Permit Number: T21CM06867
Parcel: 14106020D

Review Status: Completed

Review Details: COMMERCIAL - BLDG/FIRE/ZONING/ENG

Permit Number - T21CM06867
Review Name: COMMERCIAL - BLDG/FIRE/ZONING/ENG
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
09/01/2021 SAFEBUILT 2ND PARTY REVIEW REVIEW Reqs Change Activity Number: T21CM06867

GENERAL:
Provide written responses to all review comments.
Provide a complete plan set.
Provide additional documents as requested by review staff.

STRUCTURAL REVIEW COMMENTS:
Denied
1. Provide Structural Calculations for Foundations, retaining walls and Columns per Section 1601.1 of International Building Code 2018. The calculations submitted are inadequate, submit complete set of calculations.
2. Provide Wind Load Calculations for the Building per Section 1609 of International Building Code 2018. The calculations submitted show X bracing at few places seems inadequate. Submit complete set showing how wind loads are resisted in both directions and how the roof deck is transferring the wind loads to the Lateral Load Resisting Frames.
3. Provide Seismic Calculations for the Building per Section 1613 of International Building Code 2018. The calculations submitted show X bracing at only few places seems inadequate. Submit complete set showing how seismic loads are resisted in both directions and how the roof deck is transferring the seismic loads to the Lateral Load Resisting Frames.
4. Provide details and calculations for all design items that are not deferred. Design items include (but are not limited to) footings, anchor rods, roof joists/girders, shear walls, diaphragm, and struts. Calculations are to include loading, load combinations, design loads, and column reactions.
5. All Calculations shall be sealed and signed by Professional Engineer registered with State of Arizona per Section 107.1 of International Building Code 2018.
6. The requirements in OSHA 1926.757 for the erection of open web steel joists are to be followed. Where steel joists are used with columns that are not framed in at least two directions with solid web structural steel members, a steel joist shall be field-bolted at the column to provide lateral stability to the column during erection. Where constructability does not allow a steel joist to be installed at the column the joists are to be stabilized on both sides of the column.
7. Except for steel joists that have been pre-assembled into panels, connections of individual steel joists to steel structures in bays 40 feet or more shall be fabricated to allow for field bolting during erection.
8. Provide a vertical stabilizer plate at columns for steel joist as required by OSHA 1926.757.
9. DEFERRED SUBMITTAL REQUIREMENTS
Structural general notes are to include any components of the building that may be considered deferred submittals. IBC Section 107.3.4.1 requires deferred submittals to be approved by the building official. Examples of items that likely should not be deferred include deep foundation elements, deep excavation shoring and prefabricated metal buildings. If items will be deferred the plans are to clearly note the following per IBC Section 107.3.4.1:
* To be reviewed by design professional in responsible charge.
* Design professional shall affix a notation that the deferred items are in general conformance with their design of the building.
* They shall be submitted for review by the building official.
* Shall not be installed until approved by building official.
10. Submit a response letter addressing these correction items and provide bubbles on the revisions to the drawings.

BUILDING REVIEW COMMENTS:
Denied
1. Provide a detailed breakdown of the square footages of the occupancies and clearly indicate those areas on the floor plans. These calculations should provide evidence that the square footages meet the requirements that permits this building to be of unlimited square footage.
2. The plans do not indicate what method of mixed occupancy approach is being used. Indicate which approach is being used and associated code requirements in compliance with Section 508.
3. Provide a detailed narrative on the process that occurs in the sterilization process.
4. Provide a detailed list of chemicals and quantities of chemicals being stored in and outside the structure. Ensure these
storage areas meet the requirements of the IBC and IFC for chemical storage.
5. The egress out of the H-3 travels through an intervening space of the S-1 occupancy. Additionally, there are occasions of exit through intervening spaces in the Business occupancy. This travel must comply with Section 1016.2 #5 or Section 1016.2 #2.
6. All doors must swing in the direction of egress. There are multiples doors that do not comply with Section 1010.1.2.1.
7. The plans indicate wall type tags through out, however, no partition schedule could not be located. Provide a detailed partition schedule. Along with any appropriate UL listed assemblies and required separations throughout that are required.


