Permit: T21CM09453

Parcel: 11620637A


Addresses:

165 S LINDA AV

Inspection Status: Partial Pass

Inspection History: COT - HCPL - Plumbing Progress 

Date Description Inspector Results Comments
01/30/2026 COT - HCPL - Plumbing Progress  Partial Pass 405,428,412,413,414,415,416,418,417,419,420,421. in wall approved. Pending draft stop at every 10’mat party walls and drop ceiling inspections. Okay to proceed with progress areas. 1/30/2026
02/06/2026 COT - HCPL - Plumbing Progress  Partial Pass 2/6/26: MEP 4TH FLOOR AREA C 427,425,424,401,408,407,405, 406,404,427,425,424,404,426,428,412,413,414,415,416, 418,417, 419,420
03/05/2025 COT - HCPL - Plumbing Progress  Not Ready Will reschedule for 6 March.
03/09/2026 COT - HCPL - Plumbing Progress  Not Ready
05/27/2025 COT - HCPL - Plumbing Progress  Partial Pass Domestic water lines (pex) at Level #4, section D:,room units 413, 426, 428. Level #5 Section D: all room units in this section.
05/28/2025 COT - HCPL - Plumbing Progress  Partial Pass 5/28/25: DVW at west 1st floor exterior porch under test ok to proceed. Pending east exterior porch first floor
06/05/2025 COT - HCPL - Plumbing Progress  Partial Pass DWV. level 3,2,1 south building pressure test sewer top out area C.
Pex pressure test. 102,101,103,104,110,111,112,125,124,127. Okay to proceed progress areas. 6/5/2025
06/09/2025 COT - HCPL - Plumbing Progress  Partial Pass Section D Levels 1-3. DWV and pex on test. Rooms 105&107 included. 6/9/2025
06/11/2026 COT - HCPL - Plumbing Progress  Not Ready
06/17/2024 COT - HCPL - Plumbing Progress  Partial Pass North side of structure, 8” sewer line with 6” laterals to new man hole. mom to cover progress areas.
06/18/2024 COT - HCPL - Plumbing Progress  Partial Pass Sewer line (8”) with 5 laterals (6”) at North side of building center to West side. Ok to compact and back fill progress areas.
06/18/2026 COT - HCPL - Plumbing Progress  Partial Pass
06/21/2024 COT - HCPL - Plumbing Progress  Partial Pass North side sewer lines at private man hole. Pressure tested at both sides. Ok to cover progress areas.
06/30/2026 COT - HCPL - Plumbing Progress  Partial Pass Partial pass 2nd floor MEP approved units 210, 211. 6/30/2026
07/07/2026 COT - HCPL - Plumbing Progress  Partial Pass Partial pass. 2nd floor MEP approved in units 213, 214,215,216,218,217. 7/7/2026
07/10/2026 COT - HCPL - Plumbing Progress  Partial Pass Partial pass. MEP approved 2nd floor units 219,220,221,222. 7/10/2026
07/12/2024 COT - HCPL - Plumbing Progress  Partial Pass Sewer lines (4” and 8”) and laterals on North side of building. Ok to cover progress areas.
07/16/2026 COT - HCPL - Plumbing Progress  Not Ready
07/17/2024 COT - HCPL - Plumbing Progress  Partial Pass Fire truck turn-around area; 2” - 4” vent and drain lines. Ok to cover progress areas.
07/22/2026 COT - HCPL - Plumbing Progress  Not Ready
07/28/2026 COT - HCPL - Plumbing Progress  Partial Pass 7-28-26: Inspection of MEP's above ceiling at garage entryway- add ground screws to 6-metal boxes. Penetrations above ceiling grid properly fire caulked and DWV supported. Will need to verify ground screws but okay to continue with construction at progress areas.
08/09/2024 COT - HCPL - Plumbing Progress  Partial Pass Swimming pool equipment room plumbing. Ok to cover progress areas.
09/29/2023 COT - HCPL - Plumbing Progress  Partial Pass Plumbing underground: waste lines at 4” - 8’ lines in section C. Ok to cover progress areas.
10/23/2024 COT - HCPL - Plumbing Progress  Partial Pass Waste lines in South portion of structure (2” - 4” lines)
10/24/2024 COT - HCPL - Plumbing Progress  Partial Pass Level #1, plumbing bang plates installed in room units; S133, S135, S138, S139, S140, S157, S158, S160.
10/29/2024 COT - HCPL - Plumbing Progress  Partial Pass Level #1, room units S141, S143, S144, S148, S159.
12/06/2024 COT - HCPL - Plumbing Progress  Partial Pass Domestic water lines on Levels 3, 4, 5 in sections A and B. Lines under test at 110 psi.
12/16/2024 COT - HCPL - Plumbing Progress  Partial Pass Parking garage waste and vent lines: 2” - 10”. Hose bib lines need to tested.
12/23/2024 COT - HCPL - Plumbing Progress  Partial Pass Domestic main lines (3” - 4”) in parking garage. Hose bibs to be installed when RFI,is,received.