| 04/04/2025 | Bldg Permits - Post Review Express | PENDING ASSIGNMENT | |||
| 04/04/2025 | Commercial Building Standard | REQUIRES RESUBMIT | April 4, 2025 2nd Review Light+Path Architects LLC. Attn: Brian G. Hagedon 475 S. Gollob Road Tucson, Arizona 85710 Re: TEEN CHALLENGE BUILDING 2 – STAFF LIVING CORE, SHELL, & FITOUT City of Tucson Permit Number: TC-COM-0225-00339 Stantec Project Number: 185215066 Stantec File Number: TUC-25-026 Plan review for the above referenced project has been completed. This letter reflects comments to be addressed. PLEASE send all response to comments back to the City through the permit portal! Responses sent directly to Stantec will be ignored. Also, please submit complete copies of all permit documents (i.e. plans, calculations, reports, etc.) even if they have not been changed. Please cloud and delta all changes and provide a letter with a written response to each of the comments indicating the action taken. The scope of this review covers the architectural, plumbing, mechanical, and electrical designs as they relate to the codes adopted by the jurisdiction. All features were checked only to the extent allowed by the submittals provided. All portions of this project are assumed to meet or will meet other departmental requirements, conditions, and concerns before permit approval. Occupancy Group Construction Type Area (Square feet) Occupant Load Automatic Fire Sprinklers Fire Alarms R-2 V-B 16,332 78 Yes Yes Separate Permits: Automatic fire sprinklers and fire alarm. Deferred Submittals: None. Special Inspections: Water resistive barrier coating. ARCHITECTURAL COMMENTS General 1. Addressed. 2. Previous Comment: Note on the cover of the drawings that special inspection is required for water-resistive barrier coating [Ref. IBC 2018 Sec. 1705.16.1]. Also, provide City of Tucson special inspection certificate(s) with Parts A and B completed. Make sure that the owner or their legal representative signs the form. Still Required: The special inspection certificate provided indicates Syndey Palmer as the water-resistive barrier coating special inspector. Sydney Palmer is not included in the Town of Oro Valley approved special inspectors lists that is recognized by the City of Tucson. Please provide someone included on this list. {Terracon does have special inspectors certified in EIFS special inspection that would be acceptable for this special inspection.} 3. Addressed. Sheet GA111 1. Addressed. Sheet A111 1. Addressed. 2. Addressed. 3. Addressed. Sheet A112 1. Addressed. 2. Addressed. STRUCTURAL COMMENTS There are no comments. MECHANICAL COMMENTS Sheet M101 1. Addressed. PLUMBING COMMENTS General 1. Addressed. 2. Addressed. Sheet 202 1. Addressed. ELECTRICAL COMMENTS Sheet E511 1. Addressed. Should you have any questions regarding the plan review comments, please contact the plan reviewer listed for the appropriate discipline. Plans reviewed by: Trevor Bies, Senior Plan Reviewer 602-338-9922 trevor.bies@stantec.com |
||
| 04/04/2025 | Commercial Electrical Standard | REQUIRES RESUBMIT | April 4, 2025 2nd Review Light+Path Architects LLC. Attn: Brian G. Hagedon 475 S. Gollob Road Tucson, Arizona 85710 Re: TEEN CHALLENGE BUILDING 2 – STAFF LIVING CORE, SHELL, & FITOUT City of Tucson Permit Number: TC-COM-0225-00339 Stantec Project Number: 185215066 Stantec File Number: TUC-25-026 Plan review for the above referenced project has been completed. This letter reflects comments to be addressed. PLEASE send all response to comments back to the City through the permit portal! Responses sent directly to Stantec will be ignored. Also, please submit complete copies of all permit documents (i.e. plans, calculations, reports, etc.) even if they have not been changed. Please cloud and delta all changes and provide a letter with a written response to each of the comments indicating the action taken. The scope of this review covers the architectural, plumbing, mechanical, and electrical designs as they relate to the codes adopted by the jurisdiction. All features were checked only to the extent allowed by the submittals provided. All portions of this project are assumed to meet or will meet other departmental requirements, conditions, and concerns before permit approval. Occupancy Group Construction Type Area (Square feet) Occupant Load Automatic Fire Sprinklers Fire Alarms R-2 V-B 16,332 78 Yes Yes Separate Permits: Automatic fire sprinklers and fire alarm. Deferred Submittals: None. Special Inspections: Water resistive barrier coating. ARCHITECTURAL COMMENTS General 1. Addressed. 