Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCEL - Electrical Intermediate
Permit Number - T21CM09453
Inspection Description - COT - HCEL - Electrical Intermediate
Inspection Status - Partial Pass
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/09/2025 | COT - HCEL - Electrical Intermediate | Partial Pass | Level #2, Section A room units:S330, S329, S356, S358, S360, S340, S339, S338, S337, S336, S335, S333, S334, S331. | |
| 01/14/2025 | COT - HCEL - Electrical Intermediate | Partial Pass | Level #3, Area B: Room units S355, S354, S353, S351, S350, S348, S349, S347, S346, S345, S344, S343, S342, S341, S359, S357. | |
| 01/22/2026 | COT - HCEL - Electrical Intermediate | Re-inspection required | 1/22/26: nail plates required for electrical and plumbing that come within 1 1/4" from face of 2x, over notched studs both at bearing and non bearing walls must be properly fixed and be addressed prior to next inspection, fire caulking required at all penetrations through top plate and vapor barrier, Properly secure nm cable throughout, receptacle spacing not per approved plans not per code (bedrooms and living rooms) staples required throughout at nm cables coming out of box. units inspected were (402, 426, 428,413,414,415 receptacle at bathroom, 416,418) notes are the same for all. | |
| 01/30/2026 | COT - HCEL - Electrical Intermediate | Partial Pass | 405,428,412,413,414,415,416,418,417,419,420,421. in wall approved. Pending draft stop at every 10’mat party walls and drop ceiling inspections. Okay to proceed with progress areas. 1/30/2026 | |
| 02/06/2026 | COT - HCEL - Electrical Intermediate | Partial Pass | 2/6/26: MEP 4TH FLOOR AREA C 427,425,424,401,408,407,405, 406,404,427,425,424,404,426,428,412,413,414,415,416, 418,417, 419,420 | |
| 03/04/2025 | COT - HCEL - Electrical Intermediate | Partial Pass | In wall electric for units: 242, 246, 247, 248, 257, 259. | |
| 05/01/2025 | COT - HCEL - Electrical Intermediate | Partial Pass | 3/19/25: section A rooms, 431,432,434,433,435,436,439,440 ( Not ready will need to re-inspect rooms) 3/25/25: Section A 4th floor rooms (441,460,459,458,457,456) not ready multiple issues need to be addressed prior to re-inspection. 3rd floor room 352 not ready 3/28/25: Section B 4th floor rooms (455,454,453,452,451,450,449,448,446) Not ready multiple issues need to be addressed prior to re-inspection. 4/3/25: Re-inspection required with fee 5/1/25: Electrical intermediate in rooms 557,558,559,560,536 approved. |
|
| 06/20/2025 | COT - HCEL - Electrical Intermediate | Partial Pass | 6-20-25: rough electrical on room's 172, 173, 174, 175 (secure awg wires to framing within 12" of wires exiting a box and staple every 4' thereafter & firefoam penetrations at top plates), 170-add staple within 12" of awg wires exiting a box, 169-firefoam penetrations at blocking or top plates,168-staple awg within 12" of light switch and every 4' thereafter, firefoam DWV at penetrations. Items mentioned will be verified at intermediates-okay to continue with construction. | |
| 10/15/2024 | COT - HCEL - Electrical Intermediate | Partial Pass | Electric room #116; Ok to Sheetrock throughout. | |
| 10/23/2024 | COT - HCEL - Electrical Intermediate | Not Ready | Will reschedule for 24 October. | |
| 10/24/2024 | COT - HCEL - Electrical Intermediate | Partial Pass | In wall electric in room units; S133, S135, S138, S139, S140, S157, S158, S160. | |
| 10/29/2024 | COT - HCEL - Electrical Intermediate | Partial Pass | Level #1 in wall electric in room units S141, 143, 144, 148, 159. OK to insulate and cover walls. | |
| 12/10/2024 | COT - HCEL - Electrical Intermediate | Partial Pass | Level #2 Room units: S229, S230, S231, S232, S233, S234, S235, S236, S238, S239, S240, S241, S256,S258, S260 | |
| 12/11/2025 | COT - HCEL - Electrical Intermediate | Canceled | 12/11/2025 canceled per contractor. |