Permit: TD-DEV-0823-00371
Permit Details
Apply Date:
08/23/2023
Applicant:
Elliot Welch
Description:
Restricted Access - Development of new community park featuring small parking area, splash pad, playground, and restroom building.
Permit Reviews
Permit Number - TD-DEV-0823-00371
Permit Status: Complete
Permit Description: Restricted Access - Development of new community park featuring small parking area, splash pad, playground, and restroom building.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/28/2024 | DEVELOPMENT PACKAGE NEW v.3 | 03/13/2024 | APPROVED |
| 12/13/2023 | DEVELOPMENT PACKAGE NEW v.2 | 01/11/2024 | REQUIRES RESUBMIT |
| 07/30/2026 | AS-BUILT v.1 | 08/10/2026 | APPROVED |
| 08/28/2023 | DEVELOPMENT PACKAGE NEW v.1 | 10/31/2023 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TD-DEV-0823-00371
Permit Status: Complete
Permit Description: Restricted Access - Development of new community park featuring small parking area, splash pad, playground, and restroom building.
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 03/13/2024 | Prior to project being finalized applicant must provide REPLACE THIS SECTION WITH THE REQUIRED DOCUMENT(S). |
Outstanding Inspections
Permit Status: Complete
Permit Number: TD-DEV-0823-00371
Permite Description: Restricted Access - Development of new community park featuring small parking area, splash pad, playground, and restroom building.
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/21/2025 | ENGR Paving | N/A | Partial Pass | I looked at the paving in the parking lot area still needs to be striped. They call me in for a striping inspection later. |
| 03/10/2025 | SITE - Stormwater Follow-up | N/A | Complete (Recurring) | |
| 08/05/2025 | Consultation SITE | N/A | Complete (Recurring) | See photo attachments for areas of concern for a soft opening. |
Completed Inspections
Permit Status: Complete
Permit Number: TD-DEV-0823-00371
Permit Description: Restricted Access - Development of new community park featuring small parking area, splash pad, playground, and restroom building.
Total Completed Inspections - 7
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/04/2025 | PDSD Engineering Division Pre-Construction SITE | Passed | Pre con was completed after work was well on its way. Several notes with contractor and PM were done and inspection list on upcoming inspections was given to the contractors PM. | |
| 03/10/2025 | SITE - Stormwater Setup and Controls | Passed | All items have been completed. Keep up with the by-weekly inspection starting from this point until completion. | |
| 04/10/2025 | For trash and recycling enclosures | Passed | Contractor is installing the rebar for the floor and the apron for the trash enclosure. They’re not quite ready. Superintendent inform me that he would send me photos when it’s completed. | |
| 08/25/2025 | ENGR Engineering Final | Passed | Sidewalk repairs to be completed as warranty work per Parks PM | |
| 08/20/2025 | Passed | Damaged sidewalk panels approved to be replaced as warranty item by Parks | ||
| 08/20/2025 | LAND Landscape Appearance & Function Final | Passed | Landscaping accepted by Parks | |
| 08/20/2025 | Passed | Irrigation passed by Parks |