Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Plan Details

Status:
Accepted
Type:
Capital Improvement Project
Apply Date:
08/28/2024
Applicant:
Tucson Water
Description:
DP for CIP-0824-00030. PRJ000609 Houghton F-G Booster Station Rehab. Demolition of existing booster station and site perimeter fence to build new booster station, add control buildings and secure site with new CMU screening wall. Development cannot meet all scenic route requirements, City Manager's Office Waiver is provided.
Architects:
  • EMA Inc.
  • HERMAN CONTRACTING
  • Tucson Water
Contractors:

Outstanding Plan Activity Conditions

Plan Number - CIP-0824-00030
Plan Description: DP for CIP-0824-00030. PRJ000609 Houghton F-G Booster Station Rehab. Demolition of existing booster station and site perimeter fence to build new booster station, add control buildings and secure site with new CMU screening wall. Development cannot meet all scenic route requirements, City Manager's Office Waiver is provided.
Date Name Approved Comments
09/11/2024 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. Not Approved Sheet S3/S8
09/11/2024 SPECIAL INSPECTION FOR REINFORCING STEEL IS REQUIRED. Not Approved Sheet S3/S8
09/11/2024 SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. Not Approved Sheet S3/S8

Plan Reviews

Plan Number - CIP-0824-00030
Plan Status: Accepted
Plan Description: DP for CIP-0824-00030. PRJ000609 Houghton F-G Booster Station Rehab. Demolition of existing booster station and site perimeter fence to build new booster station, add control buildings and secure site with new CMU screening wall. Development cannot meet all scenic route requirements, City Manager's Office Waiver is provided.
Start Date Submittal Complete Date Status  
04/16/2026 CIP - Development Site - Final v.2 APPROVED Review Details
11/14/2025 CIP - Dev Site + Comm Structure - Final v.1 REQUIRES RESUBMIT Review Details
02/20/2026 CIP - Development Site - Final v.1 REQUIRES RESUBMIT Review Details
08/30/2024 CIP - Dev Site + Comm Structure - Initial v.1 REQUIRES RESUBMIT Review Details