Permit Number: TD-DEV-0323-00170
Parcel: 14106020D

Review Status: Requires Resubmit

Review Details: DEVELOPMENT PACKAGE REVIEW v.1

Permit Number - TD-DEV-0323-00170
Review Name: DEVELOPMENT PACKAGE REVIEW v.1
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
04/25/2023 Commercial Plumbing APPROVED
04/25/2023 NPPO APPROVED
04/27/2023 CDRC Post Review PENDING ASSIGNMENT
04/24/2023 External Reviewers - Tucson Airport Authority REQUIRES RESUBMIT Scott Robidoux <srobidoux@flytucson.com>
Good afternoon,
Attached is a copy of TAA’s comment letter on TD-DEV-0323-00170.

Thank you,
Scott Robidoux, C.M.
Manager of Planning
TUCSON AIRPORT AUTHORITY
7250 South Tucson Blvd, Suite 300
Tucson, Arizona 85756
Phone 520-573-8100
Direct 520-573-4811
04/25/2023 ROW Engineering Review REQUIRES RESUBMIT TP-PRE-1222-00061
7345 E. Valencia Rd.

Comments:
1. A PIA is going to be required for this project. https://www.tucsonaz.gov/tdot/private-improvement-agreement Contact TDOT Engineering for information. DOT-Engineering-Review-Section@tucsonaz.gov Or call. 520-791-5100 Jesus Villezcas
2. Please provide the PIA number for DP approval.

Construction requirements in the Right of Way-

1. SRP Pipe must conform to P.A.G. standard specification, 1010-2 DRAINAGE PIPE. 1010-2.01 & 1010-2.02. Please provide Material Certs for the SRP pipe.
2. Concrete Curb and Curb Returns shall be constructed per P.A.G. standard 209.
3. Concrete Curb Access Ramps constructed per P.A.G. standard 207.
4. Concrete Sidewalk on Valencia Rd and Valencia Ramp North, shall be constructed per P.A.G. standard 200 and shall be 6’ wide.
5. Handrail required. Where the concrete sidewalk from the onsite circulation path crosses the drainage area of both entrances/ exits of the property, a handrail per P.A.G. standard Detail 105 is required. Please provide material (mill) certs for the steel used; according to P.A.G. standard specifications- 933-2.01 & Paint per P.A.G. standard specifications- 933-2.03 (and requirements of section 1002.)
6. Please provide an appropriate pavement structural section for entrances according to and appropriate for the ingress/ egress of projected truck traffic. City Mix No. 2 asphalt shall be used- (confirmation with inspection.)
7. Please provide Sight Visibility Triangles on the site plan.


David Stiffey
DTM Project Coordinator
David.Stiffey@tucsonaz.gov
04/25/2023 Site Engineering REQUIRES RESUBMIT Drainage Report:
1. Proposed conditions figure 5 seems to match old Project Oasis plan, and does not match current proposed building configuration. Ensure all calculations are updated to current proposed site configuration
2. Provide basin inlet protection at end of channel.
3. Ensure outlet protection for culvert at Valencia entrance and clarify what type of culvert is being proposed. SRP is shown on the plans while RCP is shown in the calculation sheet. Note DTM doesn't allow anything but concrete culverts in the right-of-way.

Stephen Blood
(520) 837-4958
Stephen.blood@tucsonaz.gov
04/26/2023 Site Landscape REQUIRES RESUBMIT PROJECT: BP PROJECT PUEBLO
ACTIVITY NO. TD-DEV-0323-00170
ADDRESS/PARCEL: 7345 E VALENCIA RD/141-06-020D
ZONING: SR, PAD -26

This plan has been reviewed for compliance with applicable development criteria in the City of Tucson Unified Development Code (UDC) Administrative Manual (AM) Section 2-11 and Technical Manual (TM) Section for landscape, native plants and water harvesting.
COMMENTS:
1. Ensure all Zoning and Engineering comments are addressed prior to the Landscape/NPPO comments.
2. If using d.g at a 2” depth, ensure the rainwater harvesting basins are 8” in depth to account for the d.g.
3. You must have a permit from Department of Transit and Mobility for any planting being done in the right of way. Please reach out to David Marhefka (david.marhefka@tucsonaz.gov) if this is the case.
4. Show all curb cuts/downspouts/splashpads on the landscape and the commercial rainwater harvesting plan.
5. Show roof directional arrows on Commercial Rainwater Harvesting Plan.

Please resubmit revised drawings along with a detailed response letter, which states how all Landscape Review Section comments are addressed.
04/05/2023 Site Zoning REQUIRES RESUBMIT CDRC TRANSMITTAL
TO: Development Services Department
Plans Coordination Office
FROM: Iman Monshizadeh
PDSD Zoning Review Section

PROJECT: Development Package (1st Review)
TD-DEV-0323-00170
TRANSMITTAL DATE: 4/04/2023



COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed.



Section 3.3.3.G.5.c UDC, An applicant has one year from the date of application to obtain approval of a site plan that complies with zoning and other development requirements in effect at the time of application, unless an ordinance adopted by Mayor and Council during this period states otherwise. A site plan application that has been in review for a period of one year and has not yet been approved is considered denied. To continue the review of a site plan for the property, a new site plan must be submitted that complies with regulations in effect at the time of re-submittal. The new submittal initiates a new one-year review period.



SECTION 2-06.0.0: DEVELOPMENT PACKAGE (TENTATIVE PLATS AND SITE PLANS)





2-06.4.3 - The administrative street address and relevant case numbers (development package document, subdivision, rezoning, board of adjustment, DDO, MDR, DSMR, overlay, etc.) shall be provided adjacent to the title block on each sheet.



