Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCBU - Framing
Permit Number - T21CM09453
Inspection Description - COT - HCBU - Framing
Inspection Status - Partial Pass
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/03/2025 | COT - HCBU - Framing | Partial Pass | Level #1, Area A room unit #107 - MEP. OK to insulate and cover walls. Level #2, Areas A and B courtyard overlook in corridors; straps and walls covered. Levels 3 - 5 not ready. | |
| 02/10/2025 | COT - HCBU - Framing | Partial Pass | North building: pitched roofs, nailing in place, Ok to dry-in progress areas. South building (flat roofs) at areas A & B OK to dry-in roof systems. | |
| 02/11/2025 | COT - HCBU - Framing | Partial Pass | Rooms #235 and 237. | |
| 02/24/2025 | COT - HCBU - Framing | Partial Pass | Level #1: Fire Truck turn-around Titan anchors in shear walls. Level #3; Area B, shear walls and ATS System. | |
| 04/04/2025 | COT - HCBU - Framing | Not Ready | ||
| 04/08/2025 | COT - HCBU - Framing | Partial Pass | Sheet rock nailing (shear walls included) on Levels #1 and #2 in sections A and B. OK to tape progress areas in subject units. Electric, mechanical and plumbing intermediates in room units on Level #4, Section B. Level #3, room 352 electrical corrections have been completed. | |
| 04/19/2024 | COT - HCBU - Framing | Partial Pass | Information,walk through in areas A & B Level #1: All hardware must be installed before framing at Level #2 in a designated area. Areas in question must be inspected before progressing to next level. | |
| 04/22/2025 | COT - HCBU - Framing | Canceled | ||
| 05/05/2025 | COT - HCBU - Framing | Canceled | Contractor cancelled, will reschedule when area is ready for inspection. | |
| 05/06/2024 | COT - HCBU - Framing | Partial Pass | Area A, Northwest portion (commercial area): shear walls #1, 2, 3. | |
| 05/06/2025 | COT - HCBU - Framing | Partial Pass | 5/6/25: hold-downs per plan at first floor breezeway, (anchor bolts with appropriate washer plates required to be installed where sill plate is larger than 12"), (anchor bolt spacing not per schedule) please call us back out once issues are corrected to ensure items were completed. Ok to proceed with sheathing at first floor south building patio columns on south half and west half. | |
| 05/07/2024 | COT - HCBU - Framing | Not Ready | Section A deck area missing required straps. All straps must be in place as per plans before vertical construction can continue in this area. | |
| 05/13/2024 | COT - HCBU - Framing | Partial Pass | Level #1, Northwest portion of Area A: Straps and clips,are in place: straps for Area A deck are in place. Ok to proceed,vertically in Area A. | |
| 05/23/2025 | COT - HCBU - Framing | Canceled | Canceled per contractor. 5/23/2025 | |
| 05/27/2025 | COT - HCBU - Framing | Partial Pass | Level #1, shear walls at stairwell #4, corridor at elevator, room units 107, 110, 111, 112, 127, 113, 128, 104. | |
| 05/28/2025 | COT - HCBU - Framing | Partial Pass | 5/6/25: hold-downs per plan at first floor breezeway, (anchor bolts with appropriate washer plates required to be installed where sill plate is larger than 12"), (anchor bolt spacing not per schedule) please call us back out once issues are corrected to ensure items were completed. Ok to proceed with sheathing at first floor south building patio columns on south half and west half. Canceled per contractor. 5/23/2025 5/28/25: partial pass for hardware at stairway 2 at north building. Pending R302.11 Fireblocking at landings. |
|