2. Previous Comment: Note on the cover of the drawings that special inspection is required for water-resistive barrier coating [Ref. IBC 2018 Sec. 1705.16.1]. Also, provide City of Tucson special inspection certificate(s) with Parts A and B completed. Make sure that the owner or their legal representative signs the form. Still Required: The special inspection certificate provided indicates Syndey Palmer as the water-resistive barrier coating special inspector. Sydney Palmer is not included in the Town of Oro Valley approved special inspectors lists that is recognized by the City of Tucson. Please provide someone included on this list. {Terracon does have special inspectors certified in EIFS special inspection that would be acceptable for this special inspection.} 3. Addressed. Sheet GA111 1. Addressed. Sheet A111 1. Addressed. 2. Addressed. 3. Addressed. Sheet A112 1. Addressed. 2. Addressed. STRUCTURAL COMMENTS There are no comments. MECHANICAL COMMENTS Sheet M101 1. Addressed. PLUMBING COMMENTS General 1. Addressed. 2. Addressed. Sheet 202 1. Addressed. ELECTRICAL COMMENTS Sheet E511 1. Addressed. Should you have any questions regarding the plan review comments, please contact the plan reviewer listed for the appropriate discipline. Plans reviewed by: Trevor Bies, Senior Plan Reviewer 602-338-9922 trevor.bies@stantec.com |
||
| 04/04/2025 | Commercial Mechanical Standard | REQUIRES RESUBMIT | April 4, 2025 2nd Review Light+Path Architects LLC. Attn: Brian G. Hagedon 475 S. Gollob Road Tucson, Arizona 85710 Re: TEEN CHALLENGE BUILDING 2 – STAFF LIVING CORE, SHELL, & FITOUT City of Tucson Permit Number: TC-COM-0225-00339 Stantec Project Number: 185215066 Stantec File Number: TUC-25-026 Plan review for the above referenced project has been completed. This letter reflects comments to be addressed. PLEASE send all response to comments back to the City through the permit portal! Responses sent directly to Stantec will be ignored. Also, please submit complete copies of all permit documents (i.e. plans, calculations, reports, etc.) even if they have not been changed. Please cloud and delta all changes and provide a letter with a written response to each of the comments indicating the action taken. The scope of this review covers the architectural, plumbing, mechanical, and electrical designs as they relate to the codes adopted by the jurisdiction. All features were checked only to the extent allowed by the submittals provided. All portions of this project are assumed to meet or will meet other departmental requirements, conditions, and concerns before permit approval. Occupancy Group Construction Type Area (Square feet) Occupant Load Automatic Fire Sprinklers Fire Alarms R-2 V-B 16,332 78 Yes Yes Separate Permits: Automatic fire sprinklers and fire alarm. Deferred Submittals: None. Special Inspections: Water resistive barrier coating. ARCHITECTURAL COMMENTS General 1. Addressed. 2. Previous Comment: Note on the cover of the drawings that special inspection is required for water-resistive barrier coating [Ref. IBC 2018 Sec. 1705.16.1]. Also, provide City of Tucson special inspection certificate(s) with Parts A and B completed. Make sure that the owner or their legal representative signs the form. Still Required: The special inspection certificate provided indicates Syndey Palmer as the water-resistive barrier coating special inspector. Sydney Palmer is not included in the Town of Oro Valley approved special inspectors lists that is recognized by the City of Tucson. Please provide someone included on this list. {Terracon does have special inspectors certified in EIFS special inspection that would be acceptable for this special inspection.} 3. Addressed. Sheet GA111 1. Addressed. Sheet A111 1. Addressed. 2. Addressed. 3. Addressed. Sheet A112 1. Addressed. 2. Addressed. STRUCTURAL COMMENTS There are no comments. MECHANICAL COMMENTS Sheet M101 1. Addressed. PLUMBING COMMENTS General 1. Addressed. 2. Addressed. Sheet 202 1. Addressed. ELECTRICAL COMMENTS Sheet E511 1. Addressed. Should you have any questions regarding the plan review comments, please contact the plan reviewer listed for the appropriate discipline. Plans reviewed by: Trevor Bies, Senior Plan Reviewer 602-338-9922 trevor.bies@stantec.com |
||
| 04/04/2025 | Commercial Plumbing Standard | REQUIRES RESUBMIT | April 4, 2025 2nd Review Light+Path Architects LLC. Attn: Brian G. Hagedon 475 S. Gollob Road Tucson, Arizona 85710 Re: TEEN CHALLENGE BUILDING 2 – STAFF LIVING CORE, SHELL, & FITOUT City of Tucson Permit Number: TC-COM-0225-00339 Stantec Project Number: 185215066 Stantec File Number: TUC-25-026 Plan review for the above referenced project has been completed. This letter reflects comments to be addressed. PLEASE send all response to comments back to the City through the permit portal! Responses sent directly to Stantec will be ignored. Also, please submit complete copies of all permit documents (i.e. plans, calculations, reports, etc.) even if they have not been changed. Please cloud and delta all changes and provide a letter with a written response to each of the comments indicating the action taken. The scope of this review covers the architectural, plumbing, mechanical, and electrical designs as they relate to the codes adopted by the jurisdiction. All features were checked only to the extent allowed by the submittals provided. All portions of this project are assumed to meet or will meet other departmental requirements, conditions, and concerns before permit approval. Occupancy Group Construction Type Area (Square feet) Occupant Load Automatic Fire Sprinklers Fire Alarms R-2 V-B 16,332 78 Yes Yes Separate Permits: Automatic fire sprinklers and fire alarm. Deferred Submittals: None. Special Inspections: Water resistive barrier coating. ARCHITECTURAL COMMENTS General 1. Addressed. 