Permit Review Detail
Review Status: Requires Resubmit
Review Details: COMMERCIAL REVIEW - FULL v.1
Permit Number - T22CM02647
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 01/03/2023 | Commercial Plumbing | APPROVED | |||
| 11/23/2022 | Fire New Construction | APPROVED | |||
| 11/23/2022 | Site Engineering | APPROVED | |||
| 11/23/2022 | Site Zoning | APPROVED | |||
| 01/03/2023 | Bldg Permits - Post Review Express | PENDING ASSIGNMENT | |||
| 12/23/2022 | External Reviewers - SAFEBuilt | REQUIRES RESUBMIT | Activity Number: T22CM02647 GENERAL: Provide written responses to all review comments. Provide a complete plan set. Provide additional documents as requested by review staff. STRUCTURAL REVIEW COMMENTS: CONDITIONALLY APPROVED NOTE: Every effort has been made to identify the code violations. Any oversight by the review team shall not be considered an authority to violate, set aside, cancel or alter applicable codes or ordinances. The plan review and permit issuance shall not be considered a warranty or guarantee. The Structural Engineer is responsible for following ALL applicable Federal, State and local Municipal Codes and Ordinances. BUILDING REVIEW COMMENTS: DENIED 1. The occupant load provided is incorrect. Occupant loads are calculated by a space by space basis in accordance with Section 1004.3 and Table 1004.5. Provide a properly calculated occupant load. NOT COMPLIED. Note: THE OCCUPANT LOAD CALCULATION PROVIDED IS NOT CORRECT. 1. Previous comment: Provide required plumbing fixture calculations. Response: The schedule provided is not a plumbing fixture calculation. Provide a plumbing fixture calculation that shows the minimum number of plumbing fixtures required. NOT COMPLIED. NOTE: PROVIDE PLUBMING FIXUTRE CALCULATIONS IN ACCORDANCE WITH THE IPC THAT CORRELATE WITH AN UPDATED OCCUPANT LOAD. 1. Previous comment: The water fountain does not meet the accessibility requirements of Section 1109.5.1. Provide all detailed drawings for the water fountain. NOT COMPLIED. Response: The water fountain detail provided DOES NOT meet the accessibility requirements of Section 1109.5.1. MECHANICAL REVIEW COMMENTS: CONDITIONALLY APPROVED 3. Provide an approved ventilation calculation table. (i.g. the total area for this building is 6,080 square feet, the total area your providing in your table is 5,300 square feet, your missing 780 square feet, also your lumping all the rooms as offices, when you got different rooms that must be calculated as different occupancies with different CFM requirements than an office. for example a dining room, Zuma room, sleeping room requires different outside air than an office and they must be listed accordingly sheet M4 (IMC2018,106.3.1) Complied 4. Public restrooms require 70 cfm of exhaust air you got 60 cfm and you don't specify if it is continuous or intermittent exhaust sheet M4 (IMC2018,403.3.1.1) on your ventilation calcs's you got 3 restroom's with a total combined cfm capacity of 150 cfm, with no note that says continuous ventilation, and then you got a exhaust air fan schedule, that says exhaust fan 85 cfm 1. it contradicts the numbers in your ventilation calc's and 2. it say's it is interlocked with the air handler but it doesn't say it is continuous like you imply in your written response. you must submit a revised plan that matches your written response on sheet M4 Complied Approved/subject to field approval ELECTRICAL REVIEW COMMENTS APPROVED PLUMBING REVIEW COMMENTS: DENIED Third Plumbing Review: 1). OK 2). Revised scupper calcs on plan page A5 are calculated with 1.5" of rainfall, Tucson is 3" per hour -see Tucson plumbing code amendments. B- scupper detail #1 on plan page A3 still; shows different scupper sizes than show on A3 elevations & A5 roof plan?. -IPC 106.3.1 , 1106.1 3 thru 10 OK If you require additional clarification regarding these comments, please contact Doris Benoit at doris.benoit@tucsonaz.gov |
||
| 11/23/2022 | PDSD Application Completeness Express | REVIEW COMPLETED |