Permit Details

Status:
Complete
Type:
Right-of-Way (ROW)
Address:
165 S LINDA AV
Address NEW:
165 S LINDA AV
Apply Date:
04/11/2023
Applicant:
DANNY COCOA
Description:
Install Fiber and Conduit Pathway. 4-days Congress Crossing by Directional Bore. 25-days for Linda Ave conduit install by trench on east side shoulder. 2-days for aerial Cable over lash.

Permit Reviews

Permit Number - TR-ROW-0423-00625
Permit Status: Complete
Permit Description: Install Fiber and Conduit Pathway. 4-days Congress Crossing by Directional Bore. 25-days for Linda Ave conduit install by trench on east side shoulder. 2-days for aerial Cable over lash.
Start Date Submittal Complete Date Status  
04/13/2023 RIGHT-OF-WAY REVIEW v.1 04/21/2023 REQUIRES RESUBMIT Review Details
04/28/2023 RIGHT-OF-WAY REVIEW v.2 05/04/2023 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TR-ROW-0423-00625
Permit Status: Complete
Permit Description: Install Fiber and Conduit Pathway. 4-days Congress Crossing by Directional Bore. 25-days for Linda Ave conduit install by trench on east side shoulder. 2-days for aerial Cable over lash.
Total Outstanding Activity Conditions - 4
Date Name
04/20/2023 This project is located in an Archaeological Sensitivity Zone. An Archaeological Monitor hired by the permit applicant is required to be on-site during any digging, unless a waiver is issued. Monitoring reports are to be submitted to Historic Preservation Office, City of Tucson, P.O. Box 27210, Tucson, AZ 85726.** Please contact Jodie Brown at Jodie.Brown@tucsonaz.gov with any questions.
04/20/2023 Bus Stop/Route
04/20/2023 Traffic control set-up approved between 9AM - 3:30PM
04/20/2023 Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area.

Completed Inspections

Permit Status: Complete
Permit Number: TR-ROW-0423-00625
Permit Description: Install Fiber and Conduit Pathway. 4-days Congress Crossing by Directional Bore. 25-days for Linda Ave conduit install by trench on east side shoulder. 2-days for aerial Cable over lash.
Total Completed Inspections - 1
Date Description Inspector Results Comments
06/20/2023 TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting Passed