2. Previous Comment: Note on the cover of the drawings that special inspection is required for water-resistive barrier coating [Ref. IBC 2018 Sec. 1705.16.1]. Also, provide City of Tucson special inspection certificate(s) with Parts A and B completed. Make sure that the owner or their legal representative signs the form. Still Required: The special inspection certificate provided indicates Syndey Palmer as the water-resistive barrier coating special inspector. Sydney Palmer is not included in the Town of Oro Valley approved special inspectors lists that is recognized by the City of Tucson. Please provide someone included on this list. {Terracon does have special inspectors certified in EIFS special inspection that would be acceptable for this special inspection.} 3. Addressed. Sheet GA111 1. Addressed. Sheet A111 1. Addressed. 2. Addressed. 3. Addressed. Sheet A112 1. Addressed. 2. Addressed. STRUCTURAL COMMENTS There are no comments. MECHANICAL COMMENTS Sheet M101 1. Addressed. PLUMBING COMMENTS General 1. Addressed. 2. Addressed. Sheet 202 1. Addressed. ELECTRICAL COMMENTS Sheet E511 1. Addressed. Should you have any questions regarding the plan review comments, please contact the plan reviewer listed for the appropriate discipline. Plans reviewed by: Trevor Bies, Senior Plan Reviewer 602-338-9922 trevor.bies@stantec.com |
||
| 04/04/2025 | Outdoor Lighting Standard | REQUIRES RESUBMIT | April 4, 2025 2nd Review Light+Path Architects LLC. Attn: Brian G. Hagedon 475 S. Gollob Road Tucson, Arizona 85710 Re: TEEN CHALLENGE BUILDING 2 – STAFF LIVING CORE, SHELL, & FITOUT City of Tucson Permit Number: TC-COM-0225-00339 Stantec Project Number: 185215066 Stantec File Number: TUC-25-026 Plan review for the above referenced project has been completed. This letter reflects comments to be addressed. PLEASE send all response to comments back to the City through the permit portal! Responses sent directly to Stantec will be ignored. Also, please submit complete copies of all permit documents (i.e. plans, calculations, reports, etc.) even if they have not been changed. Please cloud and delta all changes and provide a letter with a written response to each of the comments indicating the action taken. The scope of this review covers the architectural, plumbing, mechanical, and electrical designs as they relate to the codes adopted by the jurisdiction. All features were checked only to the extent allowed by the submittals provided. All portions of this project are assumed to meet or will meet other departmental requirements, conditions, and concerns before permit approval. Occupancy Group Construction Type Area (Square feet) Occupant Load Automatic Fire Sprinklers Fire Alarms R-2 V-B 16,332 78 Yes Yes Separate Permits: Automatic fire sprinklers and fire alarm. Deferred Submittals: None. Special Inspections: Water resistive barrier coating. ARCHITECTURAL COMMENTS General 1. Addressed. 2. Previous Comment: Note on the cover of the drawings that special inspection is required for water-resistive barrier coating [Ref. IBC 2018 Sec. 1705.16.1]. Also, provide City of Tucson special inspection certificate(s) with Parts A and B completed. Make sure that the owner or their legal representative signs the form. Still Required: The special inspection certificate provided indicates Syndey Palmer as the water-resistive barrier coating special inspector. Sydney Palmer is not included in the Town of Oro Valley approved special inspectors lists that is recognized by the City of Tucson. Please provide someone included on this list. {Terracon does have special inspectors certified in EIFS special inspection that would be acceptable for this special inspection.} 3. Addressed. Sheet GA111 1. Addressed. Sheet A111 1. Addressed. 2. Addressed. 3. Addressed. Sheet A112 1. Addressed. 2. Addressed. STRUCTURAL COMMENTS There are no comments. MECHANICAL COMMENTS Sheet M101 1. Addressed. PLUMBING COMMENTS General 1. Addressed. 2. Addressed. Sheet 202 1. Addressed. ELECTRICAL COMMENTS Sheet E511 1. Addressed. Should you have any questions regarding the plan review comments, please contact the plan reviewer listed for the appropriate discipline. Plans reviewed by: Trevor Bies, Senior Plan Reviewer 602-338-9922 trevor.bies@stantec.com |
||