Permit Details

Status:
Approved
Type:
Development Package
Apply Date:
08/13/2024
Applicant:
Andie Hemmah
Description:
Rev 1 - sidewalk, parking, water, started 09.12.2025** 3.42 ac park amenities with splash pad, playground, parking lot, and associated pedestrian paths and infrastructure in Common Area "B" on La Escalera Phase 1.

Permit Reviews

Permit Number - TD-DEV-0824-00231
Permit Status: Approved
Permit Description: Rev 1 - sidewalk, parking, water, started 09.12.2025** 3.42 ac park amenities with splash pad, playground, parking lot, and associated pedestrian paths and infrastructure in Common Area "B" on La Escalera Phase 1.
Start Date Submittal Complete Date Status  
09/12/2025 DEVELOPMENT PACKAGE NEW REVISION v.1 10/21/2025 APPROVED Review Details
01/23/2025 DEVELOPMENT PACKAGE NEW v.3 04/03/2025 REQUIRES RESUBMIT Review Details
04/04/2025 DEVELOPMENT PACKAGE NEW v.4 05/05/2025 APPROVED Review Details
08/23/2024 DEVELOPMENT PACKAGE NEW v.2 09/27/2024 REQUIRES RESUBMIT Review Details
08/15/2024 DEVELOPMENT PACKAGE NEW v.1 08/23/2024 REQUIRES RESUBMIT Review Details

Outstanding Inspections

Permit Status: Approved
Permit Number: TD-DEV-0824-00231
Permite Description: Rev 1 - sidewalk, parking, water, started 09.12.2025** 3.42 ac park amenities with splash pad, playground, parking lot, and associated pedestrian paths and infrastructure in Common Area "B" on La Escalera Phase 1.
Total Outstanding Inspections - 5
Last Inspection Date Description Inspector Results Comments
07/22/2025 N/A Partial Pass Okay to backfill up to where emitter elbow needs to be placed. Compact backfill that is under Flatwork.
09/26/2025 Consultation SITE N/A Partial Pass Met with engineer of record to discuss non-compliant slopes. will have entire sidewalk network checked and follow back up. Additional handrail and area modifications will be performed to minimize panel replacement.
10/27/2025 ENGR Paving N/A Partial Pass 10/27/25
Parking lot for Park off of Escalera. Plans still not approved. I checked depths and slope, Good for 3" AC and it will all drain to curb cuts to basin. Contractor says Subgrade compaction tested at 95% and ABC was 100%. Submit reports to the portal. ADA parking ok but one aisle is close to 2% I notified contractor. Pavers will have to be careful to make aisle comply. Ok To pave. Scheduled for Nov. 11 along with roadway.
08/18/2025 N/A Partial Pass 9/9/25
Header curb along other half of wood chip play area with rebar is correct. OK to pour the header.

The curb ramp with the island at the north west side of the parking area should have a curb cut in the planter as shown in the plans. The header along the edge of the ramp should slope down to the curb cut at grade with sidewalk ramp, preventing a tripping hazard. Do not pour this as it is now formed.
07/28/2025 N/A Not Applicable 7/28/25
Junior from Borderland consulted with me about how to coordinate inspection for putting in approximately 275 ft of 2’ copper pipe. It is potable water that will run about 9’ from the water main over to the water meter for the splash pad. Water will make the connection to the main later. 2” pipe will be in poly wrap. I can be back out late morning on Wednesday to check it. Call in inspection for Wednesday.

Completed Inspections

Permit Status: Approved
Permit Number: TD-DEV-0824-00231
Permit Description: Rev 1 - sidewalk, parking, water, started 09.12.2025** 3.42 ac park amenities with splash pad, playground, parking lot, and associated pedestrian paths and infrastructure in Common Area "B" on La Escalera Phase 1.
Total Completed Inspections - 1
Date Description Inspector Results Comments
07/22/2025 PDSD Engineering Division Pre-Construction SITE Passed

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
DRAINAGE STATEMENT_3_V1.PDF DOCUMENTS VIEW
RESPONSE LETTER.PDF DOCUMENTS VIEW