Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T21CM09453

Parcel: 11620637A


Addresses:

165 S LINDA AV


Inspection Status: Partial Pass

Inspection History: COT - HCBU - Framing

Permit Number - T21CM09453

Inspection Description - COT - HCBU - Framing

Inspection Status - Partial Pass

Date Description Inspector Results Comments
01/03/2025 COT - HCBU - Framing Partial Pass Level #1, Area A room unit #107 - MEP. OK to insulate and cover walls. Level #2, Areas A and B courtyard overlook in corridors; straps and walls covered. Levels 3 - 5 not ready.
02/10/2025 COT - HCBU - Framing Partial Pass North building: pitched roofs, nailing in place, Ok to dry-in progress areas. South building (flat roofs) at areas A & B OK to dry-in roof systems.
02/11/2025 COT - HCBU - Framing Partial Pass Rooms #235 and 237.
02/24/2025 COT - HCBU - Framing Partial Pass Level #1: Fire Truck turn-around Titan anchors in shear walls. Level #3; Area B, shear walls and ATS System.
04/04/2025 COT - HCBU - Framing Not Ready
04/08/2025 COT - HCBU - Framing Partial Pass Sheet rock nailing (shear walls included) on Levels #1 and #2 in sections A and B. OK to tape progress areas in subject units. Electric, mechanical and plumbing intermediates in room units on Level #4, Section B. Level #3, room 352 electrical corrections have been completed.
04/19/2024 COT - HCBU - Framing Partial Pass Information,walk through in areas A & B Level #1: All hardware must be installed before framing at Level #2 in a designated area. Areas in question must be inspected before progressing to next level.
04/22/2025 COT - HCBU - Framing Canceled
05/05/2025 COT - HCBU - Framing Canceled Contractor cancelled, will reschedule when area is ready for inspection.
05/06/2024 COT - HCBU - Framing Partial Pass Area A, Northwest portion (commercial area): shear walls #1, 2, 3.
05/06/2025 COT - HCBU - Framing Partial Pass 5/6/25: hold-downs per plan at first floor breezeway, (anchor bolts with appropriate washer plates required to be installed where sill plate is larger than 12"), (anchor bolt spacing not per schedule) please call us back out once issues are corrected to ensure items were completed. Ok to proceed with sheathing at first floor south building patio columns on south half and west half.
05/07/2024 COT - HCBU - Framing Not Ready Section A deck area missing required straps. All straps must be in place as per plans before vertical construction can continue in this area.
05/13/2024 COT - HCBU - Framing Partial Pass Level #1, Northwest portion of Area A: Straps and clips,are in place: straps for Area A deck are in place. Ok to proceed,vertically in Area A.
05/23/2025 COT - HCBU - Framing Canceled Canceled per contractor. 5/23/2025
05/27/2025 COT - HCBU - Framing Partial Pass Level #1, shear walls at stairwell #4, corridor at elevator, room units 107, 110, 111, 112, 127, 113, 128, 104.
05/28/2025 COT - HCBU - Framing Partial Pass 5/6/25: hold-downs per plan at first floor breezeway, (anchor bolts with appropriate washer plates required to be installed where sill plate is larger than 12"), (anchor bolt spacing not per schedule) please call us back out once issues are corrected to ensure items were completed. Ok to proceed with sheathing at first floor south building patio columns on south half and west half.

Canceled per contractor. 5/23/2025
5/28/25: partial pass for hardware at stairway 2 at north building. Pending R302.11 Fireblocking at landings.
06/02/2025 COT - HCBU - Framing Partial Pass 5/6/25: hold-downs per plan at first floor breezeway, (anchor bolts with appropriate washer plates required to be installed where sill plate is larger than 12"), (anchor bolt spacing not per schedule) please call us back out once issues are corrected to ensure items were completed. Ok to proceed with sheathing at first floor south building patio columns on south half and west half.

Canceled per contractor. 5/23/2025
5/28/25: partial pass for hardware at stairway 2 at north building. Pending R302.11 Fireblocking at landings.
6/2/25: exterior shear wall approved in units 303,403,503,302,402,502,301,402,502,324,424,524,323,322,321. First floor south building south columns per plan. Ok to proceed with sheathing.
06/06/2024 COT - HCBU - Framing Partial Pass Level #2, Section A, room units Northeast portion. Ensure proper nailing for hardware (hangers)
06/10/2024 COT - HCBU - Framing Partial Pass Level #2; section “A”, ensure all straps are properly secured. Ok to progress vertically in approved areas.
06/11/2025 COT - HCBU - Framing Partial Pass ATS at Level 1 section D South Building approved. Stair 3 okay to proceed with drywall. Pending SDS screws re inspection. 6/11/2025
06/14/2024 COT - HCBU - Framing Partial Pass Level #2, Section B, straps and hardware in place; Ok to vertical in this area. Deck area rooms S126and S128: Ok to frame progress area. Level #1. section B West room units.

