Permit: TR-PIA-0623-00023
Permit Details
Status:
Complete
Type:
Private Improvement Agreement (PIA)
Address:
7345 E VALENCIA RD
Address NEW:
7345 E VALENCIA RD
Apply Date:
06/07/2023
Applicant:
German Valenzuela
Description:
Offsite Improvement Plans for BD Project Pueblo on Valencia Road east of Kolb Road - includes new business entrance, ADA Ramps, Sidewalk, Curb, Asphalt, and 4 x 24" RCP drainage.
Permit Reviews
Permit Number - TR-PIA-0623-00023
Permit Status: Complete
Permit Description: Offsite Improvement Plans for BD Project Pueblo on Valencia Road east of Kolb Road - includes new business entrance, ADA Ramps, Sidewalk, Curb, Asphalt, and 4 x 24" RCP drainage.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/31/2023 | PRIVATE IMPROVEMENT AGREEMENT REVIEW v.2 | 08/07/2023 | APPROVED |
| 07/10/2025 | PRIVATE IMPROVEMENT AGREEMENT REVIEW v.1 | 08/07/2025 | APPROVED |
| 06/07/2023 | PRIVATE IMPROVEMENT AGREEMENT REVIEW v.1 | 06/27/2023 | REQUIRES RESUBMIT |
| 03/12/2025 | PRIVATE IMPROVEMENT AGREEMENT REVIEW REVISION v.1 | 04/24/2025 | APPROVED |
Outstanding Inspections
Permit Status: Complete
Permit Number: TR-PIA-0623-00023
Permite Description: Offsite Improvement Plans for BD Project Pueblo on Valencia Road east of Kolb Road - includes new business entrance, ADA Ramps, Sidewalk, Curb, Asphalt, and 4 x 24" RCP drainage.
Total Outstanding Inspections - 4
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/22/2024 | TRSP - PIA - Materials - Testing/Sampling | N/A | Partial Pass | AB tests are being requested for Monday, November 25th at Noon. |
| 11/25/2024 | TRSP - PIA - Backfill - Placement/Compaction | N/A | Complete (Recurring) | |
| 11/26/2024 | TRSP - PIA - Concrete - Subgrade/forms/rebar/place | N/A | Complete (Recurring) | Concrete sampling is done every 50 yards. This pour was 10 yards; therefore, another sample will not be needed until possibly when sidewalk is poured. |
| 12/05/2024 | TRSP - PIA - Miscellaneous/Unscheduled | N/A | Partial Pass | The Valencia entrance is still pending to be paved at this time. Paving began at Kolb Loop entrance. |
Completed Inspections
Permit Status: Complete
Permit Number: TR-PIA-0623-00023
Permit Description: Offsite Improvement Plans for BD Project Pueblo on Valencia Road east of Kolb Road - includes new business entrance, ADA Ramps, Sidewalk, Curb, Asphalt, and 4 x 24" RCP drainage.
Total Completed Inspections - 8
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/21/2024 | TRSP - PIA - Pre-Construction Meeting | Passed | ||
| 10/09/2024 | TRSP - PIA - Drainage - Pipe Installation/Removal | Passed | ||
| 12/04/2024 | TRSP - PIA - AB Placement | Passed | ||
| 03/17/2025 | TRSP - PIA - Concrete - Subgrade/forms/rebar/place | Passed | ||
| 05/05/2025 | TRSP - PIA - Miscellaneous/Unscheduled | Passed | Handrail inspection at Valencia entrance. | |
| 07/01/2025 | TRSP - PIA - Signage/Striping Final | Passed | Traffic Engineering Technician Dean Mullaney | |
| 06/08/2026 | TRSP - PIA - Striping/Signs Warranty | Passed | Dean Mullaney Traffic Engineering Tech - Currently your Traffic Engineering obligation to the Private Improvement Agreement contract has been adequately met and approved. Currently your Traffic Engineering obligation to the Private Improvement Agreement contract has been adequately met and approved. Dean Mullaney - Traffic Engineering Technician Currently your Traffic Engineering obligation to the Private Improvement Agreement contract has been adequately met and approved. Dean Mullaney Traffic Engineering Technician Dean Mullaney Traffic Engineering Technician Currently your Traffic Engineering obligation to the Private Improvement Agreement contract has been adequately met and approved. Currently your Traffic Engineering obligation to the Private Improvement Agreement contract has been adequately met and approved. Dean Mullaney Traffic Engineering Technician Dean Mullaney - Traffic Engineering Technician - The warranty obligation to the Private Improvement Agreement contract has been adequately met and approved. |
|
| 06/02/2026 | TRSP - PIA - Engineering Final - Completion of PIA Work (Final Lot Release/Acceptance) | Passed | One-year warranty inspection passed completely without any punch list items needing to be addressed. |