COMMENT: 2-06.4.3 - Provide the development package case number, TD-DEV-0323-00170, adjacent to the title block on each sheet.





2-06.4.7.A.2 - List the gross area of the site/subdivision by square footage and acreage.



COMMENT: 2-06.4.7.A.2 - Pima County assessor's parcel data shows this site as 32.72 acres or 1,425,314 square feet. This comment is to verify site area. If the site area provided on the plans is verified to be correct and up to date then this comment can be ignored.





2-06.4.9.F - All existing zoning classifications on and adjacent to the project (including across any adjacent right-of-way) shall be indicated on the drawing with zoning boundaries clearly defined. If the property is being rezoned, use those boundaries and classifications. The basis for this requirement is that some zoning requirements on a project are based on the zoning classification of adjacent property. Also, in some instances, each zone has to be taken into consideration on property that is split by two or more zoning classifications, as each may have different requirements.



COMMENT: 2-06.4.9.F - Show the zoning boundaries of the surrounding properties as listed by the standard above





2-06.4.9.O - All applicable building setback lines, such as erosion hazard, floodplain detention/retention basins, and zoning, including sight visibility triangles, will be shown.



COMMENT: 2-06.4.9.O - Provide a setback dimension from the building to the adjacent residential zone to the east. Setback requirements for a industrial use adjacent to a residential use are 1.5 * Height of the structure.





2-06.4.9.R - Show on-site pedestrian circulation and refuge utilizing location and the design criteria in Section 7-01.0.0, Pedestrian Access, of the Technical Standards Manual.



COMMENT: 2-06.4.9.R - Demonstrate pedestrian circulation for the entire site, specifically for how pedestrians can access the building from all parking spaces located on site.



If you have any questions about this transmittal, Contact Iman Monshizadeh at (520) 837-4082 or by email Iman.Monshizadeh@tucsonaz.gov



RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised development package
04/25/2023 Traffic Engineering Review REQUIRES RESUBMIT TP-PRE-1222-00061
7345 E. Valencia Rd.

Comments:
1. A PIA is going to be required for this project. https://www.tucsonaz.gov/tdot/private-improvement-agreement Contact TDOT Engineering for information. DOT-Engineering-Review-Section@tucsonaz.gov Or call. 520-791-5100 Jesus Villezcas
2. Please provide the PIA number for DP approval.

Construction requirements in the Right of Way-

1. SRP Pipe must conform to P.A.G. standard specification, 1010-2 DRAINAGE PIPE. 1010-2.01 & 1010-2.02. Please provide Material Certs for the SRP pipe.
2. Concrete Curb and Curb Returns shall be constructed per P.A.G. standard 209.
3. Concrete Curb Access Ramps constructed per P.A.G. standard 207.
4. Concrete Sidewalk on Valencia Rd and Valencia Ramp North, shall be constructed per P.A.G. standard 200 and shall be 6’ wide.
5. Handrail required. Where the concrete sidewalk from the onsite circulation path crosses the drainage area of both entrances/ exits of the property, a handrail per P.A.G. standard Detail 105 is required. Please provide material (mill) certs for the steel used; according to P.A.G. standard specifications- 933-2.01 & Paint per P.A.G. standard specifications- 933-2.03 (and requirements of section 1002.)
6. Please provide an appropriate pavement structural section for entrances according to and appropriate for the ingress/ egress of projected truck traffic. City Mix No. 2 asphalt shall be used- (confirmation with inspection.)
7. Please provide Sight Visibility Triangles on the site plan.


David Stiffey
DTM Project Coordinator
David.Stiffey@tucsonaz.gov
03/16/2023 CDRC Application Completeness REVIEW COMPLETED
03/30/2023 CDRC Review Coordinator REVIEW COMPLETED
04/27/2023 External Reviewers - COT Parks & Recreation REVIEW COMPLETED <tom.fisher@tucsonaz.gov>
Hello CDRC team,
On behalf of the City of Tucson Parks and Recreation Department, I have no comments on the above development plan.
Tom Fisher
Project Manager
City of Tucson Parks and Recreation Department
900 S. Randolph Way
Tucson, Arizona 85716
(520) 837-8037
03/30/2023 External Reviewers - Pima Association of Governments REVIEW COMPLETED FYI email sent per SOP
04/18/2023 External Reviewers - Pima County Addressing REVIEW COMPLETED Good afternoon,
This project does not require review by Pima County Addressing. The correct address for this project is 7345 E Valencia RD.
Thank you
Nicholas Jordan
Site Review Project Manager - Addressing Official
Pima County Development Services Department
201 N Stone AV – 1st Floor
Tucson, AZ 85701
(520) 724-9623
03/30/2023 External Reviewers - Southwest Gas REVIEW COMPLETED FYI email sent per SOP
03/30/2023 External Reviewers - Tucson Electric Power (TEP) REVIEW COMPLETED Hello,
Attached is our response letter for TD-DEV-0323-00170, BD Project Pueblo.
Thank you,
Conor Mahoney
Design Administrator
OH201
Cell: (520) 404-8437
03/30/2023 External Reviewers - United States Postal Service (USPS) REVIEW COMPLETED FYI email sent per SOP
04/21/2023 Fire New Construction REVIEW COMPLETED
03/20/2023 OK to Submit - Engineering REVIEW COMPLETED
03/16/2023 OK to Submit - Landscape REVIEW COMPLETED
03/27/2023 OK to Submit - Zoning REVIEW COMPLETED