MECHANICAL REVIEW COMMENTS:
Denied

1. provide overpressure protection device for gas line (IMC2018,416)
2. A report SHALL BE submitted to the building official identifying the maximum expected quantities of hazardous materials to be stored, used in a closed system and used in an open system, and subdivided to separately address hazardous material classification categories based on Tables 307.1(1) and 307.1(2). THE METHODS OF PROTECTION FROM SUCH HAZARDS, INCLUDING BUT NOT LIMITED TO control areas, fire protection systems and Group H occupancies shall be indicated in the report and on the construction documents. The opinion and report shall be prepared by a QUALIFIED person, firm or corporation APPROVED BY THE BUILDING OFFICIAL and provided without charge to the enforcing agency. (IBC2018, 414.1.3)
3. Provide fire damper where a duct penetrates a fire rated wall (IMC2018,607.5.2)
4. Fan powered terminals shall shut down when the rtu smoke detectors are activated along with the rtu (IMC2018,606.2.2)
5. Ducts shall be protected with a shaft when penetrating a 3 hour rated wall (IMC2018,607.5.2)
6. Provide ventilation tables (IMC2018.403.3.3)
7. see markups in narratives

ELECTRICAL REVIEW COMMENTS
Denied

E1.3 OFFICE/BATTERY CHARGING LIGHTING PLAN: Where are the lighting controls for Detail #2
E3.4 ROOF FIRE ALARM PLAN: Need to expand notes to use aluminum to copper adapters and use copper conductors within 18 inches of the soil and below. Aluminum cannot be in contact with earth.
E4.1 MAIN SWITCHBOARD "MSB" ONE LINE DIAGRAM:
#18 on conductor schedule needs conductors upsized and another conductor to function as a 3 wire panel. Should use same transformer as used on sheet E4.2 as 15 KVA is not a typical 1 ph transformer size.
Panel HB does not show short circuit calculated value above panel. This panel is rated at 14 KAIC and may be underrated.
Panel MB does not show short circuit calculated value above panel. This panel is rated at 14 KAIC and may be underrated.
Panel HGH does not show short circuit calculated value above panel. This panel is rated at 22 KAIC and may be underrated.
E4.2 MAIN PROCESS DISTRIBUTION PANEL "PMDP" ONE LINE DIAGRAM: Panel HPH shows short circuit calculated value of 46 KA but is rated at 22 KAIC.
E4.3 MOTOR CONTROL CENTER ONE LINE DIAGRAMS:
MCC-A section 1, One Line does not correspond to MCC-A elevation (Section 1 mislabeled 2B and 2C).
MCC-B section 1, One Line does not correspond to MCC-B elevation (Section 1 mislabeled 2B 2C, and 2D).
E5.2 ELECTRICAL SCHEDULES FOR HVAC LOADS: Circuit breakers for MAU- 5, 6, & 7 should call out for 125A CBs, as 120 amp CBs do not exist.

