Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.

Permit: T21CM09453

Parcel: 11620637A


Addresses:

165 S LINDA AV

Inspection Status: Partial Pass

Inspection History: COT - HCBU - Excavation/Rebar/Zoning 

Date Description Inspector Results Comments
01/04/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Areas C & D garage walls (South) and slab area. OK to place concrete in progress areas.
01/17/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Retaining wall footing for swimming pool at East side if site; approximately 80 feet. Ok to place concrete in progress areas.
01/28/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass East pool/retaining wall footing; expanded as per RFI #218, 31 August 2024.
01/29/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Masonry pre-grout for East pool wall at 0’ - 4’. Ok to grout progress areas.
01/30/2025 COT - HCBU - Excavation/Rebar/Zoning  Canceled Contractor cancelled, will reschedule for 31 January.
01/31/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Ramp area at Southeast corner of South building and exit area at Southwest corner of South building. Ok to place concrete in progress areas.
02/05/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass East pool wall at 4’ - 8’; approximately 85’. Ok to grout progress areas.
02/28/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Corrections for Southeast footings affected. Rebar epoxied as per request from Engineer of Record.
03/09/2026 COT - HCBU - Excavation/Rebar/Zoning  Not Ready
03/20/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Basement areas of CMU walls at 0” - 48”; stairway #1, bicycle storage area, electric room, elevator #2/lobby area, MDF room. OK to grout progress areas.
05/08/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass CMU walls at 0’ - 4’ of elevator/stairwell #3. Ok to grout progress areas.
05/10/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Area B, North garage stairs/elevator shaft #3, Room #117; CMU walls at 4’ - 9’4”. Ok to place grout in progress areas.
06/03/2025 COT - HCBU - Excavation/Rebar/Zoning  Not Ready
06/12/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Ramp area at entrance to garage (South). Wire mesh and rebar reinforcement in place. Ok to place concrete in progress areas.
06/13/2025 COT - HCBU - Excavation/Rebar/Zoning  Re-inspection required 6/13/2025 Planter walls in courtyard C and D need to be re inspected due to seal tight against forms. Provide manufacturing specs on Smurf tubing for concrete enclosure.
06/23/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Retaining/stem wall footings (WF-2) at GL: 14.2/R.1 - H. OK to place concrete in progress areas.
06/26/2025 COT - HCBU - Excavation/Rebar/Zoning  Not Ready
06/29/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Ramp footings at GL: K - M.2/8.5, K - M.2/9.5. OK to place concrete in progress areas
07/02/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 10/18/23: Basement/garage slab in Area C: #4 wire mesh reinforcement, rebar reinforcement around columns. Ok to place concrete in progress areas.
10/27/23: Basement/garage slab in Area D: #5 wire mesh reinforcement, rebar reinforcement around columns. Ok to place concrete in progress areas

6/13/2025 Planter walls in courtyard C and D need to be re inspected due to seal tight against forms. Provide manufacturing specs on Smurf tubing for concrete enclosure
7/2/25. Planter walls in courtyard A reinforcement steel per plan. UF romex required at conduits encased in concrete.
07/05/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Wall footing/retention wall footings at GL: 2 - 7/L -M, 2/F - G, L/5. Ok to place concrete in progress areas. Column footings at GL: 9/J (F2), 9/I (F2), 9/H (F2), 8/K (F2), 10/I (F2), 8/H (F2), 8/J F4), 11/K (F2), 11/I (F2), 11/H (F2), 11/J (F4)
07/07/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Retaining wall at GL: I - K.5/14.2. OK to place concrete in progress areas.
07/11/2023 COT - HCBU - Excavation/Rebar/Zoning  Not Ready Contractor cancelled.
07/12/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Garage CMU walls at GL: F.5/14 - I, I/14 - 14.2, 14.2/K - L. Wall footing 1 at M.5/5.2 - 8.5, R.1/9.2 14.2. Columns at N/11, K/8. OK to set forms and place concrete in progress areas.
07/13/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Retaining wall footings at GL: 2/K - L, L - M/2 - 7, Retaining wall at 2/K - G. Column 8/K. OK to set forms and place concrete in progress areas.
07/14/2023 COT - HCBU - Excavation/Rebar/Zoning  Not Ready Contractor cancelled.
07/15/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 10/18/23: Basement/garage slab in Area C: #4 wire mesh reinforcement, rebar reinforcement around columns. Ok to place concrete in progress areas.
10/27/23: Basement/garage slab in Area D: #5 wire mesh reinforcement, rebar reinforcement around columns. Ok to place concrete in progress areas

