Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Approved
Review Details: COMMERCIAL REVIEW - FULL v.3
Permit Number - TC-COM-1223-02914
Review Name: COMMERCIAL REVIEW - FULL v.3
Review Status: Approved
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
05/16/2024 | Site Zoning | APPROVED | |||
05/30/2024 | Bldg Permits - Post Review | REVIEW COMPLETED | |||
05/30/2024 | External Reviewers - SAFEBuilt | REVIEW COMPLETED | Structural(S) Reviewer Madeline Nelson mnelson@safebuilt.com Approved with Comments Reason: Date Completed : 3/29/2024 12:18:37 AM GENERAL - DEFERRED SUBMITTAL REQUIREMENTS: The engineer of record has indicated that design of the prefabricated wood trusses and steel solar parking covers (carports) will be submitted as a Deferred Submittal. Please note that IBC Section 107.3.4.1 requires deferred submittals to be approved by the building official. The IBC further requires the following procedure be followed when permitting deferred submittals: 1. All submittals shall first be reviewed by design professional in responsible charge. 2. Design professional shall affix a notation that the deferred items are in general conformance with their design of the building. 3. They shall then be submitted for review by the building official. 4. No structural elements shall be installed until approved by building official. Building(B) Reviewer Andrew Bevis abevis@safebuilt.com Approved Reason: Date Completed : 3/25/2024 11:45:43 AM Mechanical(M) Reviewer Jorge Valido jvalido@safebuilt.com Approved Reason: Date Completed : 1/8/2024 11:47:56 AM Electrical(E) Reviewer Ron Ross rross@safebuilt.com Approved Reason: Date Completed : 3/22/2024 10:53:30 AM Plumbing(P) Reviewer Perry Hendershott phendershott@safebuilt.com Approved with Comments Reason: Date Completed : 5/29/2024 9:54:37 PM T Plumbing Review:OK Subject to field inspections RESOLVED-1). All Hose bibs on plan page P101 need shut off valves -IPC 606.2 RESOLVED-2). Roof deck on plan page A102 doesn't illustrate the required secondary scuppers as stated on plan page P102. -IPC 1108 OK Per Building Official Letter Attached)...3). Exterior Drinking fountain on plan page P101 needs to be protected from receiving rainwater into drain. -IPC 1101.3**** DESIGNER Response: = Communication has been initiated with the Tucson Building Official Clayton Trevillyan (clayton.trevillyan@tucsonaz.gov) to accept the minimal amount of rainwater which would enter the sanitary sewer from the water cooler |
||
04/25/2024 | PDSD Application Completeness | REVIEW COMPLETED |