Note: Sewer inspection performed on this date at North and Northeast side of structure. Sewer line (8”) with 5 each laterals at 6” from corner of structure to new man hole. Ok to back fill progress areas.
06/16/2025 COT - HCBU - Framing Partial Pass ATS at section C level 2 of South Building. Approved. Okay to proceed progress areas. 6/16/2025
06/18/2025 COT - HCBU - Framing Partial Pass 6-18-25: framing at stair 2, levels 1-5-verified fire blocking with correct hardware. Fire caulk any penetrations-Either reschedule inspection or provide pics. Okay to continue with construction at progress areas.
06/20/2025 COT - HCBU - Framing Partial Pass 6-20-25: revision submitted and approved on stair #4. Steel Handrail missing at stair basement-this will be inspected at later date. Stairs for Levels 1-5 verified per plans. Okay to proceed with construction at progress areas.
06/23/2025 COT - HCBU - Framing Partial Pass 5/6/25: hold-downs per plan at first floor breezeway, (anchor bolts with appropriate washer plates required to be installed where sill plate is larger than 12"), (anchor bolt spacing not per schedule) please call us back out once issues are corrected to ensure items were completed. Ok to proceed with sheathing at first floor south building patio columns on south half and west half.

Canceled per contractor. 5/23/2025
5/28/25: partial pass for hardware at stairway 2 at north building. Pending R302.11 Fireblocking at landings.
6/2/25: exterior shear wall approved in units 303,403,503,302,402,502,301,402,502,324,424,524,323,322,321. First floor south building south columns per plan. Ok to proceed with sheathing.

ATS at Level 1 section D South Building approved. Stair 3 okay to proceed with drywall. Pending SDS screws re inspection. 6/11/2025

ATS at section C level 2 of South Building. Approved. Okay to proceed progress areas. 6/16/2025
6-18-25: framing at stair 2, levels 1-5-verified fire blocking with correct hardware. Fire caulk any penetrations-Either reschedule inspection or provide pics. Okay to continue with construction at progress areas.
6-20-25: revision submitted and approved on stair #4. Steel Handrail missing at stair basement-this will be inspected at later date. Stairs for Levels 1-5 verified per plans. Okay to proceed with construction at progress areas.
6/23/25:framing at stair 2, levels 1-5-verified fire blocking. Ok to proceed
06/24/2024 COT - HCBU - Framing Canceled Contractor cancelled inspection.
06/26/2024 COT - HCBU - Framing Partial Pass Level #2; Areas B and D, straps are in place. OK to proceed vertically in these areas.
06/26/2025 COT - HCBU - Framing Partial Pass 5/6/25: hold-downs per plan at first floor breezeway, (anchor bolts with appropriate washer plates required to be installed where sill plate is larger than 12"), (anchor bolt spacing not per schedule) please call us back out once issues are corrected to ensure items were completed. Ok to proceed with sheathing at first floor south building patio columns on south half and west half.

Canceled per contractor. 5/23/2025
5/28/25: partial pass for hardware at stairway 2 at north building. Pending R302.11 Fireblocking at landings.
6/2/25: exterior shear wall approved in units 303,403,503,302,402,502,301,402,502,324,424,524,323,322,321. First floor south building south columns per plan. Ok to proceed with sheathing.

ATS at Level 1 section D South Building approved. Stair 3 okay to proceed with drywall. Pending SDS screws re inspection. 6/11/2025