6/13/2025 Planter walls in courtyard C and D need to be re inspected due to seal tight against forms. Provide manufacturing specs on Smurf tubing for concrete enclosure
7/2/25. Planter walls in courtyard A reinforcement steel per plan. UF romex required at conduits encased in concrete.
7/15/25: Rebar and forms at center courtyard planters (4)
07/17/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Caisson footings at GL: K/10, L/10, J/10, M/10, J/11, K/11, M/11, N/11, J12, K/12, L/12, L/11. See RFI dared 6 Jin 23. Ok to set forms and place concrete. Retaining wall rebar at GL: 14.2/M - M.2
07/18/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Columns: H/9, H/10, H/11, H/12, I/9, I/10, I/11, 1/12. OK to set forms and place concrete in progress areas. Retaining walls at I/11 - 11. 5, 11.5/A - A.5, A.5/11.5 - 13, 13/A -B.5, B.5/12.8 - 14. OK to set forms and place concrete in progress areas. Elevator #6 at GL: 10.5/C - C. 5. OK to place concrete in progress areas.
07/20/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Column cage for columns at GL: G/9, G/10, G/11, F/9, F/10, F/11, H/11, J/9, H/8, I/8. OK to set forms and place concrete.
07/23/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 10/18/23: Basement/garage slab in Area C: #4 wire mesh reinforcement, rebar reinforcement around columns. Ok to place concrete in progress areas.
10/27/23: Basement/garage slab in Area D: #5 wire mesh reinforcement, rebar reinforcement around columns. Ok to place concrete in progress areas

6/13/2025 Planter walls in courtyard C and D need to be re inspected due to seal tight against forms. Provide manufacturing specs on Smurf tubing for concrete enclosure
7/2/25. Planter walls in courtyard A reinforcement steel per plan. UF romex required at conduits encased in concrete.
7/15/25: Rebar and forms at center courtyard planters (4)
7/23/25: Rebar and forms at center courtyard (2)
07/24/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Retaining wall footings at GL: F.5 - B/1, A/5 - 7. OK to place concrete in progress areas. Column footings at GL: 7/F - M, 8/F-I. Elevator pit at 4/B. Ok to cover progress areas.
07/25/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Elevator pit #5 and column footing at C/11. OK to place concrete in progress areas.
07/26/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Columns at GL: 7/M - H (6 columns). Spread footings at GL: 8 (5 footings), GL: 11 (6 footings), Ok to place concrete in progress areas.
07/27/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Vertical wall footings at GL: R.1/9 - 14.2, elevator #4 at GL: A - B/3.5 -4.5. OK to place concrete in progress areas.
07/28/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Retaining wall footings at GL: R.2/2.8 - 13. OK to place concrete in progress areas. Columns in area A & C at GL: 5/D, E, E, G, H, I, L. 3/H, I, J, K, L, I, L. 6/D, E, F, G, H. 14/K, L, M. OK to set forms and place concrete in progress areas.
07/31/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Area A North retaining wall at GL: F.5 - L.5/2. OK to set forms and place concrete in progress areas.
08/01/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Fire truck turn-around area (Room 122), West side ramp rebar for wall. OK to place concrete in progress areas.
08/03/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Column footings at GL: 3/C, 3/D, 3/E, 3/F, 4/E, 4/F, 4/G, 4,H, 4/I. Elevator walls at elevator #2, elevator #5, elevator #6. Ok to place concrete in progress areas.
08/04/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Column footings at GL: 12/D, 12/E, 12/F, 12/G. Columns at GL: E/7, E/8, E/9, E/10, 8/M, 8/L. OK to place concrete in progress areas.
08/07/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Caisson columns at GL: 3/C, 3/D, 3/E, 3/F, 3/G, 4/C/, 4/D, 4/E, 4/F, 4/F, 5/C. OK to set forms and place concrete in progress areas. Retaining wall on Eastside of site (approximately 30’). Ok to set forms and place concrete.
08/07/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Fire truck turn-around area; West ramp walk way (#5 rebar reinforcement in walking surface). Ok to place concrete at ramp and in swimming pool,equipment,room.
08/08/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Inspections for 9 & 10 August: Columns at GL: 12/D, E, F, G. 14/J, K, L. Wall at GL: 2/F - L.5. Ok to set forms and place concrete.
08/12/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 8/12/2025 Courtyard B planters. Total of three. Okay for concrete placement.
08/13/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Pool equipment room; #3 rebar utilized for reinforcement. Ok to place concrete in progress areas .
08/16/2023 COT - HCBU - Excavation/Rebar/Zoning  Not Ready Contractor cancelled.
08/18/2023 COT - HCBU - Excavation/Rebar/Zoning  Not Ready Elevator #3 walls at GL: M/11.5 - 12.9. Columns at GL: B/4, B/5, B/6, B/7, B/9, B/10, B/11, B/12, C/3, C/4, C/5, C/6, D/3, D/4, D/5, D/6, D/8, D/9, E/E, E/6, E/7, E/8, E/9. OK to set forms and place concrete.
08/29/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass South wall at GL: M/2.4 - 4. OK to set forms and place concrete in progress areas.
08/31/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Area 15 columns at GL: M/12, N/14,M/14, L/13. OK to set forms and place concrete in progress areas.
09/18/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Column footings @ GL: 9/C,9/D, 8/C, 8/D. OK to set forms and place concrete.
09/18/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 1 Planter wall center courtyard. North end center planter. Okay for concrete placement. 9/18/2025
09/19/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Columns at GL; 7/C, 7/D, 8/C, 8/D. OK to set forms and place concrete.
09/29/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Elevator sump pit at GL: F/7. OK to set forms and place concrete.
09/29/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Pool retaining wall footing approved. Okay for concrete placement. 9/25/2025
10/02/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Basement/garage slab in Area B: #4 wire mesh reinforcement, rebar reinforcement around columns. Ok to place concrete in progress areas.

10/18/23: Basement/garage slab in Area C: #4 wire mesh reinforcement, rebar reinforcement around columns. Ok to place concrete in progress areas.
10/03/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Two planters at South side of center courtyard. Ok to place concrete in progress areas.
10/09/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Area A & B, pour #2 of basement slabs. OK to place concrete in progress areas.
10/12/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Storage room footings in Area A and Area B. Ok to place concrete in progress areas.
10/16/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Large planters in central courtyard: concrete placed as per plans.
10/18/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 10/18/23: Basement/garage slab in Area C: #4 wire mesh reinforcement, rebar reinforcement around columns. Ok to place concrete in progress areas.
10/23/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 10/23/25:Stair #3 ramp footing NB-L1-North elevation
10/27/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 10/18/23: Basement/garage slab in Area C: #4 wire mesh reinforcement, rebar reinforcement around columns. Ok to place concrete in progress areas.
10/27/23: Basement/garage slab in Area D: #5 wire mesh reinforcement, rebar reinforcement around columns. Ok to place concrete in progress areas
10/28/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 10/28/25:Three planters in the center courtyard
12/08/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Podium areas A & B, placement #5 top mat. Ok to place concrete in progress areas.
12/21/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Wall #3, footings and 2 column footings at South entry area. Ok to place concrete in progress areas.