| 06/11/2026 |
TWPE Daily Field Inspection |
|
In Field Accepted |
Pre-con conducted today. |
| 06/12/2026 |
TWPE Daily Field Inspection |
|
In Field Accepted |
No water work. |
| 06/17/2026 |
TWPE Daily Field Inspection |
|
In Field Accepted |
No water work. |
| 07/06/2026 |
TWPE Daily Field Inspection |
|
In Field Accepted |
Arrived on-site Borderland construction installed 200’ of 8” PVC with a 6”x8” tee with a 6” gate valve all restraints are wrapped tracer wire installed and glue cation tape installed. |
| 07/07/2026 |
TWPE Daily Field Inspection |
|
In Field Accepted |
Arrived on site borderland construction installed 100 feet of C900 8” PVC pipe with an 8“ x 6“ tee with a 6” valve and also installed 17 feet of 8 inch DIP all pipe joints valves and tee were wrapped tracer wire was installed. All pipe was bedded and shaded and blue caution tape installed. |
| 07/08/2026 |
TWPE Daily Field Inspection |
|
In Field Accepted |
Arrived on-site borderland construction installed an 8” x 6” cross with two 6” gate valves and one 8” gate valve, borderland also installed 120’ of 8” C900 PVC, all fittings and restraints were fully wrapped tracer wire was installed pipe was bedded and shaded and trench was backfield blue caution tape installed. |
| 07/09/2026 |
TWPE Daily Field Inspection |
|
In Field Accepted |
Arrived on-site Borderland installed 4’ of 8” C900 PVC pipe with a vertical 45 coupling and a horizontal 45 coupling for a dip section, borderland also installed 80’ of 8” DI pipe, all pipe and couplings were wrapped tracer wire was installed and all pipe and couplings were bedded and shaded and blue caution tape installed. |
| 07/10/2026 |
TWPE Daily Field Inspection |
|
In Field Accepted |
Arrived on-site borderland installed 20’ of 8” DI pipe and installed 100’ of 8” C900 PVC, all restraints and couplings were wrapped tracer wire was installed all pipe was bedded and shaded and blue cation tape installed. |
| 07/20/2026 |
TWPE Daily Field Inspection |
|
In Field Accepted |
Arrived on-site Borderland Construction installed 120’ of 8” PVC all restraints were wrapped tracer wire was installed and all pipe was needed and shaded blue caution tape was installed. |
| 07/29/2026 |
TWPE Daily Field Inspection |
|
In Field Accepted |
On July 28, 2026 borderland construction installed 56 feet of pipe that is including 22 1/2 couplings and 20 feet of ductal, iron pipe and 36 of 8 inch PVC. On July 29th 2026 borderland construction installed 96 feet of 8 inch PVC with a 8 x 6 with one 6 inch valve and an 8 inch valve all pipe restraints and couplings were wrapped tracer wire was installed bedded and shaded completely and blue caution tape installed. |
| 08/07/2026 |
TWPE Daily Field Inspection |
|
In Field Accepted |
No water work will be done today |
| 08/10/2026 |
TWPE Daily Field Inspection |
|
In Field Accepted |
Arrived on-site Borderland installed 100’ of 8” PVC with two 8”x6” tee with two 6” gate valves and two 8” gate valves, all restraints and tees were wrapped all pipe was bedded and shaded tracer wire and blue caution tape were installed. |
| 08/12/2026 |
TWPE Daily Field Inspection |
|
In Field Accepted |
On August 11, 2026, Borderland Construction installed 100’ of C900 8” PVC and on August 12, 2026 Borderland Construction installed 20’ of DI pipe and four 45 coupling and 17’ of C900 8” PVC all restraints couplings were wrapped and pipe and components were bedded and shaded tracer wire and blue caution was installed. |
| 08/13/2026 |
TWPE Daily Field Inspection |
|
In Field Accepted |
No water work, rain day. |
| 08/18/2026 |
TWPE Daily Field Inspection |
|
In Field Accepted |
Arrived on-site Borderland Construction installed 104’ of 8” C900 PVC with two 8”x6” tees with 2 8” valves and 2 6” valves all restraints and tees and valves were wrapped tracer wire and blue caution tape was installed. |
| 08/19/2026 |
TWPE Daily Field Inspection |
|
In Field Accepted |
Arrived on-site Borderland installed 80” of C900 PVC, all restraints were wrapped tracer wire and blue caution tape were installed. |
| 08/20/2026 |
TWPE Daily Field Inspection |
|
In Field Accepted |
Arrived on-site Borderland installed 25’ of 8” C900, all restraints were wrapped, tracer wire and blue caution tape were installed. |
| 08/21/2026 |
TWPE Daily Field Inspection |
|
In Field Accepted |
No water work, contractor was potholing under utilities for a dip section. |
| 08/28/2026 |
TWPE Daily Field Inspection |
|
In Field Accepted |
Boderland construction installed 77’ of 8” PVC, all couplings and restraints were wrapped and tracer wire and blue caution tape were installed. |
| 08/31/2026 |
TWPE Daily Field Inspection |
|
In Field Accepted |
No water work, rain day. |
| 10/02/2026 |
TWPE Daily Field Inspection |
|
In Field Accepted |
Borderland installed 3 services of 1” copper approximately 25’ each service tracer wire was installed bedded and shaded and blue caution tape was installed. |
| 10/26/2026 |
TWPE Daily Field Inspection |
|
In Field Accepted |
performed pressure test on all pipe for phase 2 pressure was set at 200 psi pressure test complete today and passed took a sample of high chlorination and tested 80+ PPM. |
| 10/28/2026 |
TWPE Daily Field Inspection |
|
In Field Accepted |
no water work |
|
TWPE Daily Field Inspection |
|
Scheduled |
|