Permit: TW-CONS-0326-0033

Parcel: 128061430


Addresses:

1000 S DEL VALLE AV

Inspection Status: In Field Accepted

Inspection History: TWPE Summary review of Daily Field Inspections

Date Description Inspector Results Comments
06/12/2026 TWPE Summary review of Daily Field Inspections In Field Accepted No water work.
07/06/2026 TWPE Summary review of Daily Field Inspections In Field Accepted
07/20/2026 TWPE Summary review of Daily Field Inspections In Field Accepted
07/29/2026 TWPE Summary review of Daily Field Inspections In Field Accepted
08/10/2026 TWPE Summary review of Daily Field Inspections In Field Accepted Borderland installed 336’ of 8” PVC between Monday August 03, 2026 and Thursday August 06, 2026 and 30’ of 8” DI with 45 couplings for a dip section, 8”x6” tees and 8” gate valves and 6” gate valves all pipe and restraints were wrapped all installed pipe couplings and tees were bedded and shaded tracer and blue caution tape were installed.
08/18/2026 TWPE Summary review of Daily Field Inspections In Field Accepted Arrived on-site Borderland Construction installed 104’ of 8” C900 PVC with two 8”x6” tees with 2 8” valves and 2 6” valves all restraints and tees and valves were wrapped tracer wire and blue caution tape was installed.
08/28/2026 TWPE Summary review of Daily Field Inspections In Field Accepted Borderland construction installed a dip section with a vertical 45 with 6’ of 8” PVC and then another vertical 45, then proceeded to installed a 20’ of 8” DI pipe then installed another vertical 45 to come out of the dip section with a 7’ of 8” PVC pipe and then installed 12’ of 8” PVC pipe and then installed 120’ of 8” PVC and two 22 couplings. all couplings and DI pipe and restraints were wrapped and tracer wire and blue caution were installed.
10/02/2026 TWPE Summary review of Daily Field Inspections In Field Accepted Contractor did not work due to rain from Monday September 28 to September 30.

Contractor installed another services Thursday and Friday about 5 services and a lateral of 60’ of 6’ PVC and 2 45 all fittings were wrapped and tracer wire installed bedded and shaded and blue caution tape installed.
10/26/2026 TWPE Summary review of Daily Field Inspections In Field Accepted no water work project has not begun
TWPE Summary review of Daily Field Inspections Scheduled