Permit Number: T22CM03953
Parcel: 140440040

Review Status: Completed

Review Details: COMMERCIAL - BLDG/FIRE/ZONING/ENG

Permit Number - T22CM03953
Review Name: COMMERCIAL - BLDG/FIRE/ZONING/ENG
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
05/24/2022 VFLORES1 PIMA COUNTY - ADDRESSING PIMA COUNTY - ADDRESSING Reqs Change PLEASE CONTACT PC ADDRESSING BUILDING NUMBER NEEDS TO BE ASSIGNED PRIOR TO ISSUANCE PH# 520-724-9512, ADDRESSING@PIMA.GOV
06/07/2022 SAFEBUILT 2ND PARTY REVIEW REVIEW Reqs Change Activity Number: T22CM03953

GENERAL:
Provide written responses to all review comments.
Provide a complete plan set.
Provide additional documents as requested by review staff.


STRUCTURAL REVIEW COMMENTS:
Denied
1. Provide Geotechnical Report for the proposed building per International Building Code 2018, Section 1803.1.
2. Verify the design lateral pressure from the surcharge loads are included in the lateral earth pressure load and design of the foundation wall as indicated in IBC 2018 Section 1610.1
3. The requirements in OSHA 1926.757 for the erection of open web steel joists are to be followed. Where steel joists are used with columns that are not framed in at least two directions with solid web structural steel members, a steel joist shall be field-bolted at the column to provide lateral stability to the column during erection. Where constructability does not allow a steel joist to be installed at the column the joists are to be stabilized on both sides of the column.
4. Except for steel joists that have been pre-assembled into panels, connections of individual steel joists to steel structures in bays 40 feet or more shall be fabricated to allow for field bolting during erection.
5. Provide a vertical stabilizer plate at columns for steel joist as required by OSHA 1926.757.
6. Verify OSHA steel erection standards for open web steel joists. Section 1926.757 (a)(8) requires connections of individual steel joists to steel structures in bays of 40 feet or more shall be fabricated to allow for field bolting during erection.
7. Verify loadings shown on Joist Purlin (JP) Schedule and Joist Girder (JG) Schedule on Drawing S0.3 and the loadings shown on Structural Calculation on sheets 6, 7 and 8 of Structural Calculations submitted. They don’t match, make changes as needed.
8. Structural steel, components and fasteners that are exposed to weather are to be protected against corrosion in accordance with AISC 360 Section B.13 as indicated in IBC 2018 Section 2203.1.
9. Designer is to coordinate venting and drainage hole requirements for HSS tube members that are galvanized using the hot-dip galvanizing process. Provide for plugs as needed. AWS D-19.0 calls for welds on galvanized steel to be free of zinc. Field welds on galvanized parts requires the removal of the zinc coating in the area of weld. Provide zinc paint (approved by the galvanizer) and apply as required to the weld and steel area to provide protection.
10. Show lines of bridging for the steel joists per the recommendation of the Joist Manufacturer.
Submit a response letter addressing these correction items and provide bubbles on the revisions to the drawings.


BUILDING REVIEW COMMENTS:
Denied
Construction documents – Permit application project address is “4761” East Los Reales Rd., while structural calculation shows “150”, architectural and structural drawing sheets show “4150”, mechanical/plumbing/electrical sheets show “150” that show discrepancies. Provide accurate address for all construction documents including permit application. What is the project address?
Sheet A0.1 – Civil and landscape drawings missing. Sheet A1.1 states to reference civil and landscape drawings but missing in set. Show exterior wall opening dimensions coordinated with sheet S4.1-4.2.
Sheet A0.1 – Window schedule, door schedule, wall type schedule, finish schedule and reflected ceiling plans missing from construction document. Provide complete scope of work to clarify.
Sheet A0.1a – Include “City of Tucson/Pima County Outdoor Lighting Code” in applicable codes.
Sheet A0.5 – What are the provided maximum travel distance to exits? Only maximum distance shown. Show proposed future office area in life safety/egress plan.
Sheet A1.0 – Show fire hydrant locations in overall site plan. Show all items on site legend.
Sheet A2.2 – Show all door window and door tags in floor plans. For example, exterior double door located at grid 1/E is missing door identifier tag.
Structural calculations – 5th page plan shows structural grid up to “16” while structural drawings only show structural grid up to “15”. Provide coordinated drawings and structural calculation documents.
Geotechnical report missing while referenced in structural sheets


MECHANICAL REVIEW COMMENTS:
Denied
1. Provide mechanical plans (IMC2018,106.3.1)
2. Provide ventilation calculations (IMC2018,,403.3.1.1.1)
3. Provide a detailed narrative on the process that occurs in the warehouse (e.g. what materials are you storing in the warehouse, what type of forklifts are you using in the warehouse is it fuel or electric) (imc2018,106.3.1)


ELECTRICAL REVIEW COMMENTS
Denied
E1.1 PHOTOMETRIC PLAN: Need to provide an exterior lighting power density calculation per Tucson City requirements.
E4.1 PARTIAL ELECTRICAL POWER - FIRST FLOOR PLAN:
Need to provide interior lighting to a minimum level ie stumble lighting, emergency lighting, and exit signage.
Need to provide an interior lighting comcheck to show compliance to 2018 IECC code.
Need to provide service receptacles within 25 feet of any HVAC equipment or conditioned space. Should provide an additional 4-6 receptacles for a Core and Shell design throughout the building.
E4.2 PARTIAL ELECTRICAL POWER - FIRST FLOOR PLAN: See comments on E4.1.


PLUMBING REVIEW COMMENTS:
Denied
1). Plumbing Plan pages MP3.3, MP3.4 show 6" roof drains/overflow drains & shows scuppers with downspouts. Plan page A6.2 only shows scupper with downspout detail, Add Roof drain/overflow detail for roof assembly & discharge termination detail to plan page A6.2 -IPC 106.3.1
2). Plan submittal needs to include site utility piping plan for continuation of water, sewer, storm piping. -IPC 106.3.1
3). Add roof drain & clean out assembly manufacturer name & model numbers to plan pages. MP2.0 -IPC 303
4). Add storm piping material types to plan page MP0.0. -IPC 1102


If you require additional clarification regarding these comments, please contact Doris Benoit at doris.benoit@tucsonaz.gov
06/15/2022 ROBERT SHERRY WATER REVIEW Completed
06/21/2022 WBERGER1 ZONING REVIEW Reqs Change PDSD TRANSMITTAL

FROM: Wyatt Berger
Planner

PROJECT: T22CM03953
4150 E Los Reales Rd
New industrial warehouse building (1st Review)

TRANSMITTAL DATE: June 21, 2022

COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed.

1. Zoning has reviewed the building plans for compliance with DP22-0122. Although it appears that the building plan matches the DP, Zoning cannot approve the building plan until the DP is approved.

If you have any questions about this transmittal, please contact Wyatt Berger at Wyatt.Berger@tucsonaz.gov.
06/21/2022 WBERGER1 COMMERCIAL IMPACT FEE COMMERCIAL IMPACT FEE PROCESSING Needs Review
06/28/2022 SSHIELD1 ENGINEERING REVIEW Reqs Change See Zoning comments
07/07/2022 JVINCEN1 FIRE REVIEW Reqs Change See building comments

john.vincent@tucsonaz.gov
5203495581
10/14/2022 LMAKUS1 LANDFILL REVIEW Passed Greater than 1000 feet from landfill.

Final Status

Task End Date Reviewer's Name Type of Review Description
10/14/2022 NGARCIA3 OUT TO CUSTOMER Completed