Permit: TD-DEV-0625-00157
Permit Details
Status:
Inspections
Type:
Development Package
Address:
1135 W MIRACLE MILE
Address NEW:
1135 W MIRACLE MILE
Apply Date:
06/06/2025
Applicant:
Alejandro Higuera
Description:
Restricted Record - Phase 2; New 4-story, 58-unit Multi-family development on western half of parcel
Permit Reviews
Permit Number - TD-DEV-0625-00157
Permit Status: Inspections
Permit Description: Restricted Record - Phase 2; New 4-story, 58-unit Multi-family development on western half of parcel
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/09/2025 | DEVELOPMENT PACKAGE NEW v.1 | 07/08/2025 | REQUIRES RESUBMIT |
| 01/02/2026 | DEVELOPMENT PACKAGE NEW v.5 | 01/13/2026 | APPROVED |
| 08/26/2025 | DEVELOPMENT PACKAGE NEW v.2 | 09/08/2025 | REQUIRES RESUBMIT |
| 09/29/2025 | DEVELOPMENT PACKAGE NEW v.3 | 10/17/2025 | REQUIRES RESUBMIT |
| 12/22/2025 | DEVELOPMENT PACKAGE NEW v.4 | 12/30/2025 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TD-DEV-0625-00157
Permit Status: Inspections
Permit Description: Restricted Record - Phase 2; New 4-story, 58-unit Multi-family development on western half of parcel
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 10/17/2025 | CRWHPLAN NEEDS TO BE CREATED PRIOR TO CLOSEOUT |
Conditions
Permit Number - TD-DEV-0625-00157
Permit Status: Inspections
Permit Description: Restricted Record - Phase 2; New 4-story, 58-unit Multi-family development on western half of parcel
| Date | Description | Comments |
|---|---|---|
| 01/13/2026 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 02/09/2026 | Dust Control/Air Quality Permit is Required. (Utilized with DP's & TP's) |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TD-DEV-0625-00157
Permite Description: Restricted Record - Phase 2; New 4-story, 58-unit Multi-family development on western half of parcel
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/18/2026 | SITE - Sign Footer/Setback/Excavation Layout/Rebar | N/A | Not Applicable | |
| 07/01/2026 | ENGR - Drainage Structures | N/A | Partial Pass | Contractor wanted us to look at the 12'x12" Mirafi wrapped Rock Pocket that runs along the Retaining wall on west side of site before it is covered. Wall is on the building permit and is being inspected by Bldg and 3rd party. Rock pocket is correct to plan. Submit RFI of drainage through wall to PDSD Engineering Dept. |
Completed Inspections
Permit Status: Inspections
Permit Number: TD-DEV-0625-00157
Permit Description: Restricted Record - Phase 2; New 4-story, 58-unit Multi-family development on western half of parcel
Total Completed Inspections - 2
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/09/2026 | PDSD Engineering Division Pre-Construction SITE | Passed | All SWPPP is being handled by third-party and stormwater initial is being scheduled for Monday. No construction activities will be started other than sweat BMP's until the stormwater initial is completed. Good benchmark is at North East corner of site next to water meter.. |
|
| 04/13/2026 | SITE - Stormwater Setup and Controls | Passed | SWWWP Board is not yet in place- It is in process and will be on Fence at Miracle Mile Entrance ASAP. Earthworks Environmental Is 3rd Party. ON SWPPP Board put Address, Site Name, ID # and SWPPP Contact information. BMP's in place. NOI Is good. SWPPP binder is being printed and will be placed in waterproof box ASAP that is now next to construction entrance. Ensure no dirty water leaves site or any dirt gets in the roadway. Okay to start Grading. |