Permit Review Detail
Review Status: Completed
Review Details: RESUBMITTAL
Permit Number - T21CM06867
Review Name: RESUBMITTAL
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
05/24/2022 | SAFEBUILT | 2ND PARTY REVIEW | REVIEW | Reqs Change | Activity Number: T21CM06867 GENERAL: Provide written responses to all review comments. Provide a complete plan set. Provide additional documents as requested by review staff. STRUCTURAL REVIEW COMMENTS: Denied THE RESPONSE LETTER SAYS THAT THE FOLLOWING ITEMS ARE ATTACHED, NONE OF THE FOLLOWING ITEMS WERE FOUND IN THIS SUBMITTAL. 1. Provide Structural Calculations for Foundations, retaining walls and Columns per Section 1601.1 of International Building Code 2018. The calculations submitted are inadequate, submit complete set of calculations. 2. Provide Wind Load Calculations for the Building per Section 1609 of International Building Code 2018. The calculations submitted show X bracing at few places seems inadequate. Submit complete set showing how wind loads are resisted in both directions and how the roof deck is transferring the wind loads to the Lateral Load Resisting Frames. 3. Provide Seismic Calculations for the Building per Section 1613 of International Building Code 2018. The calculations submitted show X bracing at only few places seems inadequate. Submit complete set showing how seismic loads are resisted in both directions and how the roof deck is transferring the seismic loads to the Lateral Load Resisting Frames. 4. Provide details and calculations for all design items that are not deferred. Design items include (but are not limited to) footings, anchor rods, roof joists/girders, shear walls, diaphragm, and struts. Calculations are to include loading, load combinations, design loads, and column reactions. 5. All Calculations shall be sealed and signed by Professional Engineer registered with State of Arizona per Section 107.1 of International Building Code 2018. BUILDING REVIEW COMMENTS: Denied 1. While the provided areas do meet the maximum areas permitted however, they do exceed 10% of the area permitted for unlimited buildings. Additionally, the aggregate areas of H occupancies not on the perimeter of the building exceed 25%. Provide area compliant plans in accordance with Sections 507.8.1 and 507.8.1.1. MECHANICAL REVIEW COMMENTS: Denied 1. Provide overpressure protection device for gas line (IMC2018,416) Response: Gas line overpressure protection device specified on GAS PRV SCHEDULE on sheet P3.3. Complied 2. A report SHALL BE submitted to the building official identifying the maximum expected quantities of hazardous materials to be stored, used in a closed system and used in an open system, and subdivided to separately address hazardous material classification categories based on Tables 307.1(1) and 307.1(2). THE METHODS OF PROTECTION FROM SUCH HAZARDS, INCLUDING BUT NOT LIMITED TO control areas, fire protection systems and Group H occupancies shall be indicated in the report and on the construction documents. The opinion and report shall be prepared by a QUALIFIED person, firm or corporation APPROVED BY THE BUILDING OFFICIAL and provided without charge to the enforcing agency. (IBC2018, 414.1.3) Response: Hazardous Material Opinion and Response.pdf as performed by Ino-Tek, Inc. as well as Method of Protection response.pdf uploaded along with this response letter for building official review. Based on the findings of the report the architect of record is requesting two modifications as allowed by Section 104.10 Modifications (IBC2018). This modification request letter has also been uploaded and titled Modification Request.pdf. Not Complied there is no report from Ino-tek provided in your submittal's 3. Provide fire damper where a duct penetrates a fire rated wall (IMC2018,607.5.2) Response: Fire dampers have been provided in any duct that penetrates fire rated walls. Fire dampers specified on sheet M0.1 note 14 under Products. Complied 4. Fan powered terminals shall shut down when the rtu smoke detectors are activated along with the rtu (IMC2018,606.2.2) Response: Note added to fan powered terminal schedule on sheet M0.2 stating “FAN POWERED TERMINALS SHALL SHUT DOWN ALONG WITH THE ASSOCIATED RTU WHEN THE RTU SMOKE DETECTOR ACTIVATES.” Complied 5. Ducts shall be protected with a shaft when penetrating a 3 hour rated wall(IMC2018,607.5.2) Response: Clarified on discussion with author of this comment on conference call that this code section does not apply to the mechanical plans as designed. Complied 6. Provide ventilation tables (IMC2018.403.3.3) Response: Ventilation table provided on new sheet M0.6 Complied ELECTRICAL REVIEW COMMENTS Approved PLUMBING REVIEW COMMENTS: Denied second Plumbing Review: 1). Ok 2). OK 3). OK 4). Ok 5). OK 6).OK 7). OK 8). OK 9). Ok 10). OK 11). OK 12). Ok 13). OK 14). OK 15). What Will the S2 Sink in Chem lab & the battery area scrubber be discharging to the sanitary system? will these items or any other fixtures/drains be discharging harmful substances to the drainage system that will require an interceptor? _IPC 1003.1 If you require additional clarification regarding these comments, please contact Doris Benoit at doris.benoit@tucsonaz.gov |
05/31/2022 | STEVE SHIELDS | ZONING | REVIEW | Approved | |
05/31/2022 | SSHIELD1 | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Completed | |
06/08/2022 | JPEELDA1 | FIRE | REVIEW | Reqs Change | IFC 6004.2.2.10- 6004.2.2.10.1 Gas detection system states they are required to have a gas detection system and the notification is local with audible and visual indicators inside and outside the area of gas detection. This should also be distinct from other types of alarms No copper, silver or magnesium piping/material shall be used in vicinity of EO, as it can cause it to explode. Confirm that the exhaust system is not connected to main building supply power and in event of emergency these do NOT shut off. Provide a detailed narrative on the process that occurs in the sterilization process. Provide a detailed list of chemicals and quantities of chemicals being stored in and outside the structure. Ensure these storage areas meet the requirements of the IBC and IFC for chemical storage. All doors must swing in the direction of egress. There are multiples doors that do not comply with Section 1010.1.2.1. Building plans shall state: Tucson Fire Department will not authorize future roof mounted solar systems. Solar systems added to the project in the future shall be of shade structure only over the parking lot. Questions: Jennifer Peel-Davis Jennifer.Peel-Davis@Tucsonaz.gov 520-837-7033 |
06/10/2022 | LOREN MAKUS | ENGINEERING | REVIEW | Approved |