Permit Number: TC-COM-0523-01382
Parcel: 14106020D

Review Status: Requires Resubmit

Review Details: COMMERCIAL REVIEW - FULL v.1

Permit Number - TC-COM-0523-01382
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
06/27/2023 Bldg Permits - Post Review PENDING ASSIGNMENT
06/12/2023 External Reviewers - SAFEBuilt REQUIRES RESUBMIT Activity Number: TC-COM-0523-01382

GENERAL:
Provide written responses to all review comments.
Provide a complete plan set.
Provide additional documents as requested by review staff.

Structural(S) Reviewer
Daljit Benipal
dbenipal@safebuilt.com
Denied
Reason:
Date Completed : 6/11/2023 10:53:24 AM
1. Show lines of bridging for the steel joists per joist manufacturer’s recommendations.
2. The requirements in OSHA 1926.757 for the erection of open web steel joists are to be followed. Where steel joists are used with columns that are not framed in at least two directions with solid web structural steel members, a steel joist shall be field-bolted at the column to provide lateral stability to the column during erection. Where constructability does not allow a steel joist to be installed at the column the joists are to be stabilized on both sides of the column.
3. Except for steel joists that have been pre-assembled into panels, connections of individual steel joists to steel structures in bays 40 feet or more shall be fabricated to allow for field bolting during erection.
4. Provide a vertical stabilizer plate at columns for steel joist as required by OSHA 1926.757.
5. Verify OSHA steel erection standards for open web steel joists. Section 1926.757 (a)(8) requires connections of individual steel joists to steel structures in bays of 40 feet or more shall be fabricated to allow for field bolting during erection.

Submit a response letter addressing these correction items and provide bubbles on the revisions to the drawings.

Building(B) Reviewer
Jake Doub
jdoub@safebuilt.com
Denied
Reason:
Date Completed : 6/10/2023 9:37:45 AM
1. Revise the plans or provide a narrative that better defines the use of the space in the "warehouse" area. It appears that part of this area might fall under an "industrial" use, and would change the occupant load factor. 2018 IBC - Table 1004.5
2. The plans indicate a second story (equipment mezzanine) with an area which exceeds 3000 sqft. and is not provided with an accessible route. Revise the plans to show an accessible route to this area. 2018 IBC - 1104.4(1).
3. The plans do not appear to have a permanent ladder to access the roof. Revise the plans to show the location of a permanent roof access and provide the construction details of the access ladder or stairs. 2018 IBC - 1011.16, 2018 IMC - 306.5.
4. The plans are missing most measurements for accessible components in the bathrooms. Revise the plans to include all mounting heights and required floor spaces. 2009 ANSI A117.1.
5. The plans do not indicate a vertical grab bar has been provided. Revise the plans to include the required grab bar. 2009 ANSI A117.1 - 609.4.


Mechanical(M) Reviewer
Neil Samaan
nsamaan@safebuilt.com
Conditionally Approved
Reason:
Date Completed : 5/27/2023 11:46:39 AM
Approved/subject to field approval


Electrical(E) Reviewer
Ron Ross
rross@safebuilt.com
Denied
Reason:
Date Completed : 6/9/2023 9:49:11 AM
Electrical Review for Project Pueblo
By: Ron Ross PE
E0.3 ELECTRICAL SCHEDULES: Should provide description for LBC-1 thru 4.
E3.0 ELECTRICAL ONE LINE DIAGRAM: Tucson requires short circuit calculations to every new panel starting from the Utility provided transformer (local power company provides short circuit available fault current on secondary side of transformer). EOR may need to estimate transformer size to be provided by Utility and then use Utility table provided on Utility’s website for estimated short circuit current)
E4.0 PANEL SCHEDULES:
Need to show Panels H-FP and LV-FP or explain why they are not shown. It is understood that Guard shack cannot be shown.
Suggestion for future submittals: Should change VA columns in panel schedules to KVA as VA is a small unit that results in trailing numbers to be cut off. Cannot determine actual values used as trailing numbers may be ONE or TWO or more numbers ie cannot directly determine magnitude of values.
E4.1 PANEL SCHEDULES: Comment only: NZ units call out for an MOP of 50 Amps, but you provide 60-amp circuit breakers for NZ-1, NZ-2, and NZ-4.


Plumbing(P) Reviewer
Perry Hendershott
phendershott@safebuilt.com
Denied
Reason:
Date Completed : 6/10/2023 12:41:58 PM
First Plumbing Review:
1). Plan page A3.0 needs list the gutter & downspout calculations- IPC 1106.1, 1106.3, 1106.6
2). Trap Primer Detail #9 on plan page P2.1 needs a shut off valve. -IPC 606.2
3). Lavatories on plan page P0.2 need ASSE 1070 mixing valves with max temp of 110 Deg. the mixing valve currently shown on P0.2 is 115 Deg. -IPC 419.5, 607.1.2
4). Add Backflow device type, manufacturer name & model number to plan P1.7 for air separator water connection. -IPC 608.3, Table 608.1
5). Add trap guard device info to FS1 on plan page P0.2 as stated on plan P1.6 - IPC 1002.4.1
6). FD3 on plan page P0.2 needs a trap seal device -IPC 1002.4.1
06/13/2023 Site Engineering REQUIRES RESUBMIT See zoning comment
06/06/2023 Site Zoning REQUIRES RESUBMIT ZONING REVIEW TRANSMITTAL

FROM: PDSD Zoning Review

PROJECT:
TC-COM-0523-01382
7345 E. Valencia Rd. – PAD-26
New Processing and Cleaning Building(1st Review)

TRANSMITTAL: June 06, 2023

Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed.

This site is located in PAD-26 Zone (UDC 4.7.24). Processing and Cleaning is an allowed use in the PAD.

1. As the first review of Development Package (DP) TD-DEV-0323-00170 has not been completed Zoning cannot review the building plans at this time and will review on the next submittal.

If you have any questions about this transmittal, please contact Zone1.desk@tucsonaz.gov.
06/27/2023 Water - PDSD REQUIRES RESUBMIT Show the location of the proposed water meter, backflow preventer, and the water service pipe on a site plan. Provide the size of the water meter serving this building, the size of the backflow preventer associated with the water meter, and the total water demand served by the water meter. Reference: Section 107.2.1 and 107.2.6, IBC 2018.
06/13/2023 Fire New Construction REVIEW COMPLETED
05/26/2023 PDSD Application Completeness REVIEW COMPLETED