Plan Number: S06-031
Parcel: Unknown

Review Status: Completed

Review Details: RESUBMITTAL - CDRC - FINAL PLAT REVIEW

Plan Number - S06-031
Review Name: RESUBMITTAL - CDRC - FINAL PLAT REVIEW
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
01/05/2007 KAY MARKS PIMA COUNTY ADDRESSING Denied 201 N. STONE AV., 1ST FL
TUCSON, AZ 85701-1207

KAY MARKS
ADDRESSING OFFICIAL
PH: 740-6480
FAX #: 740-6370


TO: CITY PLANNING
FROM: KAY MARKS, ADDRESSING OFFICIAL
SUBJECT: S06-031 SIERRA MORADO UNIT 4/REVISED FINAL PLAT
DATE: 1/05/07



The above referenced project has been reviewed by this Division for all matters pertaining to street naming/addressing, and the following matters must be resolved prior to our approval:

Change Civano Master Block Plat Block 82 Book 50, Page 36 to Civano I Book 52, Page 84 on pgs. 2 (western most,) 5, 6, 11 & 12.

Change Morning Shadow Drive to Morning Shadows Drive on pg. 2 (southern most).


es
01/05/2007 PATRICIA GEHLEN ZONING-DECISION LETTER REVIEW Denied COMMUNITY DESIGN REVIEW COMMITTEE
DEVELOPMENT SERVICES

January 5, 2007

Ryan R. Stucki, PE
Stantec Consulting
201 North Bonita
Tucson, AZ 85745

Subject: S06-031 Sierra Morado Unit 4 Final Plat

Dear Ryan:

Your submittal of December 6, 2006 for the above project has been reviewed by the Community Design Review Committee and the comments reflect the outstanding requirements which need to be addressed before approval is granted. Please review the comments carefully. Once you have addressed all of the comments, please submit the following revised documents and a DETAILED cover letter explaining how each outstanding requirement has been addressed:

ALL BLUELINES MUST BE FOLDED

4 Copies Revised Final Plat (TEP, Addressing, Engineering, DSD)








Should you have any questions, please call me at 791-5608 ext. 1179.

Sincerely,


Patricia Y. Gehlen
CDRC Manager

All comments for this case are available on our website at http://www.ci.tucson.az.us/dsd/

Via fax: 750-7470
12/06/2006 FERNE RODRIGUEZ START PLANS SUBMITTED Completed
12/19/2006 FRODRIG2 PIMA COUNTY WASTEWATER Approv-Cond December 19, 2006

To: Ryan Stucki, P.E.
Stantec Consulting, Inc.

Thru: Patricia Gehlen, CDRC Project Manager
City of Tucson Development Services Department

From: Chandubhai C. Patel, P.E.
Pima County Development Services Department
Development Review Division (Wastewater)

Subject: Sierra Morado, Unit 4
Lots 1118-1530 and Common Areas "A", "B" and "C"
Final Plat – 4th Submittal, S06-031

The drawings for the proposed final plat of the above-referenced project have been reviewed on behalf of the Pima County Department of Environmental Quality (PDEQ) and the Pima County Wastewater Management Department (PCWMD). This review letter may contain comments pertaining to the concerns of either Department. The following comments are offered for your use.


1. A Sewer Service Agreement was emailed to you on June 5, 2006. This needs to be executed in triplicate and returned to us for further processing. The Mylars for this project cannot be approved until these documents are received by us.

SUBJECT TO THE ABOVE, the Pima County Department of Environmental Quality and the Wastewater Management Department hereby approve the above referenced submittal of the Final Plat as received by us on December 5, 2006.

Please note the following: Approval of the above referenced submittal does not authorize the construction of public or private sewer collection lines, or water distribution lines. Prior to the construction of such features, a Construction Authorization (Approval To Construct) may need to be obtained from the Pima County Environmental Quality Department.

Also, air quality activity permits must be secured by the developer or prime contractor from the Pima County Department of Environmental Quality before constructing, operating, or engaging in any activity which may cause or contribute to air pollution.

If you have any questions regarding the above comments, please do not hesitate to contact me.




Sincerely,




Chandubhai C. Patel, P.E.
Phone: 520-740-6563

Copy: Project File
12/20/2006 GLYNDA ROTHWELL UTILITIES TUCSON ELECTRIC POWER Denied SUBJECT: SIERRA MORADO, UNIT 4

S06-031



Tucson Electric Power Company (TEP) has received the final plat
submitted for review December 6, 2006. This Company is unable to
approve the plat at this time.



TEP is in the process of completing the electrical design to determine
our easement requirements. The design will be completed approximately
01/31/2007.



Please contact me at (520) 917-8745 if you have any questions.


Liza Castillo, Right of Way Agent
Land Management
Tucson Electric Power Co.
Unisource Energy Gas & Unisource Energy Electric
PH: (520) 917-8745
lcastillo@tep.com <mailto:lcastillo@tep.com>
12/21/2006 LAITH ALSHAMI ENGINEERING REVIEW Denied Laith Alshami, Engineering and Floodplain Review, 12/21/2006,

TO: Patricia Gehlen FROM: Laith Alshami, P.E.
CDRC Engineering

SUBJECT: Sierra Morado Unit 4
S06-031, T15S, R15E, SECTION 01

RECEIVED: Final Plat and Assurances on December 06, 2006

The subject project has been reviewed. We offer the following comments:

Final Plat:

1. Drexel Road right of way shown on Sheet 5/17 appears to stop short of the property line. It is not clear if the right of way dimension is wrong or the property line location is not correct (D.S. 2-03.6.5.B.).
2. Although the existing Nebraska Road appears to be on private land and does not have a dedicated right of way, it appears that it is being used by several parcels for access. Eliminating or blocking the roadway might create some access problems for the adjacent neighbors. Additionally, even if the roadway is not being used for access by the public, most of Nebraska road is dedicated as a sewer and telephone easement, which means that access to the utility companies has to be maintained. Investigate this issue and check with all the adjacent parcels owners (including Pima County) and impacted utilities if they currently use this road for their primary access and if they still need it to stay this way. This Office recommends setting up a meeting, with City Staff to address the access issue and hopefully resolve it. Contact the Civano Project Manager (Hector Martinez at 791-4545, Ext. 108) to set up the meeting.

Assurances

The submittal did not include a copy of the assurance package. Provide a revised Assurances Package that includes the following information:

1. Add, in Exhibit "B", the following as a separate assurable item "All applicable fees, e.g. permit fees, impact fees must be paid in full to the City of Tucson prior to the final release of subdivision assurances.
2. Revise the description of Common Area "B" through out the Assurance document to match the Final Plat.
3. Include the "Trust Agreement" in the Assurances Package.
4. Include the "Special Warranty Deed" in the Assurances Package.
5. Include in the Assurances Package and up to date Title report.


RESUBMITTAL REQUIRED: Revised Final Plat and Assurances