in corridors into restrooms 107, 108, 127, 128. Ok to sheet rock progress areas in corridors, walls and,ceilings. Mechanical shafts near rooms 155 and 132.
10/23/2024 COT - HCEL - Electrical Progress   Not Ready Will reschedule for 24 October.
10/24/2024 COT - HCEL - Electrical Progress   Partial Pass Level #1 Room units: S133, S135, S138, S139, S140, S157, S158, S160
10/28/2024 COT - HCEL - Electrical Progress   Partial Pass Level #1, room units 141, 143, 144, 148, 159.
12/06/2024 COT - HCEL - Electrical Progress   Not Ready Contractor cancelled; will reschedule for 9 December
12/10/2024 COT - HCEL - Electrical Progress   Partial Pass Level #2 Room Units: S229, S230, S231, S232, S233, S234, S235, S236, S238, S239, S240, S241, S256, S258, S260
12/13/2024 COT - HCEL - Electrical Progress   Partial Pass In wall electric on Level #2, Area B; Room units S243, S244, S245, S249, S250, S251, S252, S253, S254, S255.
12/15/2025 COT - HCEL - Electrical Progress   Partial Pass
12/23/2024 COT - HCEL - Electrical Progress   Partial Pass In wall electric in units 148, 150.