Permit: TD-DEV-1023-00413
Permit Details
Apply Date:
10/05/2023
Applicant:
Bruce Paton
Description:
*Revision #1 (site modifications) started 5/14/2024* New Day Care Facility, 9,130 SF Building
Permit Reviews
Permit Number - TD-DEV-1023-00413
Permit Status: Inspections
Permit Description: *Revision #1 (site modifications) started 5/14/2024* New Day Care Facility, 9,130 SF Building
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/03/2024 | DEVELOPMENT PACKAGE NEW v.2 | 06/03/2024 | APPROVED |
10/06/2023 | DEVELOPMENT PACKAGE NEW v.1 | 11/17/2023 | REQUIRES RESUBMIT |
05/14/2024 | DEVELOPMENT PACKAGE NEW v.1 | 05/30/2024 | REQUIRES RESUBMIT |
12/07/2023 | DEVELOPMENT PACKAGE NEW v.2 | 02/01/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TD-DEV-1023-00413
Permit Status: Inspections
Permit Description: *Revision #1 (site modifications) started 5/14/2024* New Day Care Facility, 9,130 SF Building
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
01/31/2024 | Prior to project being finalized applicant must provide a recorded Lot Combination must be provided |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TD-DEV-1023-00413
Permite Description: *Revision #1 (site modifications) started 5/14/2024* New Day Care Facility, 9,130 SF Building
Total Outstanding Inspections - 5
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/26/2024 | PDSD Engineering Division Pre-Construction SITE | N/A | Failed | |
10/01/2024 | COT - ENGR - Stormwater | N/A | Partial Pass | The catch basin number two on the northwest side of the building is good to pour. The light pole foundations are good to poor. |
01/14/2025 | SITE | N/A | Canceled | |
10/09/2024 | ENGR - Drainage Structures | N/A | Partial Pass | Good to backfill the CMP pipe catch basin. And backfill the 8 inch downspout drained that goes into the storm drain |
01/29/2025 | ENGR Paving | N/A | Partial Pass | Will check asphalt again after completion and test results have come in. |
Completed Inspections
Permit Status: Inspections
Permit Number: TD-DEV-1023-00413
Permit Description: *Revision #1 (site modifications) started 5/14/2024* New Day Care Facility, 9,130 SF Building
Total Completed Inspections - 3
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/26/2024 | SITE - Stormwater Follow-up | Passed | ||
01/24/2025 | ENGR - Drainage Structures | Passed | bollards in front of the vinyl fence in front of the play area were looked at today, 3’ in depth. 1 in front of each panel. | |
01/29/2025 | ENGR Grading Final | Passed | Grading compaction at 100% in 6 areas. landscape wh and basins are ready and all sidewalk areas |