Plan: TW-PLAN-0326-0003
Plan Details
Apply Date:
09/01/2024
Applicant:
Carrie
Description:
This plan will modify the F-009 well site to deliver water from the F-009B well and F2 water service area(WSA) to the G2 WSA. Modifications include: equipping the F-009B well, changing the booster station pumps, installing new chlorination equipment, modifying the site control panel, and adding site piping and an MOV flow control valve to connect to the F2 WSA. Additional work includes rehabilitation of the reservoir and above-ground piping.
Architects:
- CEC
- Civil & Environmental Consultants, Inc
- Jacobs
Contractors:
Plan Reviews
Plan Number - TW-PLAN-0326-0003
Plan Status: In Review
Plan Description: This plan will modify the F-009 well site to deliver water from the F-009B well and F2 water service area(WSA) to the G2 WSA. Modifications include: equipping the F-009B well, changing the booster station pumps, installing new chlorination equipment, modifying the site control panel, and adding site piping and an MOV flow control valve to connect to the F2 WSA. Additional work includes rehabilitation of the reservoir and above-ground piping.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/25/2026 | TWPE 90% Design Review v.1 | IN REVIEW |