ATS at section C level 2 of South Building. Approved. Okay to proceed progress areas. 6/16/2025
6-18-25: framing at stair 2, levels 1-5-verified fire blocking with correct hardware. Fire caulk any penetrations-Either reschedule inspection or provide pics. Okay to continue with construction at progress areas.
6-20-25: revision submitted and approved on stair #4. Steel Handrail missing at stair basement-this will be inspected at later date. Stairs for Levels 1-5 verified per plans. Okay to proceed with construction at progress areas.
6/23/25:framing at stair 2, levels 1-5-verified fire blocking. Ok to proceed
6/26/25: Truss repairs in rooms 447 and 446 and RFI S-11.1/16 in 447.
6/26/25: strong rod tie-down per approved plans at 4th and 5th floor area C. Ok to proceed with progress areas.
07/10/2024 COT - HCBU - Framing Partial Pass Level #3, area “A”; framing and deck. Ok to progress vertically.
07/11/2025 COT - HCBU - Framing Partial Pass Level #2, Area D , ATS System in room units.
07/19/2024 COT - HCBU - Framing Canceled Contractor cancelled, will reschedule for 22 July.
07/21/2025 COT - HCBU - Framing Partial Pass 5/6/25: hold-downs per plan at first floor breezeway, (anchor bolts with appropriate washer plates required to be installed where sill plate is larger than 12"), (anchor bolt spacing not per schedule) please call us back out once issues are corrected to ensure items were completed. Ok to proceed with sheathing at first floor south building patio columns on south half and west half.
7/21/25: ATS level 3 section D units 314,315,316,317,318, 321,322, 323, 324,326,328,
07/22/2024 COT - HCBU - Framing Partial Pass Level,#3, Area B, room units in Southeast area. Level #4 deck straps in Area B, OK to progress vertically.
07/25/2025 COT - HCBU - Framing Partial Pass ATS System at level #4, Area D.
07/26/2024 COT - HCBU - Framing Partial Pass Level #2, units and corridors. Level #3 deck strapping, OK to go vertical.
08/02/2024 COT - HCBU - Framing Partial Pass Level #2; area “C” units. Level #3 deck, straps are in place, OK to proceed vertically.
08/09/2024 COT - HCBU - Framing Canceled Contractor cancelled.
08/12/2024 COT - HCBU - Framing Partial Pass Level #4; Area A room units and deck. Ok to proceed vertically.
08/15/2025 COT - HCBU - Framing Partial Pass 8/15/25: framing approved in rooms 302,303,404,403,402
08/18/2025 COT - HCBU - Framing Partial Pass 8/15/25: framing approved in rooms 302,303,404,403,402
8/18/25: framing approved room 304.
08/23/2024 COT - HCBU - Framing Partial Pass Level #4; room units and decking. Ok to proceed vertically.
08/28/2024 COT - HCBU - Framing Canceled Contractor cancelled.
08/29/2024 COT - HCBU - Framing Partial Pass Level #3, Room units in section “C”. Deck level of Area “C” and West portion of deck area of Area “B”; OK to proceed vertically in areas C and B
08/30/2024 COT - HCBU - Framing Partial Pass Level #1, area “A”; unit #160 West wall, unit #139 E. Wall, unit #138 E. wall, area A trash room, West wall, unit #135 West wall, unit #133 West wall. Ok to cover progress area walls.
09/10/2024 COT - HCBU - Framing Partial Pass Level #5; area “A” room units and corridors. Level #3; area “D” not ready, contractor cancelled.
09/13/2024 COT - HCBU - Framing Partial Pass Level 3, area D, room units
09/17/2024 COT - HCBU - Framing Partial Pass MEP above ceilings in corridors on Level #1, Areas A & B. Secondary electric conduits: 15 @ 3” lines at Southwest corner of building. Ok to cover progress areas.
09/18/2025 COT - HCBU - Framing Not Ready
09/20/2024 COT - HCBU - Framing Partial Pass Level #5, Area B room units.
09/25/2024 COT - HCBU - Framing Partial Pass Level #1; Area A: shear walls SW1 - SW7
09/26/2024 COT - HCBU - Framing Partial Pass Level #2 decking above fire truck turn around. Required Arturo to add straps to deck area.
10/16/2024 COT - HCBU - Framing Partial Pass Level #1, North Arcade area; interior columns, hold - downs in place. Level #4; Area C: room units 402, 403, 405, 406, 407, 408. Level #1 pre-rock in Area B; rooms 131, 1#2.
10/21/2024 COT - HCBU - Framing Partial Pass Courtyard “B” interior columns act Levels #1 & #2; Ok to cover progress areas. Note: Inspected duct work (10 x 36 and 10 x 26) in main corridor. Ok to insulate progress areas.
10/29/2024 COT - HCBU - Framing Partial Pass Level #3, 4 room units above fire truck turn-around area. Sheetrock nailing: Area B, East and West Mechanical shaft. Area A, stair #2 shaft, stair shaft of Section A. Level #1, room 116, Electric room: OK to tape progress areas.
10/30/2025 COT - HCBU - Framing Partial Pass 10/30/25: Commercial units # 166; 165; 164; 163; 162; 161 c-channels installed ok to proceed.
11/01/2024 COT - HCBU - Framing Partial Pass Level #4; section C: Room units S401, S424, 425, S426, S427, S429.
11/04/2025 COT - HCBU - Framing Partial Pass 11/4/25: Framing approved in electrical rooms 310 and 410
11/05/2024 COT - HCBU - Framing Partial Pass Shear wall framing in units S156, S158. OK to cover progress areas. IDF room #S124, framing completed; extend Sheetrock to deck above.
11/13/2024 COT - HCBU - Framing Partial Pass Shear walls in units #151, 152, 154.
11/26/2024 COT - HCBU - Framing Partial Pass MEP in units S151, S152, S153, S154, S155, S156. Shear walls in units S150, S148, Electric rooms S124, S125. Exterior sheathing on East walls: Levels #1 - #5.
11/27/2024 COT - HCBU - Framing Partial Pass Level #4; Room units S414, S415, S416, S417, S419, S418, S419, S420. Level #5 deck: straps to be applied in designated areas.
COT - HCBU - Framing Scheduled
12/18/2024 COT - HCBU - Framing Partial Pass Shear walls on Level #1: S148, S150, S157, S141, S144, S145, Corridor “B”, unit 131
12/23/2024 COT - HCBU - Framing Canceled Contractor cancelled.
12/31/2024 COT - HCBU - Framing Partial Pass Top-out sheet rock nailing in Section A room units: S138, S139, S140, S141, S133, S135, S158, S160; Section B room units: S157, S159, S143, S144, S145, S148. S150.