Permit Details

Status:
Complete
Type:
Development Package
Address NEW:
1603 S VAN BUREN AV
Apply Date:
12/13/2024
Applicant:
David Evans
Description:
Multi-family development

Permit Reviews

Permit Number - TD-DEV-1224-00342
Permit Status: Complete
Permit Description: Multi-family development
Start Date Submittal Complete Date Status  
12/17/2024 DEVELOPMENT PACKAGE NEW v.1 02/25/2025 REQUIRES RESUBMIT Review Details
03/20/2025 DEVELOPMENT PACKAGE NEW v.2 04/10/2025 APPROVED Review Details

Conditions

Permit Number - TD-DEV-1224-00342
Permit Status: Complete
Permit Description: Multi-family development
Date Description Comments
10/02/2025 CRWHPLAN NEEDS TO BE CREATED PRIOR TO CLOSEOUT

Outstanding Inspections

Permit Status: Complete
Permit Number: TD-DEV-1224-00342
Permite Description: Multi-family development
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
08/21/2025 ENGR Paving N/A Partial Pass AB is proper depth and slopes, pending compaction of 100% or greater, site is okay to pave.

Completed Inspections

Permit Status: Complete
Permit Number: TD-DEV-1224-00342
Permit Description: Multi-family development
Total Completed Inspections - 8
Date Description Inspector Results Comments
05/06/2025 PDSD Engineering Division Pre-Construction SITE Passed informed the contractor that he needed all his test results on the compaction subgrade AB grade, and they will be looking at all the basins and the rip rap,
08/14/2025 Consultation SITE Passed Site walk to access progress:
1. Install remaining scuppers.
2. Correct safety issue on North wall; top course is loose.
3. Ensure compaction of sub-grade (95%) and AB (100%) as well as positive drainage from parking lot.
4. Clear vegetation from sidewalk space (width of sidewalk and 84" high)
5. Curb cut to open driveway to 24'
10/10/2025 ENGR Paving Passed Asphalt is complete in accordance with approved plans. Striping is complete and in accordance with approved plans. Drainage requirements and ADA requirements have been met.
10/14/2025 COT - ENGR - Signage Final Passed ADA parking sign is in place and correct.
10/15/2025 ENGR Engineering Final Passed Site is complete in accordance with approved plans.
10/15/2025 LAND Landscape Appearance & Function Final Passed Landscaping is good.
10/14/2025 Passed Sidewalks and flatwork are complete within tolerance and in accordance with approved plans.
10/14/2025 Passed Site striping is complete and in accordance with approved plans.

Documents

File Name Document Type  
2_DEVELOPMENT PACKAGE FOR 1603 S VAN BUREN AV_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW