Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T21CM09453

Parcel: 11620637A


Addresses:

165 S LINDA AV


Inspection Status: Partial Pass

Inspection History: COT - HCBU - Excavation/Rebar/Zoning 

Permit Number - T21CM09453

Inspection Description - COT - HCBU - Excavation/Rebar/Zoning 

Inspection Status - Partial Pass

Date Description Inspector Results Comments
01/04/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Areas C & D garage walls (South) and slab area. OK to place concrete in progress areas.
03/20/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Basement areas of CMU walls at 0” - 48”; stairway #1, bicycle storage area, electric room, elevator #2/lobby area, MDF room. OK to grout progress areas.
05/08/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass CMU walls at 0’ - 4’ of elevator/stairwell #3. Ok to grout progress areas.
05/10/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Area B, North garage stairs/elevator shaft #3, Room #117; CMU walls at 4’ - 9’4”. Ok to place grout in progress areas.
06/12/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Ramp area at entrance to garage (South). Wire mesh and rebar reinforcement in place. Ok to place concrete in progress areas.
06/23/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Retaining/stem wall footings (WF-2) at GL: 14.2/R.1 - H. OK to place concrete in progress areas.
06/29/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Ramp footings at GL: K - M.2/8.5, K - M.2/9.5. OK to place concrete in progress areas
07/05/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Wall footing/retention wall footings at GL: 2 - 7/L -M, 2/F - G, L/5. Ok to place concrete in progress areas. Column footings at GL: 9/J (F2), 9/I (F2), 9/H (F2), 8/K (F2), 10/I (F2), 8/H (F2), 8/J F4), 11/K (F2), 11/I (F2), 11/H (F2), 11/J (F4)
07/07/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Retaining wall at GL: I - K.5/14.2. OK to place concrete in progress areas.
07/11/2023 COT - HCBU - Excavation/Rebar/Zoning  Not Ready Contractor cancelled.
07/12/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Garage CMU walls at GL: F.5/14 - I, I/14 - 14.2, 14.2/K - L. Wall footing 1 at M.5/5.2 - 8.5, R.1/9.2 14.2. Columns at N/11, K/8. OK to set forms and place concrete in progress areas.
07/13/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Retaining wall footings at GL: 2/K - L, L - M/2 - 7, Retaining wall at 2/K - G. Column 8/K. OK to set forms and place concrete in progress areas.
07/14/2023 COT - HCBU - Excavation/Rebar/Zoning  Not Ready Contractor cancelled.
07/17/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Caisson footings at GL: K/10, L/10, J/10, M/10, J/11, K/11, M/11, N/11, J12, K/12, L/12, L/11. See RFI dared 6 Jin 23. Ok to set forms and place concrete. Retaining wall rebar at GL: 14.2/M - M.2
07/18/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Columns: H/9, H/10, H/11, H/12, I/9, I/10, I/11, 1/12. OK to set forms and place concrete in progress areas. Retaining walls at I/11 - 11. 5, 11.5/A - A.5, A.5/11.5 - 13, 13/A -B.5, B.5/12.8 - 14. OK to set forms and place concrete in progress areas. Elevator #6 at GL: 10.5/C - C. 5. OK to place concrete in progress areas.
07/20/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Column cage for columns at GL: G/9, G/10, G/11, F/9, F/10, F/11, H/11, J/9, H/8, I/8. OK to set forms and place concrete.
07/24/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Retaining wall footings at GL: F.5 - B/1, A/5 - 7. OK to place concrete in progress areas. Column footings at GL: 7/F - M, 8/F-I. Elevator pit at 4/B. Ok to cover progress areas.
07/25/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Elevator pit #5 and column footing at C/11. OK to place concrete in progress areas.
07/26/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Columns at GL: 7/M - H (6 columns). Spread footings at GL: 8 (5 footings), GL: 11 (6 footings), Ok to place concrete in progress areas.
07/27/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Vertical wall footings at GL: R.1/9 - 14.2, elevator #4 at GL: A - B/3.5 -4.5. OK to place concrete in progress areas.
