Inspection History Details
Inspection Status: Partial Pass
Inspection History: LAND Landscape Appearance & Function Final
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/11/2025 | LAND Landscape Appearance & Function Final | Partial Pass | Site Landscape Comments: 1. Build up the edges of the stabilized decomposed granite pathway with additional desert cobble to try and avoid washout/erosion of the decomposed granite pathway during a significant rain event. 2. Add desert cobble at the scupper outlet near the bench on the west side of the site for erosion control. 3. Repair the irrigation leak/break next to the concrete sidewalk at the east of the restroom facility. 4. Complete the eastern section of the stabilized decomposed granite pathway. Use the same method to hold the decomposed granite in place by placing desert cobble along the edges at a higher elevation than the pathway to hold the pathway in place during heavy rain events. |
|
| 08/20/2025 | LAND Landscape Appearance & Function Final | Passed | Landscaping accepted by Parks |