PLUMBING REVIEW COMMENTS:
Denied

1). Add gutter/downspout sizing calculations to A3.0, calculations need to derive from -IPC 1106.3 & 1106.6.
2). Lavatory mixing valve needs to be ASSE 1070 rated. Update plan page P0.2 and or Spec manual section 2.4 -IPC 419.5
3). Non potable piping system needs to be distinguished from the potable piping & labeled/colored per IPC 608.9.2 thru 608.9.2.3 update P0.2 and spec manual section 2.15
4). Non potable outlets need to have proper signage per IPC 608.9.1 update P0.2 and or spec manual. Labeled as NPW as shown on P1.0 is not compliant, update notes.
5). Provide an RPZ schedule on P0.2 with manufacturer names, model numbers, & locations. -IPC A106.3.1 608.3
6). Gas plans need to include a combustion air detail with calculations for the 3 boilers & 2 Lesni Abatement units. -IFGC 304.1 thru 304.12 if the combustion air is provided from an mechanical air system, that system will need to be interlocked with the gas system of those appliances. IFGC 304.9.2
7). Notate on P3.3 what gas sizing table was used. IFGC 402.4
8). Lowered gas pressures are shown on P1.5 & P1.6, include a regulator/vent detail and add a regulator schedule to the gas plans. -IFGC A106.3.1& 410.1 thru 410.3.1
9). Gas plans and need to include a complete gas equipment schedule, with manufacturer names. model numbers, locations, & BTU ratings. IFGC A106.3.1
10). Add a gas water heater exhaust detail to P2.1 -IFGC A106.3.1 & 501.2
11). Boiler exhaust detail on PR0.3 PR2.2 need to include exhaust vent size/material. IFGC A106.3.1 & 501.2
12). Add a Lesnni Abatement unit exhaust to roof termination detail to plan page PR3.1 & M1.3 _IFGC A106.3.1 & 501.2
13). Due to the H-3 occupancy, do the locations & installation methods of all the gas equipment comply with IFGC 305.2 thru 305.3?
14). Provide updated plan set & response narrative for re-submittal
09/08/2021 STEVE SHIELDS ZONING REVIEW Reqs Change ZONING REVIEW TRANSMITTAL

FROM: PDSD Zoning Review

PROJECT:
T21CM06867
7345 E Valencia Rd ā€“ PAD-26
New Building ā€“ Processing & Cleaning

TRANSMITTAL: September 8, 2021
This site is located in PAD-26, Processing & Cleaning is an allowed use in this PAD, subject to UDC Use Specific Standards 4.9.5.C.2, .5, .6, .7, & .8 and 4.9.13.Q, with Hazardous Material Storage as an accessory use subject to UDC Use Specific Standards 4.9.10.B.1 & 2.dā€.

1. The building plans have been reviewed for compliance with DP21-0097 and although it appears that the plan match unit DP21-0097 has been approved Zoning cannot approve the building plans.

2. Demonstrate on the plan or by calculation that the requirements of UDC Use Specific Standards 4.9.10.B.1 & 2.d are not exceeded.

3. The drawing index calls out for the development pack sheets to be in the building set. Once provided in the set they will either need to be the stamped approved DP set, marked for reference only.


If you have any questions about this transmittal, please contact Elisa Hamblin at Elisa.Hamblin@tucsonaz.gov.
09/14/2021 ROBERT SHERRY WATER REVIEW Completed
09/16/2021 SBLOOD1 ENGINEERING REVIEW Reqs Change The DP needs to be approved before the building plans can be approved.

Stephen Blood
(520) 837-4958
Stephen.blood@tucsonaz.gov
09/16/2021 NROSS1 COMMERCIAL IMPACT FEE COMMERCIAL IMPACT FEE PROCESSING Reqs Change Impact Fees will be assessed upon next submittal
09/27/2021 JPEELDA1 FIRE REVIEW Reqs Change IFC 6004.2.2.10- 6004.2.2.10.1 Gas detection system states they are required to have a gas detection system and the notification is local with audible and visual indicators inside and outside the area of gas detection.
This should also be distinct from other types of alarms
No copper, silver or magnesium piping/material shall be used in vicinity of EO, as it can cause it to explode.
Confirm that the exhaust system is not connected to main building supply power and in event of emergency these do NOT shut off.
Provide a detailed narrative on the process that occurs in the sterilization process.
Provide a detailed list of chemicals and quantities of chemicals being stored in and outside the structure. Ensure these storage areas meet the requirements of the IBC and IFC for chemical storage.
All doors must swing in the direction of egress. There are multiples doors that do not comply with Section 1010.1.2.1.
Building plans shall state: Tucson Fire Department will not authorize future roof mounted solar systems. Solar systems added to the project in the future shall be of shade structure only over the parking lot.

Questions:
Jennifer Peel-Davis
Jennifer.Peel-Davis@Tucsonaz.gov
520-837-7033

Final Status

Task End Date Reviewer's Name Type of Review Description
09/27/2021 VVERA1 OUT TO CUSTOMER Completed