07/28/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Retaining wall footings at GL: R.2/2.8 - 13. OK to place concrete in progress areas. Columns in area A & C at GL: 5/D, E, E, G, H, I, L. 3/H, I, J, K, L, I, L. 6/D, E, F, G, H. 14/K, L, M. OK to set forms and place concrete in progress areas.
07/31/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Area A North retaining wall at GL: F.5 - L.5/2. OK to set forms and place concrete in progress areas.
08/01/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Fire truck turn-around area (Room 122), West side ramp rebar for wall. OK to place concrete in progress areas.
08/03/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Column footings at GL: 3/C, 3/D, 3/E, 3/F, 4/E, 4/F, 4/G, 4,H, 4/I. Elevator walls at elevator #2, elevator #5, elevator #6. Ok to place concrete in progress areas.
08/04/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Column footings at GL: 12/D, 12/E, 12/F, 12/G. Columns at GL: E/7, E/8, E/9, E/10, 8/M, 8/L. OK to place concrete in progress areas.
08/07/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Caisson columns at GL: 3/C, 3/D, 3/E, 3/F, 3/G, 4/C/, 4/D, 4/E, 4/F, 4/F, 5/C. OK to set forms and place concrete in progress areas. Retaining wall on Eastside of site (approximately 30’). Ok to set forms and place concrete.
08/07/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Fire truck turn-around area; West ramp walk way (#5 rebar reinforcement in walking surface). Ok to place concrete at ramp and in swimming pool,equipment,room.
08/08/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Inspections for 9 & 10 August: Columns at GL: 12/D, E, F, G. 14/J, K, L. Wall at GL: 2/F - L.5. Ok to set forms and place concrete.
08/13/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Pool equipment room; #3 rebar utilized for reinforcement. Ok to place concrete in progress areas .
08/16/2023 COT - HCBU - Excavation/Rebar/Zoning  Not Ready Contractor cancelled.
08/18/2023 COT - HCBU - Excavation/Rebar/Zoning  Not Ready Elevator #3 walls at GL: M/11.5 - 12.9. Columns at GL: B/4, B/5, B/6, B/7, B/9, B/10, B/11, B/12, C/3, C/4, C/5, C/6, D/3, D/4, D/5, D/6, D/8, D/9, E/E, E/6, E/7, E/8, E/9. OK to set forms and place concrete.
08/29/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass South wall at GL: M/2.4 - 4. OK to set forms and place concrete in progress areas.
08/31/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Area 15 columns at GL: M/12, N/14,M/14, L/13. OK to set forms and place concrete in progress areas.
09/18/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Column footings @ GL: 9/C,9/D, 8/C, 8/D. OK to set forms and place concrete.
09/19/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Columns at GL; 7/C, 7/D, 8/C, 8/D. OK to set forms and place concrete.
09/29/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Elevator sump pit at GL: F/7. OK to set forms and place concrete.
10/02/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Basement/garage slab in Area B: #4 wire mesh reinforcement, rebar reinforcement around columns. Ok to place concrete in progress areas.

10/18/23: Basement/garage slab in Area C: #4 wire mesh reinforcement, rebar reinforcement around columns. Ok to place concrete in progress areas.
10/09/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Area A & B, pour #2 of basement slabs. OK to place concrete in progress areas.
10/12/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Storage room footings in Area A and Area B. Ok to place concrete in progress areas.
10/18/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 10/18/23: Basement/garage slab in Area C: #4 wire mesh reinforcement, rebar reinforcement around columns. Ok to place concrete in progress areas.
10/27/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 10/18/23: Basement/garage slab in Area C: #4 wire mesh reinforcement, rebar reinforcement around columns. Ok to place concrete in progress areas.
10/27/23: Basement/garage slab in Area D: #5 wire mesh reinforcement, rebar reinforcement around columns. Ok to place concrete in progress areas
12/08/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Podium areas A & B, placement #5 top mat. Ok to place concrete in progress areas.
12/21/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Wall #3, footings and 2 column footings at South entry area. Ok to place concrete in progress areas.