| 06/02/2025 | COT - HCBU - Framing | Partial Pass | 5/6/25: hold-downs per plan at first floor breezeway, (anchor bolts with appropriate washer plates required to be installed where sill plate is larger than 12"), (anchor bolt spacing not per schedule) please call us back out once issues are corrected to ensure items were completed. Ok to proceed with sheathing at first floor south building patio columns on south half and west half. Canceled per contractor. 5/23/2025 5/28/25: partial pass for hardware at stairway 2 at north building. Pending R302.11 Fireblocking at landings. 6/2/25: exterior shear wall approved in units 303,403,503,302,402,502,301,402,502,324,424,524,323,322,321. First floor south building south columns per plan. Ok to proceed with sheathing. |
|
| 06/06/2024 | COT - HCBU - Framing | Partial Pass | Level #2, Section A, room units Northeast portion. Ensure proper nailing for hardware (hangers) | |
| 06/10/2024 | COT - HCBU - Framing | Partial Pass | Level #2; section “A”, ensure all straps are properly secured. Ok to progress vertically in approved areas. | |
| 06/11/2025 | COT - HCBU - Framing | Partial Pass | ATS at Level 1 section D South Building approved. Stair 3 okay to proceed with drywall. Pending SDS screws re inspection. 6/11/2025 | |
| 06/14/2024 | COT - HCBU - Framing | Partial Pass | Level #2, Section B, straps and hardware in place; Ok to vertical in this area. Deck area rooms S126and S128: Ok to frame progress area. Level #1. section B West room units. Note: Sewer inspection performed on this date at North and Northeast side of structure. Sewer line (8”) with 5 each laterals at 6” from corner of structure to new man hole. Ok to back fill progress areas. |
|
| 06/16/2025 | COT - HCBU - Framing | Partial Pass | ATS at section C level 2 of South Building. Approved. Okay to proceed progress areas. 6/16/2025 | |
| 06/18/2025 | COT - HCBU - Framing | Partial Pass | 6-18-25: framing at stair 2, levels 1-5-verified fire blocking with correct hardware. Fire caulk any penetrations-Either reschedule inspection or provide pics. Okay to continue with construction at progress areas. | |
| 06/20/2025 | COT - HCBU - Framing | Partial Pass | 6-20-25: revision submitted and approved on stair #4. Steel Handrail missing at stair basement-this will be inspected at later date. Stairs for Levels 1-5 verified per plans. Okay to proceed with construction at progress areas. | |
| 06/23/2025 | COT - HCBU - Framing | Partial Pass | 5/6/25: hold-downs per plan at first floor breezeway, (anchor bolts with appropriate washer plates required to be installed where sill plate is larger than 12"), (anchor bolt spacing not per schedule) please call us back out once issues are corrected to ensure items were completed. Ok to proceed with sheathing at first floor south building patio columns on south half and west half. Canceled per contractor. 5/23/2025 5/28/25: partial pass for hardware at stairway 2 at north building. Pending R302.11 Fireblocking at landings. 6/2/25: exterior shear wall approved in units 303,403,503,302,402,502,301,402,502,324,424,524,323,322,321. First floor south building south columns per plan. Ok to proceed with sheathing. ATS at Level 1 section D South Building approved. Stair 3 okay to proceed with drywall. Pending SDS screws re inspection. 6/11/2025 ATS at section C level 2 of South Building. Approved. Okay to proceed progress areas. 6/16/2025 6-18-25: framing at stair 2, levels 1-5-verified fire blocking with correct hardware. Fire caulk any penetrations-Either reschedule inspection or provide pics. Okay to continue with construction at progress areas. 6-20-25: revision submitted and approved on stair #4. Steel Handrail missing at stair basement-this will be inspected at later date. Stairs for Levels 1-5 verified per plans. Okay to proceed with construction at progress areas. 6/23/25:framing at stair 2, levels 1-5-verified fire blocking. Ok to proceed |
|
