Permit Review Detail
Review Status: Completed
Review Details: DEV STDS MODIFICATION REVIEW
Permit Number - DS18-06
Review Name: DEV STDS MODIFICATION REVIEW
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 02/21/2018 | QJONES1 | START | PLANS SUBMITTED | Completed | |
| 02/22/2018 | JPEELDA1 | FIRE | REVIEW | Approved | |
| 02/22/2018 | DAVID RIVERA | ZONING | REVIEW | Denied | CDRC TRANSMITTAL TO: Development Services Department Plans Coordination Office FROM: Steve Shields Principal Planner PROJECT: DS18-06 Atlas Copco Expansion DP17-0174 TRANSMITTAL DATE: February 22, 2018 DUE DATE: February 27, 2018 COMMENTS: 01. 01. Modification request to PAG Dtl. 206 - Denied as no TSM reference was provided and PAG details are not a Technical Standard and therefore may not be modified by this process. If you have any questions about this transmittal, please call Steve Shields, (520) 837-4956 |
| 02/22/2018 | SSHIELD1 | H/C SITE | REVIEW | Passed | |
| 02/23/2018 | ZELIN CANCHOLA | TRAFFIC | TRAFFIC | Reqs Change | DS18-06 Atlas Copco February 23, 2018 1. Relief from maximum 10% slope is denied. |
| 03/02/2018 | LOREN MAKUS | ENGINEERING | REVIEW | Passed | |
| 03/12/2018 | AHINES2 | ENV SVCS | REVIEW | Needs Review | |
| 03/12/2018 | ALEXANDRA HINES | ZONING-DECISION LETTER | WRITE DECISION LETTER | Reqs Change | Courtney & Kevin The TSMR will need to be resubmitted with the following change to the application; Reference TSM Section 10-01.4.3.A & .B not the PAG detail. Zoning will do this as an over-the-counter review but I can speak for the other review agencies. There will be no additional fees. |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 03/12/2018 | AHINES2 | OUT TO CUSTOMER | Completed |