Permit: TD-DEV-1224-00342
Permit Details
Status:
Complete
Type:
Development Package
Address:
1603 S VAN BUREN AV
Address NEW:
1603 S VAN BUREN AV
Apply Date:
12/13/2024
Applicant:
David Evans
Description:
Multi-family development
Permit Reviews
Permit Number - TD-DEV-1224-00342
Permit Status: Complete
Permit Description: Multi-family development
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 12/17/2024 | DEVELOPMENT PACKAGE NEW v.1 | 02/25/2025 | REQUIRES RESUBMIT |
| 03/20/2025 | DEVELOPMENT PACKAGE NEW v.2 | 04/10/2025 | APPROVED |
Conditions
Permit Number - TD-DEV-1224-00342
Permit Status: Complete
Permit Description: Multi-family development
| Date | Description | Comments |
|---|---|---|
| 10/02/2025 | CRWHPLAN NEEDS TO BE CREATED PRIOR TO CLOSEOUT |
Outstanding Inspections
Permit Status: Complete
Permit Number: TD-DEV-1224-00342
Permite Description: Multi-family development
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/21/2025 | ENGR Paving | N/A | Partial Pass | AB is proper depth and slopes, pending compaction of 100% or greater, site is okay to pave. |
Completed Inspections
Permit Status: Complete
Permit Number: TD-DEV-1224-00342
Permit Description: Multi-family development
Total Completed Inspections - 8
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/06/2025 | PDSD Engineering Division Pre-Construction SITE | Passed | informed the contractor that he needed all his test results on the compaction subgrade AB grade, and they will be looking at all the basins and the rip rap, | |
| 08/14/2025 | Consultation SITE | Passed | Site walk to access progress: 1. Install remaining scuppers. 2. Correct safety issue on North wall; top course is loose. 3. Ensure compaction of sub-grade (95%) and AB (100%) as well as positive drainage from parking lot. 4. Clear vegetation from sidewalk space (width of sidewalk and 84" high) 5. Curb cut to open driveway to 24' |
|
| 10/10/2025 | ENGR Paving | Passed | Asphalt is complete in accordance with approved plans. Striping is complete and in accordance with approved plans. Drainage requirements and ADA requirements have been met. | |
| 10/14/2025 | COT - ENGR - Signage Final | Passed | ADA parking sign is in place and correct. | |
| 10/15/2025 | ENGR Engineering Final | Passed | Site is complete in accordance with approved plans. | |
| 10/15/2025 | LAND Landscape Appearance & Function Final | Passed | Landscaping is good. | |
| 10/14/2025 | Passed | Sidewalks and flatwork are complete within tolerance and in accordance with approved plans. | ||
| 10/14/2025 | Passed | Site striping is complete and in accordance with approved plans. |