Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Requires Resubmit
Review Details: COMMERCIAL REVIEW - FULL v.2
Permit Number - TC-COM-0523-01382
Review Name: COMMERCIAL REVIEW - FULL v.2
Review Status: Requires Resubmit
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
08/03/2023 | Water - PDSD | APPROVED | |||
08/03/2023 | Bldg Permits - Post Review | PENDING ASSIGNMENT | |||
07/14/2023 | External Reviewers - SAFEBuilt | REQUIRES RESUBMIT | Activity Number: TC-COM-0523-01382 GENERAL: Provide written responses to all review comments. Provide a complete plan set. Provide additional documents as requested by review staff. Structural(S) Reviewer Daljit Benipal dbenipal@safebuilt.com Conditinally Approved Reason: Date Completed : 7/13/2023 6:57:36 PM NOTE: Every effort has been made to identify the code violations. Any oversight by the review team shall not be considered an authority to violate, set aside, cancel or alter applicable codes or ordinances. The plan review and permit issuance shall not be considered a warranty or guarantee. The Structural Engineer is responsible for following ALL applicable Federal, State and local Municipal Codes and Ordinances Building(B) Reviewer Jake Doub jdoub@safebuilt.com Approved Reason: Date Completed : 7/11/2023 8:40:16 AM Mechanical(M) Reviewer Neil Samaan nsamaan@safebuilt.com Conditionally Approved Reason: Date Completed : 5/27/2023 11:46:39 AM Approved/subject to field approval Electrical(E) Reviewer Ron Ross rross@safebuilt.com Approved Reason: Date Completed : 7/7/2023 9:45:46 AM Plumbing(P) Reviewer Perry Hendershott phendershott@safebuilt.com Denied Reason: Date Completed : 7/8/2023 8:23:05 PM Second Plumbing Review: 1). SAME-Plan page A3.0 needs list the gutter & downspout calculations- IPC 1106.1, 1106.3, 1106.6 ** Added calculations missing the 6x6 downspouts & 8x8x gutters** 2). OK 3). OK 4). Now that a backflow has been added to the water line that supplies the air separator on plan page P1.7 the backflow needs to be located so its relief port can be piped to a drain. ( suggest locate above hub drain on same Page) -IPC 608.15.2.1 5). OK 6) OK |
||
07/18/2023 | Site Engineering | REQUIRES RESUBMIT | 1. See Zoning Comment 2. While the plans seem to match, ensure the roof drainage of the building plan matches the final approved development package submittal Scott Haseman scott.haseman@tucsonaz.gov |
||
07/11/2023 | Site Zoning | REQUIRES RESUBMIT | ZONING REVIEW TRANSMITTAL FROM: PDSD Zoning Review PROJECT: TC-COM-0523-01382 7345 E. Valencia Rd. – PAD-26 New Processing and Cleaning Building (2nd Review) TRANSMITTAL: June 06, 2023 Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed. This site is located in PAD-26 Zone (UDC 4.7.24). Processing and Cleaning is an allowed use in the PAD. 1. Zoning has reviewed the building plans for compliance with Development Package (DP) TD-DEV-0323-00170 and it although the plans appear to match until the DP is approved by all review agencies Zoning cannot approve the building plans. If you have any questions about this transmittal, please contact Zone1.desk@tucsonaz.gov. |
||
07/05/2023 | PDSD Application Completeness | REVIEW COMPLETED |