Permit: TR-UTL-0726-01117
Permit Details
Status:
Inspections
Type:
Right-of-Way (ROW) - Utility
Address:
3517 N KELLEN CANYON CT
Address NEW:
3517 N KELLEN CANYON CT
Apply Date:
07/07/2026
Applicant:
Garcia David
Description:
MMR Fiber-- SEGMENT 3 (Plan Phase 3) - THIS JOB PLACES 5100' OF (2)2" AND (4)7-WAY HDPE CONDUITS ALONG N SILVERBELL RD. METHOD OF CONSTRUCTION TO BE DIRECTIONAL BORING AND/OR DIGGING/TRENCHING DEPENDING ON AREA AND ENGINEERING DRAWINGS. POSSIBLE PITS AND PLACING HANDHOLES. FIBER CABLE TO BE PLACED IN CONDUIT LOOPING INTO HANDHOLE. (DTM Note-- Refer to Attachments for Related Permit from Contractor)
Permit Reviews
Permit Number - TR-UTL-0726-01117
Permit Status: Inspections
Permit Description: MMR Fiber-- SEGMENT 3 (Plan Phase 3) - THIS JOB PLACES 5100' OF (2)2" AND (4)7-WAY HDPE CONDUITS ALONG N SILVERBELL RD. METHOD OF CONSTRUCTION TO BE DIRECTIONAL BORING AND/OR DIGGING/TRENCHING DEPENDING ON AREA AND ENGINEERING DRAWINGS. POSSIBLE PITS AND PLACING HANDHOLES. FIBER CABLE TO BE PLACED IN CONDUIT LOOPING INTO HANDHOLE. (DTM Note-- Refer to Attachments for Related Permit from Contractor)
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/17/2026 | RIGHT-OF-WAY REVIEW v.1 | 07/20/2026 | REQUIRES RESUBMIT |
| 07/08/2026 | RIGHT-OF-WAY REVIEW v.1 | N/A | REQUIRES RESUBMIT |
| 10/25/2026 | RIGHT-OF-WAY REVIEW v.4 | 11/05/2026 | APPROVED |
| 09/25/2026 | RIGHT-OF-WAY REVIEW v.3 | 10/21/2026 | REQUIRES RESUBMIT |
| 07/28/2026 | RIGHT-OF-WAY REVIEW v.2 | 09/18/2026 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TR-UTL-0726-01117
Permit Status: Inspections
Permit Description: MMR Fiber-- SEGMENT 3 (Plan Phase 3) - THIS JOB PLACES 5100' OF (2)2" AND (4)7-WAY HDPE CONDUITS ALONG N SILVERBELL RD. METHOD OF CONSTRUCTION TO BE DIRECTIONAL BORING AND/OR DIGGING/TRENCHING DEPENDING ON AREA AND ENGINEERING DRAWINGS. POSSIBLE PITS AND PLACING HANDHOLES. FIBER CABLE TO BE PLACED IN CONDUIT LOOPING INTO HANDHOLE. (DTM Note-- Refer to Attachments for Related Permit from Contractor)
Total Outstanding Activity Conditions - 4
| Date | Name |
|---|---|
| 11/05/2026 | City of Tucson Right of Way Only ROW Permit is only allowed for work within City of Tucson Right of Way |
| 11/05/2026 | Pre-Activity Meeting w/Inspections Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. |
| 11/05/2026 | Traffic control set-up approved between 9AM - 3:30PM |
| 11/05/2026 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
Completed Inspections
Permit Status: Inspections
Permit Number: TR-UTL-0726-01117
Permit Description: MMR Fiber-- SEGMENT 3 (Plan Phase 3) - THIS JOB PLACES 5100' OF (2)2" AND (4)7-WAY HDPE CONDUITS ALONG N SILVERBELL RD. METHOD OF CONSTRUCTION TO BE DIRECTIONAL BORING AND/OR DIGGING/TRENCHING DEPENDING ON AREA AND ENGINEERING DRAWINGS. POSSIBLE PITS AND PLACING HANDHOLES. FIBER CABLE TO BE PLACED IN CONDUIT LOOPING INTO HANDHOLE. (DTM Note-- Refer to Attachments for Related Permit from Contractor)
Total Completed Inspections - 2
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/17/2026 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 11/17/2026 | Required: Start Work Notice - Notify your DTM Inspector of your work start date. Notification only; you will be contacted if a Pre-Activity Meeting is needed. | Passed |