| 06/24/2024 | COT - HCBU - Framing | Canceled | Contractor cancelled inspection. | |
| 06/26/2024 | COT - HCBU - Framing | Partial Pass | Level #2; Areas B and D, straps are in place. OK to proceed vertically in these areas. | |
| 06/26/2025 | COT - HCBU - Framing | Partial Pass | 5/6/25: hold-downs per plan at first floor breezeway, (anchor bolts with appropriate washer plates required to be installed where sill plate is larger than 12"), (anchor bolt spacing not per schedule) please call us back out once issues are corrected to ensure items were completed. Ok to proceed with sheathing at first floor south building patio columns on south half and west half. Canceled per contractor. 5/23/2025 5/28/25: partial pass for hardware at stairway 2 at north building. Pending R302.11 Fireblocking at landings. 6/2/25: exterior shear wall approved in units 303,403,503,302,402,502,301,402,502,324,424,524,323,322,321. First floor south building south columns per plan. Ok to proceed with sheathing. ATS at Level 1 section D South Building approved. Stair 3 okay to proceed with drywall. Pending SDS screws re inspection. 6/11/2025 ATS at section C level 2 of South Building. Approved. Okay to proceed progress areas. 6/16/2025 6-18-25: framing at stair 2, levels 1-5-verified fire blocking with correct hardware. Fire caulk any penetrations-Either reschedule inspection or provide pics. Okay to continue with construction at progress areas. 6-20-25: revision submitted and approved on stair #4. Steel Handrail missing at stair basement-this will be inspected at later date. Stairs for Levels 1-5 verified per plans. Okay to proceed with construction at progress areas. 6/23/25:framing at stair 2, levels 1-5-verified fire blocking. Ok to proceed 6/26/25: Truss repairs in rooms 447 and 446 and RFI S-11.1/16 in 447. 6/26/25: strong rod tie-down per approved plans at 4th and 5th floor area C. Ok to proceed with progress areas. |
|
| 07/10/2024 | COT - HCBU - Framing | Partial Pass | Level #3, area “A”; framing and deck. Ok to progress vertically. | |
| 07/11/2025 | COT - HCBU - Framing | Partial Pass | Level #2, Area D , ATS System in room units. | |
| 07/19/2024 | COT - HCBU - Framing | Canceled | Contractor cancelled, will reschedule for 22 July. | |
| 07/21/2025 | COT - HCBU - Framing | Partial Pass | 5/6/25: hold-downs per plan at first floor breezeway, (anchor bolts with appropriate washer plates required to be installed where sill plate is larger than 12"), (anchor bolt spacing not per schedule) please call us back out once issues are corrected to ensure items were completed. Ok to proceed with sheathing at first floor south building patio columns on south half and west half. 7/21/25: ATS level 3 section D units 314,315,316,317,318, 321,322, 323, 324,326,328, |
|
| 07/22/2024 | COT - HCBU - Framing | Partial Pass | Level,#3, Area B, room units in Southeast area. Level #4 deck straps in Area B, OK to progress vertically. | |
| 07/25/2025 | COT - HCBU - Framing | Partial Pass | ATS System at level #4, Area D. | |
| 07/26/2024 | COT - HCBU - Framing | Partial Pass | Level #2, units and corridors. Level #3 deck strapping, OK to go vertical. | |
| 08/02/2024 | COT - HCBU - Framing | Partial Pass | Level #2; area “C” units. Level #3 deck, straps are in place, OK to proceed vertically. | |
| 08/09/2024 | COT - HCBU - Framing | Canceled | Contractor cancelled. | |
| 08/12/2024 | COT - HCBU - Framing | Partial Pass | Level #4; Area A room units and deck. Ok to proceed vertically. | |
| 08/15/2025 | COT - HCBU - Framing | Partial Pass | 8/15/25: framing approved in rooms 302,303,404,403,402 | |
| 08/18/2025 | COT - HCBU - Framing | Partial Pass | 8/15/25: framing approved in rooms 302,303,404,403,402 8/18/25: framing approved room 304. |
|
