Permit: TW-CONS-0326-0033
Permit Details
Status:
Inspections
Type:
TW CIP Planning & Engineering
Address:
1000 S DEL VALLE AV
Address NEW:
1000 S DEL VALLE AV
Apply Date:
03/31/2026
Applicant:
Al heimpel
Description:
PHASE 2 San Fernando
Outstanding Inspections
Permit Status: Inspections
Permit Number: TW-CONS-0326-0033
Permite Description: PHASE 2 San Fernando
Total Outstanding Inspections - 4
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/26/2026 | Field Change review for As-Built and Revision determinations | N/A | Canceled | |
| 10/26/2026 | Used to track and report system pressure testing and associated water loss. | N/A | In Field Accepted | pressure tested 4500 feet of multiple different types of pipe 8 inch PVC 6 inch PVC 8 inch ductile iron pipe 1 inch copper services and 2 inch copper services. |
| 10/02/2026 | TWPE Daily Field Inspection | N/A | In Field Accepted | Borderland installed 3 services of 1” copper approximately 25’ each service tracer wire was installed bedded and shaded and blue caution tape was installed. |
| 10/02/2026 | TWPE Summary review of Daily Field Inspections | N/A | In Field Accepted | Contractor did not work due to rain from Monday September 28 to September 30. Contractor installed another services Thursday and Friday about 5 services and a lateral of 60’ of 6’ PVC and 2 45 all fittings were wrapped and tracer wire installed bedded and shaded and blue caution tape installed. |
Scheduled Inspections
Scheduled Inspections - TW-CONS-0326-0033
Status: Inspections
Description: PHASE 2 San Fernando
| Scheduled Date | Description | Entered By | Entered Date |
|---|---|---|---|
| 11/21/2026 | TWPE Daily Field Inspection | Scheduled | |
| 11/21/2026 | TWPE Summary review of Daily Field Inspections | Scheduled |
For information about today’s scheduled inspections please refer to the
PDSD Daily Inspections Dashboards (Desktop)
PDSD Daily Inspections Dashboards (Mobile)
.