Review Status: Completed
Review Details: POST 3RD PARTY REVIEW
Permit Number - T19CM07159
Review Name: POST 3RD PARTY REVIEW
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 01/29/2020 | ROBERT SHERRY | WATER | REVIEW | Completed | |
| 01/30/2020 | MROSS2 | FIRE | REVIEW | Reqs Change | The fire pump room is noted on the lower level but only on one page of the plan set, please indicate the fire pump room on all pages and ensure that the requirements are met for the pump room as listed in the previous coments and included below. Provide location and specifications for fire pump room. Fire Pump Room shall comply current codes: IFC 913.1 through 913.5 and NFPA 20. Including, power supply, equipment access, lighting, ventilation, drainage. 913.2.2 Circuits supplying fire pumps. Cables used for survivability of circuits supplying fire pumps shall be protected using one of the following methods. 1. Cables shall be listed in accordance with UL 2196 and shall have a fire-resistance rating of not less than 1 hour. 2. Electrical circuit protective systems shall have a fire-resistance rating of not less than 1 hour. 3. Construction having a fire resistance rating of not less than 1 hour. NFPA 20 4.13.2 Equipment access 4.13.2.1.1 Except as provided in 4.13.2.1.1.1 fire pump rooms not directly accessible from the outside shall be accessible through an enclosed passageway from an enclosed stairway or exterior exit. 4.13.2.1.2 The enclosed passageway shall have a fire resistance rating not less than the fire resistance rating of the fire pump room. 4.13.5 Pump rooms shall be provided with emergency lighting 4.13.7 Drainage. 4.13.7.1 Floors shall be pitched for adequate drainage of escaping water away from critical equipment such as the pump, driver, controller, and so forth. 4.13.7.2 The pump room or pump house shall be provided with a floor drain that will discharge to a frost-free location. 03-12-2020- Pages reviewed that address corrections required for the fire pump room. Once the pages are added to the plan set the plans can be approved. NOTE: Please verify the size of the fire pump and that the equipment will fit through the proposed doors to access the pump room. from the gound floor all the was into the pump room. |
| 01/30/2020 | DJELLEN1 | ZONING | REVIEW | Reqs Change | FROM: David Jellen PDSD Zoning Review Section PROJECT: T19CM07159 - New Building (Residential - Student Housing / Group Dwelling) Building Plan Review (2nd Review) Hub on Campus / Related to DP19-0056 934 E. Speedway Blvd. C-1 Zoning (to UC-1 upon DP approval) TRANSMITTAL DATE: February 6, 2020 COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed. 1. The provided zoning for the site in the code matrix on the building plans is incorrectly listed as UC-3. Revise the zoning to be listed as UC-1, per the approved development package. 2. Clarify the setbacks of the development in the code matrix on the building plans so that they are consistent with what has been approved on the development package. 3. Clarify the gross square footage of the development in the code matrix on the building plans so that it is consistent with what has been approved on the development package. 4. Clarify the location of all short-term bicycle parking areas. Short-term bicycle parking must be accessible to the public. Per the approved development package, 53 short-term bicycle parking spaces are being provided. The code matrix for the building plans show that 86 short-term bicycle parking spaces will be provided. 5. Clarify the location of all long-term bicycle parking spaces. Per the approved development package, 48 long-term bicycle parking spaces are being provided. The code matrix for the building plans show that 86 short-term bicycle parking spaces will be provided. 6. Zoning cannot approve the plans until the plans have been approved by the design professional. If you have any questions about this transmittal, Contact David Jellen at (520) 837-4082 or by email at David.Jellen@tucsonaz.gov or contact Steve Shields at (520) 837-4956 or Steve.Shields@tucsonaz.gov |
| 02/10/2020 | JOHN VAN WINKLE | ENGINEERING | REVIEW | Approved | |
| 03/13/2020 | PMARTIN1 | DESIGN PROFESSIONAL | REVIEW | Needs Review |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 03/13/2020 | PMARTIN1 | OUT TO CUSTOMER | Completed |