| 08/23/2024 | COT - HCBU - Framing | Partial Pass | Level #4; room units and decking. Ok to proceed vertically. | |
| 08/28/2024 | COT - HCBU - Framing | Canceled | Contractor cancelled. | |
| 08/29/2024 | COT - HCBU - Framing | Partial Pass | Level #3, Room units in section “C”. Deck level of Area “C” and West portion of deck area of Area “B”; OK to proceed vertically in areas C and B | |
| 08/30/2024 | COT - HCBU - Framing | Partial Pass | Level #1, area “A”; unit #160 West wall, unit #139 E. Wall, unit #138 E. wall, area A trash room, West wall, unit #135 West wall, unit #133 West wall. Ok to cover progress area walls. | |
| 09/10/2024 | COT - HCBU - Framing | Partial Pass | Level #5; area “A” room units and corridors. Level #3; area “D” not ready, contractor cancelled. | |
| 09/13/2024 | COT - HCBU - Framing | Partial Pass | Level 3, area D, room units | |
| 09/17/2024 | COT - HCBU - Framing | Partial Pass | MEP above ceilings in corridors on Level #1, Areas A & B. Secondary electric conduits: 15 @ 3” lines at Southwest corner of building. Ok to cover progress areas. | |
| 09/18/2025 | COT - HCBU - Framing | Not Ready | ||
| 09/20/2024 | COT - HCBU - Framing | Partial Pass | Level #5, Area B room units. | |
| 09/25/2024 | COT - HCBU - Framing | Partial Pass | Level #1; Area A: shear walls SW1 - SW7 | |
| 09/26/2024 | COT - HCBU - Framing | Partial Pass | Level #2 decking above fire truck turn around. Required Arturo to add straps to deck area. | |
| 10/16/2024 | COT - HCBU - Framing | Partial Pass | Level #1, North Arcade area; interior columns, hold - downs in place. Level #4; Area C: room units 402, 403, 405, 406, 407, 408. Level #1 pre-rock in Area B; rooms 131, 1#2. | |
| 10/21/2024 | COT - HCBU - Framing | Partial Pass | Courtyard “B” interior columns act Levels #1 & #2; Ok to cover progress areas. Note: Inspected duct work (10 x 36 and 10 x 26) in main corridor. Ok to insulate progress areas. | |
| 10/29/2024 | COT - HCBU - Framing | Partial Pass | Level #3, 4 room units above fire truck turn-around area. Sheetrock nailing: Area B, East and West Mechanical shaft. Area A, stair #2 shaft, stair shaft of Section A. Level #1, room 116, Electric room: OK to tape progress areas. | |
| 10/30/2025 | COT - HCBU - Framing | Partial Pass | 10/30/25: Commercial units # 166; 165; 164; 163; 162; 161 c-channels installed ok to proceed. | |
| 11/01/2024 | COT - HCBU - Framing | Partial Pass | Level #4; section C: Room units S401, S424, 425, S426, S427, S429. | |
| 11/04/2025 | COT - HCBU - Framing | Partial Pass | 11/4/25: Framing approved in electrical rooms 310 and 410 | |
| 11/05/2024 | COT - HCBU - Framing | Partial Pass | Shear wall framing in units S156, S158. OK to cover progress areas. IDF room #S124, framing completed; extend Sheetrock to deck above. | |
| 11/13/2024 | COT - HCBU - Framing | Partial Pass | Shear walls in units #151, 152, 154. | |
| 11/26/2024 | COT - HCBU - Framing | Partial Pass | MEP in units S151, S152, S153, S154, S155, S156. Shear walls in units S150, S148, Electric rooms S124, S125. Exterior sheathing on East walls: Levels #1 - #5. | |
| 11/27/2024 | COT - HCBU - Framing | Partial Pass | Level #4; Room units S414, S415, S416, S417, S419, S418, S419, S420. Level #5 deck: straps to be applied in designated areas. | |
| COT - HCBU - Framing | Scheduled | |||
| 12/18/2024 | COT - HCBU - Framing | Partial Pass | Shear walls on Level #1: S148, S150, S157, S141, S144, S145, Corridor “B”, unit 131 | |
| 12/23/2024 | COT - HCBU - Framing | Canceled | Contractor cancelled. | |
| 12/31/2024 | COT - HCBU - Framing | Partial Pass | Top-out sheet rock nailing in Section A room units: S138, S139, S140, S141, S133, S135, S158, S160; Section B room units: S157, S159, S143, S144, S145, S148. S150. |